Get Procommercial project · San Diego, CA
Commercial General Building, Electrical, Fire Protection, Plumbing work permitted July 14, 2025, with 5 permits through April 23, 2026, declaring $1,292,512 of work. Contractor on record: PCL Construction.
For the proposed exterior and interior tenant improvements to the existing hotel, no change in occupancy. For the exterior improvements at Coronado Ballroom Terrace on the first floor, such as staining of existing concrete floor, removal and replacement of existing guard rail, removal of existing storefront and installation of nanawall system with storefront above. For the replacement of scones at Seaport Ballroom Terrace on the second floor. For the interior renovation of ballroom, meeting rooms, and public restrooms. Will include new floor finishes, wall finishes, and ceiling finished.
San Diego permit records name PCL Construction, HCI Systems, Inc. and Pyro-Comm Systems, Inc. as the contractors on this project.
5 permits issued Jul 14 – Apr 23, newest first.
In San Diego, biggest first.
| Issued | Permit | Contractor | Value |
|---|
| applied Apr 6 | #PMT-3409969 Approval - Construction - Fire Pmt - Suppression Deferred Fire Sprinklers Affidavit. 1-20 Sprinklers. PRJ-1131376 Status: Issued | HCI Systems, Inc. | — |
| applied Apr 14 | #PMT-3411532 Approval - Construction - Fire Pmt - Alarm Deferred Fire Alarm Affidavit. 0- Devices/Appliances. PRJ-1131376 Status: Issued | Pyro-Comm Systems, Inc. | — |
| applied Feb 20 | #PMT-3338960 Electrical Pmt For the associated electrical work to the proposed exterior and interior tenant improvements to the existing hotel, no change in occupancy. For the exterior improvements at Coronado Ballroom Terrace on the first floor, such as staining of existing concrete floor, removal and replacement of… Status: Inspection Followup | PCL Construction | — |
| applied Feb 20 | #PMT-3338939 Building Permit For the proposed exterior and interior tenant improvements to the existing hotel, no change in occupancy. For the exterior improvements at Coronado Ballroom Terrace on the first floor, such as staining of existing concrete floor, removal and replacement of existing guard rail, removal of existing… Status: Inspection Followup | PCL Construction | $1.3M |
| applied Jun 11 | #PMT-3358336 Plumbing Pmt For the associated electrical work to the proposed exterior and interior tenant improvements to the existing hotel Status: Closed | PCL Construction | — |