Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical work permitted October 29, 2024, with 13 permits through April 3, 2026, declaring $1,346,891 of work.
TEMPORARY MULTNOMAH COUNTY SOBERING CENTER- 6,222 sf Tenant Improvement Outpatient Services for Sobering and Withdrawal Management. **w. 24-075957-MT** Entire Building will become an Ambulatory Care Facility. No change of occupancy. No proposed exterior modifications. No proposed structural modifications. Facility will be a temporary drop off point for participants to be directed to other resources. Participants will not be in the facility for longer than 23hrs and 59 minutes. Up to 13 participants will be incapable of self-preservation.
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
13 permits issued Oct 29 – Apr 3, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Apr 3 |
#2026-024232-000-00-ET
Electrical Permit · Addition/Alteration/Replacement
Run circuit for water heater
Status: Final
| Not published |
| — |
| applied Feb 12 | #2025-011528-000-00-ET Electrical Permit · Addition/Alteration/Replacement Pulling category and composite cable for three interior cameras and 1 wireless access point. Status: Final | Not published | — |
| applied Feb 4 | #2024-075952-REV-03-CO Commercial Building Permit · Alteration TEMPORARY MULTNOMAH COUNTY SOBERING CENTER-REV-03 - Movable partition walls are under 5'-9" so are being removed from the deferred submittal list Status: Final | Not published | — |
| applied Jan 21 | #2024-075952-REV-02-CO Commercial Building Permit · Alteration TEMP MULT CO SOBERING CENTER- REV-02 to DFS 01- Revise anchor bolt length and type due to existing slab being recessed with deep mortar bed and terrazzo topping Status: Final | Not published | — |
| applied Jan 21 | #2024-075952-DFS-02-CO Commercial Building Permit · Alteration TEMP MULT CO SOBERING CENTER- DFS-02- Handrail at ramp Status: Final | Not published | — |
| applied Jan 14 | #2025-003037-000-00-ET Electrical Permit · Addition/Alteration/Replacement L/V WIRING FOR FIRE ALARM - MULT CO TEMP SOBERING CENTER PH2 Status: Final | Not published | — |
| applied Dec 31 | #2024-108374-000-00-ET Electrical Permit · Addition/Alteration/Replacement Wire for Tenant improvement Phase II Status: Final | Not published | — |
| applied Dec 10 | #2024-075952-DFS-01-CO Commercial Building Permit · Alteration TEMPORARY MULTNOMAH COUNTY SOBERING CENTER- DFS-01 - Interior ramp Status: Final | Not published | — |
| applied Oct 8 | #2024-085806-000-00-FS Fire Systems Permit · Alteration SPRINKLER - MODIFICATIONS TO EXISTING WET AUTOMATIC FIRE SPRINKLER SYSTEM FOR TI (11 HEADS TOTAL) Status: Final | Not published | — |
| applied Nov 27 | #2024-099756-000-00-FS Fire Systems Permit · Addition ALARM - ADDITION OF NOTIFICATION THROUGHOUT DUE TO TI UPGRADE TO AMBULATORY CAR OCCUPANCY. Status: Final | Not published | — |
| applied Nov 5 | #2024-075952-REV-01-CO Commercial Building Permit · Alteration TEMP MULT CO SOBERING CENTER- REV-01- See Revision Narrative - Removal of 8'-0" partition walls, removal of kitchenette work, removal of OTP program, addition of double door, removal of most wall protection and all corner guards, updated hardware. Status: Final | Not published | — |
| applied Sep 12 | #2024-075957-000-00-MT Mechanical Permit · Tenant Improvement TEMP MULTNOMAH COUNTY SOBERING CENTER - **w. 24-075952-CO ** added exhaust fan/system for Soiled Hold, added dryer exhaust, and redistribute existing airflow for revised programming Status: Final | Not published | — |
| applied Sep 12 | #2024-075952-000-00-CO Commercial Building Permit · Alteration TEMPORARY MULTNOMAH COUNTY SOBERING CENTER- 6,222 sf Tenant Improvement Outpatient Services for Sobering and Withdrawal Management. **w. 24-075957-MT** Entire Building will become an Ambulatory Care Facility. No change of occupancy. No proposed exterior modifications. No proposed structural… Status: Final | Not published | $1.3M |