Commercial General Building, Electrical work permitted November 20, 2025, with 2 permits through November 20, 2025, declaring $1,925,700 of work. Contractor on record: Burns & McDonnell Western Enterprises, Inc.
Project includes installation of a hydrant fueling system to serve gates across the existing Terminal 2 West. Fueling system will include installation of a 12-inch hydrant fuel main and 14-inch fuel transfer line, hydrant pits, isolation valve vaults, isolation valve pits, high point vent/low point drain pits, and Emergency Fuel Shutoff (EFSO) System.
San Diego permit records name Burns & McDonnell Western Enterprises, Inc as the contractor on this project.
2 permits issued Nov 20 – Nov 20, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jul 15 | #PMT-3364076 Electrical Pmt San Diego International Airport-Installation of a underground fueling system for Terminal 2 West to serve for refueling of aircrafts and Emergency Fuel Shutoff (EFSO) System. |
Status: Inspection Followup
| Burns & McDonnell Western Enterprises, Inc |
| — |
| applied Jul 15 | #PMT-3364073 Building Permit Project includes installation of a hydrant fueling system to serve gates across the existing Terminal 2 West. Fueling system will include installation of a 12-inch hydrant fuel main and 14-inch fuel transfer line, hydrant pits, isolation valve vaults, isolation valve pits, high point vent/low… Status: Inspection Followup | Burns & McDonnell Western Enterprises, Inc | $1.9M |