Commercial General Building work permitted May 14, 2025, with 21 permits through August 28, 2026, declaring $52,078,067 of work. Contractor on record: Related California Construction Llc.
Get new commercial permits near 94102 or San Francisco, free weekly email
ab-004 priority phase 2c: voluntary & selective renovation of (e) mep systems serving approx 125,400 gsf of the 177,800 gsf of entire (e) bldg. proposed mep design will supplement current arch & struc ti. non-seismic struc work ltd to addition of penthouse rooftop support & anchorage of mech equip.
San Francisco permit records name Related California Construction Llc, Westates Mechanical Corporation Inc and Johnson Controls Fire as the contractors on this project, among 5 contractors in all.
21 permits issued May 14 – Aug 28, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Aug 6 |
Commercial and multifamily, biggest first.
#202608046055 additions alterations or repairs evacuation for signage for phase 2. no associated increase to student population. Status: Issued |
| Related California Construction Llc |
| $55.6K |
| applied Jun 29 | #202606183575 additions alterations or repairs evacuation signage for phase 1b.no associated increase to student population Status: Issued | Related California Construction Llc | $40.6K |
| applied Feb 25 | #202512292831 additions alterations or repairs ab-004 priority phase 2.1: int ti-construct (n) staff-operated kitchen in basement lvl w/comm cooking eq, food prep area & servery line. students & faculty will have no access to kitchen. install (n) grease interceptor w/in (e) cafeteria & minor arch finish. modification/ext to (e)fa & fs as req. Status: Issued | Related California Construction Llc | $861K |
| applied Nov 26 | #202511260527 additions alterations or repairs phase 2: new ext canopies,partial roof/skylights & column removal on 6/f,resurface payyard,new entry gates,ext stairs & ter serving new sep entry & reno of (e) main entry w/ new canopy.nonstruct-ti's basement kitchen. Status: Issued | Related California Construction Llc | $15M |
#202512292848 additions alterations or repairs ab-004 priority phase 2.2: non-structural int ti-establish staff-operated cafe serving hs students on 6th flr. limited to int arch finishes &typical mep modifications. cafe provide pre-pared, non-cooked food & bev only; no cooking equip, hooods or special ventilation of fp req. student/faculty will Status: Issued | Related California Construction Llc | $180K |
| applied Feb 20 | #202512292849 additions alterations or repairs ab-004 priority phase 2c: voluntary & selective renovation of (e) mep systems serving approx 125,400 gsf of the 177,800 gsf of entire (e) bldg. proposed mep design will supplement current arch & struc ti. non-seismic struc work ltd to addition of penthouse rooftop support & anchorage of mech equip. Status: Issued | Related California Construction Llc | $16.2M |
| applied Mar 6 | #202602276662 additions alterations or repairs mechanical energy compliance update to issued pa# 2025-09-09-4851. previously, the project pursued the prescriptive approach & has switched gears to performance approach for mechanical title-24 building energy compliance. no associated increase to student population. Status: Issued | Related California Construction Llc | — |
| applied Apr 15 | #202604099145 additions alterations or repairs install a complete emergency communications enhancement system (erces) in accordance w/ 2025 california fire code 510 & nfpa 1225 - 2022 edition. Status: Complete | Bobcomm Llc Dba Pacific Das Llc. | $87.4K |
| applied Feb 2 | #202601304951 additions alterations or repairs installation of a new facu in the basement & to upgrade (e) horn / strobe to voice evacuation. this includes addition of remote annunciator, voice evac control panel, update field devices per th enew architectural layout. Status: Complete | Johnson Controls Fire | $380K |
| applied Mar 4 | #202602266630 additions alterations or repairs install a complete emergency responder radio coverage system (errcs) in accordance with 2022 calfire code ss510 and nfpa 1225-2022 edition. Status: Complete | Related California Construction Llc | $120K |
| applied Mar 17 | #202603177752 otc alterations permit remove fire sprinkler coverage from elevator 4 and 5 - machine room, top of shared elevator hoistway, and elevator pit of each elevator Status: Complete | Westates Mechanical Corporation Inc | — |
| applied Feb 11 | #202602115706 additions alterations or repairs fire sprinkler ti refermce building permit#2025-0314-2389. add: 99, relocate 288, changeout 55, total: 439. Status: Complete | Westates Mechanical Corporation Inc | $272K |
| applied Dec 15 | #202512151748 otc alterations permit rev to reconcile architectural floor plans re-issue pa#: 202503172389 (1b) and 202509094851 (1c). 6th floor interior non-structural architectural revision to incorporate(e) storage room apprx 300 sqft. into the adjacent assemply place along with minor interior partition plan adjustments. work is Status: Complete | Related California Construction Llc | $60K |
| applied Sep 24 | #202509094851 additions alterations or repairs ab-004 priority: phase 1c - t.i.: mep upgrades to pa 202503172389. no associated increase to student population. Status: Issued | Related California Construction Llc | $13.5M |
| applied Nov 10 | #202511109273 otc alterations permit basement -ref ti 202503172389- fire sprinkler add 13, relocate 64; demo 7 -total 84 sprinklers Status: Complete | Westates Mechanical Corporation Inc | $52.2K |
| applied Oct 20 | #202510207706 otc alterations permit 300 (e) window replacement - replace (e) steel sash, single-light, non-tempered w/ high performing aluminum windows deisgn w/ tempered, insulated glass & low-e energy efficient coating. same window divisions as (e) but greater energy efficieny & bldg code req.in size opening & safety glazing. Status: Issued | Related California Construction Llc | $3.6M |
| applied Sep 8 | #202509084780 otc alterations permit 4th fl & basement: as built permit. to update location of the devices. no new devices were added. Status: Complete | Johnson Controls Fire | $1.2K |
| applied Jul 16 | #202507160958 otc alterations permit 4/f and basement - fire sprinklers: demo 3, add 15, relocate 32, and changeout 67 (total 114). upsize backflow from 4" to 6". ref permit 202503132189 Status: Complete | Westates Mechanical Corporation Inc | $110K |
| applied Jul 11 | #202507110654 otc alterations permit provide & install (4) smoke detectors, 4 horn strobes, & 2 strobes, relocate/demo (e) devices & new devices as shown on plans. demo (e) existing horn strobes on 4/f. demo 2 door holders/fsd/dd. ref to 202503132189 Status: Complete | Johnson Controls Fire | $8K |
| applied Mar 17 | #202503172389 additions alterations or repairs ab-004 priority:phase 1b: renovate restrooms on floors 1-5.replace (e) toilet partitions w/ proviacy partitions where allwed by (e) fixture layouts.additoinal gender neutral restroom added to basement & 6/f.expand (e) egress stairs #05 from 1-2/f to service basements thru 3/f.add stairs #8 fr 3-6/f. Status: Issued | Cahill Contractors Llc. | $1.2M |
| applied Mar 13 | #202503132189 additions alterations or repairs ab-004 priority: phase 1a:partial interior non-structural t.i. work on the 4/f & basement. provide make-up air using the (e) mehanical system by rerouting ductwork and air diffusers where applicable. no increase to student population. Status: Complete | Cahill Contractors Llc. | $350K |