Get Promultifamily project · Washington DC, DC
Multifamily General Building, Electrical, Elevator, Hvac/Mechanical work permitted June 4, 2025, with 4 permits through January 13, 2026.
Historic Districts FOR ELEVATOR REVIEW ONLY***INTERIOR WORK ONLY***REPAIR & REPLACE THE BELOW ITEMS IN THE E.M.R***Replace the elevator mainline disconnects, Replace the 110v cab light disconnects, Replace lights and GFIs in EMR and Pits, Replace elevator pit access ladders, RETAIN THE EXISTING ELEVATOR PIT SUMP PUMP. Replace HVAC.
Washington DC’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
4 permits issued Jun 4 – Jan 13, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#M2601249 SUPPLEMENTAL · MECHANICAL Status: Permit Issued |
Commercial and multifamily, biggest first.
| — |
#EA2502185 SHOP DRAWING · ELEVATOR - ALTERATION Modernization of 3 elevators to include. New gearless machine and hoist ropes with secondary emergency brake, new controller, new governors and governor ropes, new governor tension sheaves, new cab interiors, new fixtures (COP, Hall buttons and lanterns), new door operator, new car door and track… Status: Permit Issued | Not published | — |
#B2504329 CONSTRUCTION · ALTERATION AND REPAIR Historic Districts FOR ELEVATOR REVIEW ONLY***INTERIOR WORK ONLY***REPAIR & REPLACE THE BELOW ITEMS IN THE E.M.R***Replace the elevator mainline disconnects, Replace the 110v cab light disconnects, Replace lights and GFIs in EMR and Pits, Replace elevator pit access ladders, RETAIN THE EXISTING… Status: Permit Issued | Not published | — |
#E2509512 SUPPLEMENTAL · ELECTRICAL Status: Permit Issued | Not published | — |