Commercial General Building work permitted April 29, 2025, with 8 permits through February 19, 2026, declaring $71,362,282 of work. Contractor on record: Cranshaw Construction.
Interior fitout within the building on floors 7,6,5,4,3,2,1 and the basement level. Includes new walls, flooring, ceilings, mechanical systems, electrical systems, plumbing systems and fire protection systems for laboratory and office space.
Cambridge permit records name Cranshaw Construction and The Richmond Group as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
8 permits issued Apr 29 – Feb 19, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jan 16 | #1195817 Building: Alteration and Addition Renovation to the 1st floor existing lobby space. |
Commercial and multifamily, biggest first.
Status: Active
| Cranshaw Construction |
| $1.3M |
| applied Nov 17 | #1190527 Building: Alteration and Addition Scope of work is on lower level and partial 1st floor space only. Work is limited to only include new elevator from lower level to first floor (only 2 stop - for delivery/logistics), small chemical/hazardous storage rooms to support the Intellia project fit-out that is under construction and minor… Status: Active | The Richmond Group | $2.8M |
| applied Oct 16 | #1187356 Building: Alteration and Addition This is an interior renovation of an existing building of the partial floors of the basement, first floorand full ninth floor to a new fitness center and conferencing center. Status: Active | Cranshaw Construction | $16.7M |
| applied Aug 11 | #1178454 Building: Alteration and Addition Interior fitout within the building on floors 7,6,5,4,3,2,1 and the basement level. Includes new walls, flooring, ceilings, mechanical systems, electrical systems, plumbing systems and fire protection systems for laboratory and office space. Status: Active | The Richmond Group | $41.6M |
| applied Jul 7 | #1173017 Building: Alteration and Addition Interior demolition within the building on floors 7,6,4,3,2,1 and the basement level. Includes demolition of walls, flooring and ceilings, mechanical systems, electrical systems, plumbing systems and fire protection systems. Some portions of the existing floor plates will remain as constructed… Status: Active | The Richmond Group | $2.7M |
| applied May 28 | #1167164 Building: Alteration and Addition Interior tenant fit up of existing space consisting of new, non-structural wall partitions, upgraded MEP / FP systems ( electrical wiring, lighting, HVAC systems and controls, plumbing fixtures and sprinkler branch lines), new wall and floor finishes throughout. Status: Complete | Cranshaw Construction | $5.3M |
| applied May 19 | #1165800 Building: Alteration and Addition Interior demolition of existing non-structural elements including wall partitions, existing flooring and wall finishes, mechanical systems including HVAC duct/piping, Plumbing piping and electrical wiring/light fixtures. Status: Complete | Cranshaw Construction | $155K |
| applied Mar 31 | #1158076 Building: Alteration and Addition Stair removal, infill floor openings on 8th and 9th floor with steel, metal deck and concrete. Miscellaneous finishes and MEP around infills. Status: Complete | The Richmond Group | $807K |