How long commercial permits take in Norfolk, by trade
Median days from application to issue and median declared value, commercial and multifamily permits issued July 31, 2026 – October 29, 2026.
| Trade | Permits | Median days to issue | Median declared value |
|---|---|---|---|
| Electrical | 174 | 1 | $6K |
| HVAC / Mechanical | 132 | 1 | $8.9K |
| Building | 102 | 37 | $65K |
| Plumbing | 97 | 1 | $6.3K |
| Fire protection | 86 | 13 | $9.3K |
| Signs | 47 | 13 | $3.5K |