Get ProEvery project in every city · from $79/mo
Get Promultifamily project · San Diego, CA
Multifamily General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted October 30, 2024, with 11 permits through March 18, 2026, declaring $524,183 of work. Contractor on record: Pacific Rock.
**Scope Change (07/31/2024)**NORTH PARK: Building, Mechanical, Electrical, and Plumbing permits for converting upper unit in building 1 into 2 units, converting garage in building 2 into ADU 7, remodel existing lower floor unit in building 2 in existing multi family structure. Work to include construction of 1 new 3-story buildings with 6 ADUs attached to the existing building 1.
San Diego permit records name Pacific Rock, Premier Fire Corp and Elite Security & Surveillance as the contractors on this project.
11 permits issued Oct 30 – Mar 18, newest first.
In San Diego, biggest first.
| Issued | Permit | Contractor | Value |
|---|
| applied Jan 29 | #PMT-3399005 Approval - Construction - Fire Pmt - Suppression Deferred Fire Sprinklers with Plans. PRJ-1063819 Status: Inspection Followup | Premier Fire Corp | — |
| applied Jan 29 | #PMT-3399003 Approval - Construction - Fire Pmt - Suppression Deferred Fire Sprinklers with Plans. PRJ-1063819 Status: Inspection Followup | Premier Fire Corp | — |
| applied Oct 16 | #PMT-3381360 Approval - Construction - Fire Pmt - Alarm Deferred fire sprinkler monitoring. PRJ-1063819 Status: Issued | Elite Security & Surveillance | — |
| applied Jul 13 | #PMT-3164865 Electrical Pmt Electrical work for converting upper unit in building 1 into 2 units, converting garage in building 2 into ADU 5, remodel existing lower floor unit in building 2. Work to include construction of 2 new 3-story buildings with 2 ADUs each (2 low income ADUs, and 2 bonus ADUs) Status: Inspection Followup | Pacific Rock | — |
| applied Jul 13 | #PMT-3164864 Mechanical Pmt Mechanical work for converting upper unit in building 1 into 2 units, converting garage in building 2 into ADU 5, remodel existing lower floor unit in building 2. Work to include construction of 2 new 3-story buildings with 2 ADUs each (2 low income ADUs, and 2 bonus ADUs). Status: Inspection Followup | Pacific Rock | — |
| applied Jul 13 | #PMT-3164873 Electrical Pmt Electrical work converting garage in building 2 into ADU 5, remodel existing lower floor unit in building 2. Status: Inspection Followup | Pacific Rock | — |
| applied Jul 13 | #PMT-3164870 Building Permit For converting garage in building 2 into ADU 5, remodel existing lower floor unit in building 2. Status: Inspection Followup | Pacific Rock | $58.9K |
| applied Jul 13 | #PMT-3164872 Mechanical Pmt Mechanical work for converting garage in building 2 into ADU 5, remodel existing lower floor unit in building 2. Status: Inspection Followup | Pacific Rock | — |
| applied Jul 13 | #PMT-3164874 Plumbing Pmt Plumbing work converting garage in building 2 into ADU 5, remodel existing lower floor unit in building 2. Status: Inspection Followup | Pacific Rock | — |
| applied Jul 13 | #PMT-3164866 Plumbing Pmt **Scope Change (07/31/2024)**NORTH PARK: Building, Mechanical, Electrical, and Plumbing permits for converting upper unit in building 1 into 2 units, converting garage in building 2 into ADU 7, remodel existing lower floor unit in building 2 in existing multi family structure. Work to include… Status: Inspection Followup | Pacific Rock | — |
| applied Jul 13 | #PMT-3164854 Building Permit **Scope Change (07/31/2024)**NORTH PARK: Building, Mechanical, Electrical, and Plumbing permits for converting upper unit in building 1 into 2 units, converting garage in building 2 into ADU 7, remodel existing lower floor unit in building 2 in existing multi family structure. Work to include… Status: Inspection Followup | Pacific Rock | $465K |