Get ProEvery project in every city · from $79/mo
Get Procommercial project · Washington DC, DC
Commercial General Building, Electrical, Elevator, Hvac/Mechanical, Plumbing work permitted February 12, 2025, with 14 permits through October 26, 2026.
THIS PROJECT CONSISTS OF AN INTERIOR OFFICE RENOVATION ON THE 5TH FLOOR OF THE EXISTING DC WATER HEADQUARTERS. THE SCOPE OF WORK INCLUDES RECONFIGURATION OF EXISTING OFFICE AND CONFERENCE ROOM SPACES, INSTALLATION OF A NEW GLASS PARTITION SYSTEM, RELOCATION OF EXISTING FURNITURE, NEW FURNITURE INSTALLATION WHERE INDICATED, AND ASSOCIATED ARCHITECTURAL, MECHANICAL, ELECTRICAL, AND FIRE ALARM MODIFICATIONS. NO STRUCTURAL WORK IS INCLUDED
Washington DC’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
14 permits issued Feb 12 – Oct 26, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
Commercial and multifamily, biggest first.
#B2608468
CONSTRUCTION · ALTERATION AND REPAIR
THIS PROJECT CONSISTS OF AN INTERIOR OFFICE RENOVATION ON THE 5TH FLOOR OF THE EXISTING DC WATER HEADQUARTERS. THE SCOPE OF WORK INCLUDES RECONFIGURATION OF EXISTING OFFICE AND CONFERENCE ROOM SPACES, INSTALLATION OF A NEW GLASS PARTITION SYSTEM, RELOCATION OF EXISTING FURNITURE, NEW FURNITURE…
Status: Permit Issued
| Not published |
| — |
#B2507914 CONSTRUCTION · ADDITION ALTERATION REPAIR THE PROJECT INVOLVES (1) CONSTRUCTING A PATH CONNECTING THE SOUTH DECK TO A THREE-SIDED GAZEBO, AND (2) INSTALLING BAR RAILING ALONG EXISTING TERRACE. FOR THE GAZEBO, DRAWINGS ARE PROVIDED FOR THE CUSTOM GAZEBO INCLUDING FOUNDATIONS, VERTICAL AND HORIZONTAL MEMBERS, AND A BENCH. THE GAZEBO ROOF… Status: Permit Issued | Not published | — |
#E2608768 SUPPLEMENTAL · ELECTRICAL Status: Completed | Not published | — |
#B2603194 CONSTRUCTION · ALTERATION AND REPAIR REPLACE THE EXISTING FIRE ALARM DIALER WITH NEW CELL DIALER. Status: Permit Issued | Not published | — |
#B2508118 CONSTRUCTION · ALTERATION AND REPAIR THE PROJECT INVOLVES CONSTRUCTING A TURNSTYLE AND ADA GATE IN THE EXISTING WALL TO PROVIDE ACCESS TO YARDS PARK INCLUDING THE ADA RAMP NECESSARY TO ACCESS THE GATES. ELECTRICAL WORK INCLUDES RELOCATION OF EXISTING CONDUITS LOCATED ON THE FACE OF THE EXISTING WALL TO MAKE WAY FOR THE ADA RAMP AND… Status: Permit Issued | Not published | — |
#E2608469 SUPPLEMENTAL · ELECTRICAL Status: Permit Issued | Not published | — |
#P2505622 SUPPLEMENTAL · PLUMBING AND GAS Status: Permit Issued | Not published | — |
#ER2501196 SHOP DRAWING · ELEVATOR - REPAIR Replaced damaged belt and sheave on Car 2 Status: Permit Issued | Not published | — |
#E2506296 SUPPLEMENTAL · ELECTRICAL Status: Completed | Not published | — |
#M2502067 SUPPLEMENTAL · MECHANICAL Status: Completed | Not published | — |
#M2501925 SUPPLEMENTAL · MECHANICAL Status: Completed | Not published | — |
#P2504437 SUPPLEMENTAL · PLUMBING AND GAS Status: Permit Issued | Not published | — |
#E2505282 SUPPLEMENTAL · ELECTRICAL Status: Completed | Not published | — |
#B2500450 CONSTRUCTION · ALTERATION AND REPAIR This project is interior renovation for DC Water, located at 1385 canal st se washington dc 20003. It involves a 1897 sf project area within a total of 145027 sf. The scope of work includes providing architectural (non-structural partitions only), electrical, mechanical, and plumbing plans. Status: Completed | Not published | — |