Commercial General Building work permitted January 17, 2025, with 13 permits through October 23, 2026, declaring $7,107,358 of work. Contractor on record: Guzman Construction Group Inc..
Get new commercial permits near 94109 or San Francisco, free weekly email
(n) entrance to the third floor of the la salle building and remnovation of the interior thrid floor of the la salle building to include non structural demo of interior partitions and finishes and mep systems to be replaced with new. no work in the public right of way and not facing street.
San Francisco permit records name Guzman Construction Group Inc., Corporate Sign Systems and Anderson, Rowe & Buckley, Inc. as the contractors on this project, among 7 contractors in all.
The contractor on 1 permit issued in the last 30 days is included with Pro.
See the contractor13 permits issued Jan 17 – Oct 23, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 23 | #202610239845 otc alterations permit install 6 evacuation maps inside building Status: Issued | Contractor with Pro | $2.9K |
| applied Jan 21 | #202601214204 otc alterations permit revision to pa 202510248084 underpinning method to replace shoring previously approved associated (n) elevator shoring & foundation. ref pa 202312212924. Status: Issued | Guzman Construction Group Inc. | — |
| applied Jul 29 | #202607295709 otc alterations permit temporary ada ramp to provide accessible entrance while elevator work is in progress. ref permit 202312212924 Status: Complete | Guzman Construction Group Inc. | $10K |
| applied Jun 29 | #202606294109 otc alterations permit install 5 evacuation maps inside building. Status: Issued | Corporate Sign Systems | $2.4K |
| applied Feb 9 | #202602095558 otc alterations permit 3rd floor: add upright sprinklers (3). add pendent sprinklers (129). add sidewall sprinklers (12). total- 144. ref permit 2025.1001.6481 Status: Complete | Anderson, Rowe & Buckley, Inc. | $89.5K |
| applied Oct 1 | #202510016481 otc alterations permit (n) entrance to the third floor of the la salle building and remnovation of the interior thrid floor of the la salle building to include non structural demo of interior partitions and finishes and mep systems to be replaced with new. no work in the public right of way and not facing street. Status: Issued | Guzman Construction Group Inc. | $5M |
| applied Oct 24 | #202510248084 otc alterations permit provide soil shoring at (n) elevator shoring + foundation. ref pa 202312212924. Status: Issued | Guzman Construction Group Inc. | — |
| applied Dec 21 | #202312212924 additions alterations or repairs alterations to(e)lobby:demo & const of stairs & ramp,reception desk,guardrails & handrails.(e)(3)story elevator will be installed @ an adjacent location.finishes will be replaced incld paint,ceiling & floor.(n)arch lighting to be provided.mech & elec work limited to upgrades for renov & elevator. Status: Issued | Guzman Construction Group Inc. | $1.6M |
| applied Sep 24 | #202509246012 otc alterations permit provide new (2) duct smoke detectors, (2) remote test stations, and (1) speaker strobe. ref permit 202410213333 Status: Complete | Johnson Controls Fire | $6.3K |
| applied Jul 25 | #202507251609 otc alterations permit to modify existing fire sprinklers to accomodate new ceiling and walls. Status: Complete | Rcm Fire Protection Inc. | $7K |
| applied Oct 21 | #202410213333 otc alterations permit conversion of existing classroom into training room with recovery equipment and an office. Status: Issued | Guzman Construction Group Inc. | $375K |
| applied Jan 13 | #202501067787 additions alterations or repairs 9 smoke detectors, 3 relay module to be provided for elevator modernization. voluntary project. Status: Complete | Pyro-Comm Systems, Inc. | $11.3K |
| applied Jan 17 | #202501178534 otc alterations permit remove existing sprinklers from elevator hoistway & machine room for sffd 2022 ab #2.01 (addendum d) Status: Complete | International Fire Equipment Co Incorpor | $3K |