Commercial Electrical, Mep, Solar work permitted June 2, 2026, with 3 permits through July 18, 2026. Contractor on record: Ian Harrison.
Install new roof-mounted 2.67 kW DC (2.40 kW CEC-AC) solar PV system: (6) Sunplus 445 W modules in one string, (1) Sol-Ark 8K-2P-N hybrid inverter, Tigo module-level rapid shutdown, load-side interconnection via new 50 A breaker in existing SPAN panel (200 A bus / 100 A main). Flush mount on composition shingle roof; no battery, no panel upgrade, no structural alterations. Owner-builder self-install.
San Diego permit records name Ian Harrison, Effect Energy Inc and GR Pro Electric Inc as the contractors on this project.
3 permits issued Jun 2 – Jul 18, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#PMT-3428512 Photovoltaic - SB 379 Install new roof-mounted 2.67 kW DC (2.40 kW CEC-AC) solar PV system: (6) Sunplus 445 W modules in one string, (1) Sol-Ark 8K-2P-N hybrid inverter, Tigo module-level rapid shutdown, load-side interconnection via new 50 A breaker in existing SPAN panel (200 A bus / 100 A main). Flush mount on… Status: Issued |
| Ian Harrison |
| — |
| applied Jun 10 | #PMT-3421231 No-Plan - Residential - Combination Mech/Elec/Plum Installation of a 200A subpanel Status: Closed | Effect Energy Inc | — |
| applied May 29 | #PMT-3419287 No-Plan - Nonresidential/Multifamily - Electrical Status: Closed | GR Pro Electric Inc | — |