Get ProEvery project in every city · from $79/mo
Get Procommercial project · San Diego, CA
Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted January 8, 2026, with 13 permits through June 18, 2026, declaring $284,928 of work. Contractor on record: Stefan LaCasse.
**Scope Change (11/20/2025)**Building 1: a conversion of an existing machine room into (3) ADUs on the 1st floor of an existing MDU. For the proposed aluminum trash enclosure to the existing lot. BC Code: 4333
San Diego permit records name Stefan LaCasse and Rios Fire Protection, Inc. as the contractors on this project.
13 permits issued Jan 8 – Jun 18, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
In San Diego, biggest first.
| applied Feb 17 |
#PMT-3401804 Approval - Construction - Fire Pmt - Suppression Deferred Fire Sprinklers with Plans. PRJ-1104563 Status: Inspection Followup |
| Rios Fire Protection, Inc. |
| — |
| applied Sep 20 | #PMT-3248163 Mechanical Pmt **Scope Change (11/20/2025)**Mechanical work associated with Building 2: a conversion of (2) existing garages into (1) ADU attached to an existing MDU. Status: Inspection Followup | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248169 Plumbing Pmt **Scope Change (11/20/2025)**Plumbing work associated with Building 3: a conversion of an existing space into (1) ADU on the 2nd floor of an existing MDU. Status: Inspection Followup | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248164 Plumbing Pmt **Scope Change (11/20/2025)**Plumbing work associated with Building 2: a conversion of (2) existing garages into (1) ADU attached to an existing MDU. Status: Inspection Followup | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248166 Electrical Pmt **Scope Change (11/20/2025)**Electrical work associated with Building 3: a conversion of an existing space into (1) ADU on the 2nd floor of an existing MDU. Status: Inspecting | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248168 Mechanical Pmt **Scope Change (11/20/2025)**Mechanical work associated with Building 3: a conversion of an existing space into (1) ADU on the 2nd floor of an existing MDU. Status: Inspection Followup | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248162 Electrical Pmt **Scope Change (11/20/2025)**Electrical work associated with Building 2: a conversion of (2) existing garages into (1) ADU attached to an existing MDU Status: Inspection Followup | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248156 Electrical Pmt **Scope Change (11/20/2025)**Electrical work associated with Building 1: a conversion of an existing machine room into (3) ADUs on the 1st floor of an existing MDU. For the proposed aluminum trash enclosure to the existing lot. Status: Inspection Followup | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248158 Plumbing Pmt **Scope Change (11/20/2025)**Plumbing work associated with Building 1: a conversion of an existing machine room into (3) ADUs on the 1st floor of an existing MDU. For the proposed aluminum trash enclosure to the existing lot. Status: Inspection Followup | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248157 Mechanical Pmt **Scope Change (11/20/2025)**Mechanical work associated with Building 1: a conversion of an existing machine room into (3) ADUs on the 1st floor of an existing MDU. For the proposed aluminum trash enclosure to the existing lot. Status: Inspecting | Stefan LaCasse | — |
| applied Sep 20 | #PMT-3248161 Building Permit **Scope Change (11/20/2025)** Building 2: a conversion of (2) existing garages into (1) ADU attached to an existing MDU. BC Code 4333 Status: Inspection Followup | Stefan LaCasse | $34.3K |
| applied Sep 20 | #PMT-3248165 Building Permit **Scope Change (11/20/2025)**Building 3: a conversion of an existing space into (1) ADU on the 2nd floor of an existing MDU. Status: Inspection Followup | Stefan LaCasse | $111K |
| applied Sep 20 | #PMT-3248153 Building Permit **Scope Change (11/20/2025)**Building 1: a conversion of an existing machine room into (3) ADUs on the 1st floor of an existing MDU. For the proposed aluminum trash enclosure to the existing lot. BC Code: 4333 Status: Inspection Followup | Stefan LaCasse | $140K |