Get ProEvery project in every city · from $79/mo
Get Procommercial project · San Diego, CA
Commercial Electrical, Plumbing, Solar work permitted December 4, 2024, with 3 permits through October 24, 2025. Contractor on record: Mitzie Edwards.
Relocate the existing Electric panel and install a new 400A dual-meter panel to meet SDG&E clearance requirements and clear the existing electric path for future ADU construction. SDG&E Service Order for Electric Relocation approved under 300000762051.
San Diego permit records name Mitzie Edwards and Sunrun as the contractors on this project.
3 permits issued Dec 4 – Oct 24, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 24 | #PMT-3382959 No-Plan - Nonresidential/Multifamily - Electrical |
In San Diego, biggest first.
Relocate the existing Electric panel and install a new 400A dual-meter panel to meet SDG&E clearance requirements and clear the existing electric path for future ADU construction. SDG&E Service Order for Electric Relocation approved under 300000762051.
Status: Inspection Followup
| Mitzie Edwards |
| — |
| applied Aug 26 | #PMT-3371591 No-Plan - Nonresidential/Multifamily - Plumbing Relocate the existing Gas Meter and install a new gas header to meet SDG&E clearance requirements, adding a second gas meter for the future ADU. SDG&E Service Order for Gas Relocation approved under 300000780500. Status: Issued | Mitzie Edwards | — |
| applied Dec 4 | #PMT-3326083 Photovoltaic - SB 379 Status: Closed | Sunrun | — |