Get ProEvery project in every city · from $79/mo
Get Procommercial project · San Diego, CA
Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted December 11, 2024, with 7 permits through March 4, 2026, declaring $21,446,208 of work. Contractor on record: BWD.
SERRA MESA: BLDG-MEP: New 5 story above ground parking structure for adjacent to be built apartment building. SCOPE CHANGE: 1/9/2024 -The Applicant is to redesign the garage MOE - The Applicant is to provide a global MOE plan for the garage & adjoining structures; the MOE plan will be reviewed by both the garage & the adjoining structure reviewers. Place a copy of MOE on both projects - The applicant is to provide a phasing plan with garage project resubmittal; after the phasing plan is approved, a copy of the approved phasing plan should be included in the adjoining structure drawings for…
San Diego permit records name BWD, Innovative Fire Protection and Coastal Fire and Integration Systems as the contractors on this project.
7 permits issued Dec 11 – Mar 4, newest first.
In San Diego, biggest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied May 28 | #PMT-3355938 Approval - Construction - Fire Pmt - Suppression Deferred Fire Sprinklers with Plans. PRJ-1060976 Status: Inspection Followup | Innovative Fire Protection | — |
| applied Jul 22 | #PMT-3365383 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarm New Installation with Plans. PRJ-1060976 Status: Inspection Followup | Coastal Fire and Integration Systems | — |
| applied Apr 17 | #PMT-3348858 Approval - Construction - Fire Pmt - Underground Deferred Fire Underground with Plans. PRJ-1060976 Status: Inspection Followup | Innovative Fire Protection | — |
| applied Jun 22 | #PMT-3161322 Plumbing Pmt SERRA MESA: BLDG-MEP: New 5 story above ground parking structure for adjacent to be built apartment building. SCOPE CHANGE: 1/9/2024 -The Applicant is to redesign the garage MOE - The Applicant is to provide a global MOE plan for the garage & adjoining structures; the MOE plan will be reviewed by… Status: Inspection Followup | BWD | — |
| applied Jun 22 | #PMT-3161321 Electrical Pmt SERRA MESA: BLDG-MEP: New 5 story above ground parking structure for adjacent to be built apartment building. SCOPE CHANGE: 1/9/2024 -The Applicant is to redesign the garage MOE - The Applicant is to provide a global MOE plan for the garage & adjoining structures; the MOE plan will be reviewed by… Status: Inspection Followup | BWD | — |
| applied Jun 22 | #PMT-3161318 Building Permit SERRA MESA: BLDG-MEP: New 5 story above ground parking structure for adjacent to be built apartment building. SCOPE CHANGE: 1/9/2024 -The Applicant is to redesign the garage MOE - The Applicant is to provide a global MOE plan for the garage & adjoining structures; the MOE plan will be reviewed by… Status: Inspection Followup | BWD | $21.4M |
| applied Jun 22 | #PMT-3161320 Mechanical Pmt SERRA MESA: BLDG-MEP: New 5 story above ground parking structure for adjacent to be built apartment building. SCOPE CHANGE: 1/9/2024 -The Applicant is to redesign the garage MOE - The Applicant is to provide a global MOE plan for the garage & adjoining structures; the MOE plan will be reviewed by… Status: Inspection Followup | BWD | — |