Get ProEvery project in every city · from $79/mo
Get Procommercial project · Portland, OR
Commercial Electrical, Plumbing work permitted December 9, 2024, with 3 permits through February 9, 2026.
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
3 permits issued Dec 9 – Feb 9, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Feb 9 | #2026-009970-000-00-PT Plumbing Permit · Addition/Alteration/Replacement installed commercial dishwasher (no hot water used) Status: Final | Not published | — |
| applied Oct 7 |
#2025-081721-000-00-ET
Electrical Permit · Addition/Alteration/Replacement
7000 N Cutter Cir at Maletis warehouse: Reconfigure existing circuits for pallet jack chargers.
Status: Final
| Not published |
| — |
| applied Dec 9 | #2024-103143-000-00-ET Electrical Permit · Addition/Alteration/Replacement Maletis Beverage: Install cabling in existing conduits for (4) total EV charging pedestals with dual port heads. Status: Final | Not published | — |