Get ProEvery project in every city · from $79/mo
Get Promultifamily project · San Diego, CA
Multifamily General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted March 19, 2026, with 45 permits through May 6, 2026. Contractor on record: Lennar Homes of Calfornia, LLC.
Deferred Fire Alarms with Plans. Bldg# 3. PRJ-1138259
San Diego permit records name Lennar Homes of Calfornia, LLC and Symons Fire Protection, Inc. as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
45 permits issued Mar 19 – May 6, newest first.
| Issued | Permit | Contractor | Value |
|---|
In San Diego, biggest first.
| applied Apr 17 | #PMT-3412048 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 3. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412061 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 9. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412068 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 12. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412059 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 8. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412056 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 7. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412063 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 10. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412047 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 2. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412049 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 4. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412072 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 14. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412066 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 11. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412046 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 1. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412051 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 5. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412071 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 13. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Apr 17 | #PMT-3412052 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarms with Plans. Bldg# 6. PRJ-1138259 Status: Issued | Symons Fire Protection, Inc. | — |
| applied Jun 18 | #PMT-3359576 Electrical Pmt Electrical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Dec 3 | #PMT-3389479 Approval - Construction - Fire Pmt - Suppression Sprinkler permit for new townhomes Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359624 Mechanical Pmt Mechanical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359626 Plumbing Pmt Plumbing permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359621 Electrical Pmt Electrical permit for work associated with building permit including PV Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Dec 3 | #PMT-3389467 Approval - Construction - Fire Pmt - Suppression Sprinkler permit for new townhomes Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359590 Electrical Pmt Electrical permit for work associated with building permit including PV Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359622 Plumbing Pmt Plumbing permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359591 Plumbing Pmt Plumbing permit for work associated with building permit. Status: Inspecting | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359589 Mechanical Pmt Mechanical permit for work associated with building permit. Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359577 Plumbing Pmt Plumbing permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359625 Electrical Pmt Electrical permit for work associated with building permit including PV Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359620 Mechanical Pmt Mechanical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Dec 3 | #PMT-3389478 Approval - Construction - Fire Pmt - Suppression Sprinkler permit for new townhomes Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Dec 3 | #PMT-3389468 Approval - Construction - Fire Pmt - Suppression Sprinkler permit for new townhomes Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359575 Mechanical Pmt Mechanical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359642 Electrical Pmt Electrical permit for work associated with building permit including PV Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359635 Plumbing Pmt Plumbing permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359628 Mechanical Pmt Mechanical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359564 Approval - Construction - Master Plan Establish **SCOPE CHANGE 11/6/2025** OTAY MESA; One-Step Master Plan Establishment for 3 (R-2) building types 3-unit 4 unit and 5-unit variation types; having 7 plan types for a total of 14 Buildings consisting of 82 Units to be Issued in phases and may be Issued in non-sequential order having models with… Status: Issued | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359630 Plumbing Pmt Plumbing permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359641 Mechanical Pmt Mechanical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Dec 3 | #PMT-3389481 Approval - Construction - Fire Pmt - Suppression Sprinkler permit for new townhomes Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Dec 3 | #PMT-3389482 Approval - Construction - Fire Pmt - Suppression Sprinkler permit for new townhomes Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359629 Electrical Pmt Electrical permit for work associated with building permit including PV Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359563 Approval - Construction - Master Plan Establish **SCOPE CHANGE 11/6/2025** OTAY MESA; One-Step Master Plan Establishment for 3 (R-2) building types 3-unit 4 unit and 5-unit variation types; having 7 plan types for a total of 14 Buildings consisting of 82 Units to be Issued in phases and may be Issued in non-sequential order having models with… Status: Issued | Lennar Homes of Calfornia, LLC | — |
| applied Dec 3 | #PMT-3389484 Approval - Construction - Fire Pmt - Suppression Sprinkler permit for new townhomes Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359633 Mechanical Pmt Mechanical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359634 Electrical Pmt Electrical permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359643 Plumbing Pmt Plumbing permit for work associated with building permit Status: Inspection Followup | Lennar Homes of Calfornia, LLC | — |
| applied Jun 18 | #PMT-3359565 Approval - Construction - Master Plan Establish **SCOPE CHANGE 11/6/2025** OTAY MESA; One-Step Master Plan Establishment for 3 (R-2) building types 3-unit 4 unit and 5-unit variation types; having 7 plan types for a total of 14 Buildings consisting of 82 Units to be Issued in phases and may be Issued in non-sequential order having models with… Status: Issued | Lennar Homes of Calfornia, LLC | — |