Commercial General Building work permitted September 23, 2025, with 13 permits through October 22, 2026, declaring $2,814,696 of work. Contractor on record: Build Group Inc..
addition of new enclosed exit stair extending from level b to 2;(n) elevator erviing lvl 1,1m,2,2m,3.construction & assoc demo for the partial reframing of mezz.mod to steel bracing frams and seismic bracing.(n) partitions,elevator shaft, exit stair.new ada baths, lighting & finishes.
San Francisco permit records name Build Group Inc. and Rrs Fire Alarm Inc Dba California Fire D as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
The contractor on 1 permit issued in the last 30 days is included with Pro.
See the contractor13 permits issued Sep 23 – Oct 22, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|
| applied Jul 31 | #202607315926 otc alterations permit 3rd fl, mep for pa 202602125890 Status: Issued | Contractor with Pro | $50K |
| applied May 18 | #202603187866 additions alterations or repairs revision to core & shell pa# 202505126265: framing detail @ level 3 elevator penthouse, elevator shaft structural framing, structural strengthening at level 3 underside of north & south roof, modification to restroom at level 2 mezzanine, a switch from a prefabication metal stair to a pre-fab wood Status: Issued | Build Group Inc. | $50K |
| applied Jul 23 | #202607235440 otc alterations permit deferred stair shop drawing submittal per pa# 202505126265. interior stair, structural detail only. Status: Issued | Build Group Inc. | — |
| applied Feb 12 | #202602125890 otc alterations permit 3rd fl arch ti - new non-load bearing partitions, doors & door hardware, interior glazing, ceilings, light fixtures, millwork and associated finishes. mep under separate permit see pa 202505126265 for arch core/shell Status: Issued | Build Group Inc. | $150K |
| applied Apr 1 | #202604018667 otc alterations permit install base station and power supply in storage room 110. install 6 call boxes on basement floor through 3rd floor. riser to be ran up two hour rated enclosure call boxes to be mounted in that enclosure. pots phone line required for communication with ul central station. pots lineto be installed Status: Issued | Rrs Fire Alarm Inc Dba California Fire D | $34.7K |
| applied Feb 9 | #202602095565 otc alterations permit 2/fl- ref 202512192346- includes provide and install 5 fan coil units, run line set from units to heat pumps on the roof Status: Issued | Build Group Inc. | $160K |
| applied Jan 30 | #202601304971 otc alterations permit 1st floor and 1m mep ti: see arch pa # 202510036734. work includes: provide and install 7 fan coil units; condensate piping by plumbing contractor. Status: Issued | Build Group Inc. | $180K |
#202512192346 otc alterations permit level 2 - 2m: scope of work includes construction of new non-load bearing partitions, doors and door + door hardware, interior glazing, ceilings, light fixtures, millwork, and associated finishes. mep under seperate permit. Status: Issued | Build Group Inc. | $150K | |
| applied Nov 12 | #202511129386 otc alterations permit core and shell mep. work includes osa supply unit, restroom exhaust and a riser for future ti permits. ref arch permit #202505126265. Status: Issued | Build Group Inc. | $120K |
| applied Jan 14 | #202601143826 otc alterations permit revision 202505126265- to include the moment frame foundation are necessitated by field verified conditions of tghe (e) footing. (e) footing was found to be too shallow to accomadate the required dowels to resist design uplift forces Status: Issued | Build Group Inc. | — |
| applied Oct 3 | #202510036734 otc alterations permit 1st floor: interior office build-out of level 1 and level2 mezzanine (l1 +lm1). scope includes construction of new non-load bearing partitions, doors, and door hardware, interior glazing ceilings, light fixtures, millwork, and associated finishes. Status: Issued | Build Group Inc. | $150K |
| applied Jun 6 | #202505126265 additions alterations or repairs addition of new enclosed exit stair extending from level b to 2;(n) elevator erviing lvl 1,1m,2,2m,3.construction & assoc demo for the partial reframing of mezz.mod to steel bracing frams and seismic bracing.(n) partitions,elevator shaft, exit stair.new ada baths, lighting & finishes. Status: Issued | Build Group Inc. | $2.1M |
| applied Feb 24 | #202502240930 otc alterations permit front bldg: ab-017. interior non structural demo of non-bearing interior partitions, doors, ceilings, lighting, mech, ductwork, interior finishes Status: Issued | Build Group Inc. | $20K |
In San Francisco, biggest first.