Get ProEvery project in every city · from $79/mo
Get Promultifamily project · San Francisco, CA
Multifamily General Building work permitted November 22, 2024, with 2 permits through September 16, 2025, declaring $97,200 of work. Contractor on record: Firelectric.
replace fire egress stairs in kind in the lightwell due to significant deterioration. no change in orientation. no firewall construction. replace loose bolts in kind in e metal stairs.
San Francisco permit records name Firelectric and Matthew Kelly Construction Inc as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
2 permits issued Nov 22 – Sep 16, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Sep 16 | #202509165353 otc alterations permit upgrade of existing fire alarm system to add 2 panel supply and law frequency sounders in all sleeping areas of the building and to comply with 1103.7.6.1 |
Commercial and multifamily, biggest first.
Status: Complete
| Firelectric |
| $38K |
| applied Nov 19 | #202411195262 otc alterations permit replace fire egress stairs in kind in the lightwell due to significant deterioration. no change in orientation. no firewall construction. replace loose bolts in kind in e metal stairs. Status: Complete | Matthew Kelly Construction Inc | $59.2K |
In San Francisco, biggest first.