Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing, Sign work permitted November 4, 2024, with 317 permits through October 30, 2026, declaring $72,209,044 of work.
SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; DEMO WALLS, NEW WALLS TO CREATE, NETWORK RM, STORAGE RM, BAGGAGE CLAIM 1 AREA, BAG CLAIM 1 SECURITY COIL DOORS, MODERIZE ESCALATORS, CEILING, FLOORING, FINISHES AND ELEC
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
317 permits issued Nov 4 – Oct 30, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 30 | #2026-080533-000-00-ET |
Electrical Permit · Addition/Alteration/Replacement
103679 Alaska Gate Conversion. New low voltage raceway installation.
Status: Issued
| Not published |
| — |
| applied Aug 20 | #2024-020399-DFS-87-CO Commercial Building Permit · Addition T CORE - DFS-87 (DFS 285 for 20-124057-MG) - Supports and seismic for RFI 8944.1 OSI added fan coil Status: Issued | Not published | — |
| applied Sep 23 | #2024-020399-DFS-90-CO Commercial Building Permit · Addition T CORE - DFS-90 (DFS 288 for 20-124057-MG) - South branch raceway seismic Status: Issued | Not published | — |
| applied Sep 2 | #2024-020399-DFS-89-CO Commercial Building Permit · Addition T CORE - DFS-89 (DFS 287 for 20-124057-MG) - Seismic anchorage for north branch raceways Status: Issued | Not published | — |
| applied Sep 28 | #2024-020399-DFS-91-CO Commercial Building Permit · Addition T CORE - DFS-91 (DFS 289 for 20-124057-MG) - Baggage Handling seismic for BPE 25-28 supports Status: Issued | Not published | — |
| applied Sep 2 | #2024-020399-DFS-88-CO Commercial Building Permit · Addition T CORE - DFS-88 (DFS 286 for 20-124057-MG) - Seismic anchorage for Sector 41/42 branch power Status: Issued | Not published | — |
| applied Aug 19 | #2024-020399-DFS-86-CO Commercial Building Permit · Addition T CORE - DFS-86 (DFS 284 for 20-124057-MG) - Baggage system - seismic anchorage for DIO 904 suspended conduit Status: Issued | Not published | — |
| applied Sep 16 | #2026-069037-000-00-PT Plumbing Permit · Addition/Alteration/Replacement Piper Mechanical will be installing 21 catch basins Status: Under Inspection | Not published | — |
| applied Aug 18 | #2026-061271-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL NEW MOVING WALKWAYS TUNNEL LVL; DEMO FLOORS, INSTALL NEW MOVING WALKWAYS IN MULTPLE LOCATIONS, FLOORING, FINISHES AND ELEC Status: Issued | Not published | $1.2M |
| applied Aug 28 | #2026-064341-000-00-ET Electrical Permit · Addition/Alteration/Replacement 200A FEEDER - ALASKA LOUNGE Status: Issued | Not published | — |
| applied Jul 17 | #2024-020399-DFS-75-CO Commercial Building Permit · Addition T CORE - DFS-75 (DFS 273 for 20-124057-MG) - Glazed aluminum curtain wall #9 Status: Issued | Not published | — |
| applied Aug 18 | #2026-061269-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL NEW MOVING WALKWAYS TUNNEL LVL; DEMO FLOORS, INSTALL NEW MOVING WALKWAYS IN MULTPLE LOCATIONS, FLOORING, FINISHES AND ELEC Status: Issued | Not published | — |
| applied Jul 23 | #2025-024142-REV-03-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; REVISION TO INSTALL NEW ESCALATORS AT SOUTH TUNNEL Status: Issued | Not published | — |
| applied Aug 13 | #2026-060140-000-00-ET Electrical Permit · Addition/Alteration/Replacement ADD POWER AND DATA TO BREAKROOM - CLEAR PDX Status: Final | Not published | — |
| applied Aug 11 | #2026-059584-000-00-ET Electrical Permit · Addition/Alteration/Replacement (1) LV circuit to run new conduit for DAS from D9 hold room to D8 hold room on enplaning level Status: Under Inspection | Not published | — |
| applied Jul 22 | #2026-054085-000-00-ET Electrical Permit · Addition/Alteration/Replacement DISC/ RECONNECT POWER FOR STARBUCKS PDX-C6 KIOSK Status: Issued | Not published | — |
| applied Oct 15 | #2025-084065-000-00-FA Facility Permit · Alteration FULL PDOX PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DEMO WALLS, NEW WALLS TO CREATE ENPLANNING - TELECOM RM, LOBBY AREA, COMMERCIAL KITCHEN, WALK IN COOLER, DRY STORAGE RM, DEPLANNING - STORAGE RMS, OFFICES, BREAKRM, MEZZANINE - BATHRMS, STORAGE RMS, BISTRO… Status: Final | Not published | — |
| applied Mar 10 | #2026-017429-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL REROOF & CLADDING CONCOURSE C, D & E; EXTERIOR - REROOF CONCOURSE C & D AND PARTIAL REROOF CONCOURSE E, INSTALL FALL PROTECTION, REPAIR SKYLIGHTS, ACCESS LADDERS, REPAIR & REPLACE CLADDING CONCOURSE D, REPLACE DOOR FRAMES, REPLACE WINDOW GASKETS, FINISHES, PLUMB… Status: Issued | Not published | $8.9M |
| applied Jul 7 | #2026-050075-000-00-ET Electrical Permit · Addition/Alteration/Replacement CONNECT NEW SIGN TO EXISTING CIRCUIT. Status: Final | Not published | — |
| applied Apr 28 | #2025-040029-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EAST ELEVATION REVOLVING DOOR REHAB TI; DFS FOR REVOLVING DOORS Status: Issued | Not published | $1.3M |
| applied Jun 16 | #2026-042657-000-00-FS Fire Systems Permit · Alteration ALARM - DESIGN, FURNISH, & COORDINATE THE INSTALLATION OF A FIRE SYSTEM UPGRADE Status: Issued | Not published | — |
| applied May 18 | #2020-124057-REV-70-MG Major Project Groups · Addition T CORE - REV-70 to 23-055994-DFS-05-CO - Revision to apply fireproofing to additional structural members and/or deck infills Status: Issued | Not published | — |
| applied Jun 11 | #2026-042662-000-00-FS Fire Systems Permit · Removal ALARM - DEMO OF SMOKE DETECTORS IN ESCALATOR PITS. ADDITION OF TWO SMOKES, TWO HEATS, AND TWO RELAY MODULES FOR BAGGAGE CLAIM ONE FIRE DOORS. RELOCATE TWO SMOKES IN NETWORK ROOM P0148. ADDING 5 SMOKES AND 4 SPEAKER STROBES FOR NEWLY REMODELED BSO OFFICES BY BAGGAGE CLAIM ONE Status: Under Inspection | Not published | — |
| applied Jun 10 | #2026-042406-000-00-ET Electrical Permit · Addition/Alteration/Replacement 181149-99-030 (28) circuits for PDX DAS CBAND Project. Status: Issued | Not published | — |
| applied Jun 5 | #2026-040472-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; FIRE ALARM SYSTEM UPGRADE, 1 STROBE, 1 HORN STROBE, 2 HEAT DETECTORS Status: Final | Not published | $12K |
| applied Jun 4 | #2026-040867-000-00-ET Electrical Permit · Addition/Alteration/Replacement adding two circuits and a low voltage Status: Final | Not published | — |
| applied Sep 11 | #2025-074016-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, CREATE BACK OF HOUSE AREA, BAR AREA, SEATING AREA, CEILING, FINISHES, ELECTRICAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied May 18 | #2026-036333-000-00-ET Electrical Permit · Addition/Alteration/Replacement 181139 PDX EAST TERMINAL CURTAIN WALL & REVOLVING DOORS. Status: Under Inspection | Not published | — |
| applied May 14 | #2026-035334-000-00-ET Electrical Permit · Addition/Alteration/Replacement 103324 Power to New Baggage Claim 1. Status: Final | Not published | — |
| applied Apr 8 | #2024-020399-DFS-84-CO Commercial Building Permit · Addition T CORE - DFS-84 (DFS 282 for 20-124057-MG) - Installation of terminal sculpture - center (Pitt) Status: Issued | Not published | — |
| applied May 7 | #2026-033634-000-00-FA Facility Permit · Alteration hvac contols - PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, CREATE OFFICE, RETAIL AREA, CEILING, FINISHES AND ELECTRICAL ***** BID ESTIMATE ***** Status: Final | Not published | — |
| applied May 7 | #2026-033606-000-00-FA Facility Permit · Alteration hvac controls: _ PDX TERMINAL MARKET 503 ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE RETAIL AREA, STORAGE RM, CEILING, FINISHES; ELECTRICAL Status: Final | Not published | — |
| applied Apr 21 | #2026-028611-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX CONCOURSE C FIRE ALARM UPGRADE; INSTALL NEW EST4 PANEL, REPLACING EXISTING EST3 PANEL Status: Issued | Not published | $30.1K |
| applied Apr 15 | #2025-058654-DFS-03-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; DFS FOR CONDENSER UNIT SEISMIC ATTACHMENT Status: Issued | Not published | $650 |
| applied Mar 24 | #2024-020399-DFS-85-CO Commercial Building Permit · Addition T CORE - DFS-85 (DFS 283 for 20-124057-MG) - Phase 2 Deplaning Arrivals - Acoustical metal pan ceilings Status: Issued | Not published | — |
| applied Apr 16 | #2026-009276-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; REVISION TO REMOVE 1 FIRE SPRINKLER HEAD FROM SCOPE AND CHANGED EXISTING FIRE SPRINKLERS TO RELOCATIONS Status: Final | Not published | — |
| applied Apr 23 | #2026-028664-000-00-FS Fire Systems Permit · Alteration ALARM - A NEW EST4 PANEL WILL REPLACE THE EXISTING EST3 PANEL. NO CONSTRUCTION WILL HAPPEN AND NO NEW/ADDITIONAL DEVICES OF ANY KIND WILL BE INSTALLED Status: Issued | Not published | — |
| applied Mar 23 | #2025-016402-DFS-13-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR FALL ARREST ANCHORS Status: Final | Not published | $13.3K |
| applied Apr 21 | #2026-028609-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX CONCOURSE C FIRE ALARM UPGRADE; INSTALL NEW EST4 PANEL, REPLACING EXISTING EST3 PANEL Status: Issued | Not published | — |
| applied Apr 9 | #2026-025659-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL MARKET 503 ENPLANNING LVL TI; INSTALL 3 HEAT DETECTORS Status: Final | Not published | $6.4K |
| applied Apr 8 | #2026-025324-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL MARKET 503 ENPLANNING LVL TI; RELOCATING FIRE SPRINKLER HEAD FOR TENANT IMPROVEMENT, 1 HEAD Status: Final | Not published | $1.4K |
| applied Apr 9 | #2026-025664-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT ROSE CITY MARKET ENPLANNING LVL TI; INSTALL 1 STROBE AT STORAGE RM, RELOCATE 2 HEAT DETECTORS Status: Final | Not published | $8.3K |
| applied Apr 2 | #2026-024030-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; INSTALL 1 SMOKE DETECTOR, 1 HEAT DETECTOR, 2 SPEAKER STROBES Status: Final | Not published | $9.1K |
| applied Apr 2 | #2026-024110-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT ROSE CITY MARKET ENPLANNING LVL TI; ADDING AND RELOCATING FIRE SPRINKLER HEADS FOR TENANT IMPROVEMENT, 5 HEADS Status: Final | Not published | $2.6K |
| applied Apr 2 | #2025-024142-REV-02-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; REVISION TO WALL LOCATION, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Issued | Not published | — |
| applied Mar 3 | #2025-016402-DFS-10-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR METAL MESH AT FIREPLACE AND BISTRO Status: Final | Not published | $400K |
| applied Jan 9 | #2020-124057-REV-69-MG Major Project Groups · Addition T CORE - REV-69 to 24-020399-DFS-34-CO - Revision to drawings and calculations for post-installed anchors into CMU wall. Status: Issued | Not published | — |
| applied Dec 16 | #2025-100518-000-00-FA Facility Permit · Alteration pwr_PDX AIRPORT ROSE CITY MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE RETAIL AREA, STORAGE RM, CEILING, FINISHES: ELECTRICAL Status: Final | Not published | — |
| applied Sep 12 | #2025-074492-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL HVAC UPGRADE; NEW HOUSEKEEPING PADS, REPLACE EXTERIOR LOUVERS, REPAIR/REPLACE STAIR WALL ENCLOSURE DUE TO CEILING WORK, NEW ROOF CURBS, CEILING, FINISHES, ELECTRICAL Status: Issued | Not published | — |
| applied Mar 30 | #2025-016402-DFS-14-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR ANCHORAGE FOR TRANSFORMER Status: Final | Not published | $100K |
| applied Apr 1 | #2026-023587-000-00-FA Facility Permit · Alteration controls - PDX TERMINAL HVAC UPGRADE; NEW HOUSEKEEPING PADS, REPLACE EXTERIOR LOUVERS, REPAIR/REPLACE STAIR WALL ENCLOSURE DUE TO CEILING WORK, NEW ROOF CURBS, CEILING, FINISHES, ELECTRICAL Status: Issued | Not published | — |
| applied Apr 1 | #2026-023594-000-00-FA Facility Permit · Alteration controls_PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; CREATE ELEVATOR SHAFT, NETWORK RM, STORAGE RM, BAGGAGE CLAIM 1 AREA, BAG CLAIM 1 SECURITY COIL DOORS, MODERNIZE ESCALATORS, CEILING, FINISHES AND ELECTRICAL Status: Issued | Not published | — |
| applied Mar 31 | #2026-023001-000-00-FA Facility Permit · Alteration fire alarm - PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE BACK OF HOUSE AREA, BAR AREA, SEATING AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Feb 24 | #2024-020399-DFS-80-CO Commercial Building Permit · Addition T CORE - DFS-80 (DFS 278 for 20-124057-MG) - Seismic for stair 342A and grease platform Status: Final | Not published | — |
| applied Dec 16 | #2025-100534-000-00-FA Facility Permit · Alteration pwr_ PDX TERMINAL MARKET 503 ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE RETAIL AREA, STORAGE RM, CEILING, FINISHES; ELECTRICAL Status: Final | Not published | — |
| applied Mar 6 | #2024-020399-DFS-82-CO Commercial Building Permit · Addition T CORE - DFS-82 (DFS 280 for 20-124057-MG) - Installation of terminal sculpture - south (Watt) Status: Issued | Not published | — |
| applied Mar 26 | #2026-022155-000-00-ET Electrical Permit · Addition/Alteration/Replacement A new EST4 panel will replace the existing EST3 panel. No construction will happen and no new/additional devices of any kind will be installed (ECONOMY EXIT PLAZA). Status: Issued | Not published | — |
| applied Mar 26 | #2026-022137-000-00-ET Electrical Permit · Addition/Alteration/Replacement A new EST4 panel will replace the existing EST3 panel. No construction will happen and no new/additional devices of any kind will be installed (GROUND TRANSPORTATION HOLD LOT BLDG). Status: Issued | Not published | — |
| applied Mar 26 | #2026-022163-000-00-ET Electrical Permit · Addition/Alteration/Replacement A new EST4 panel will replace the existing EST3 panel. No construction will happen and no new/additional devices of any kind will be installed (PUMP STATION N). Status: Issued | Not published | — |
| applied Mar 26 | #2026-022170-000-00-ET Electrical Permit · Addition/Alteration/Replacement A new EST4 panel will replace the existing EST3 panel. No construction will happen and no new/additional devices of any kind will be installed (PUMP STATION S). Status: Issued | Not published | — |
| applied Mar 26 | #2026-022174-000-00-ET Electrical Permit · Addition/Alteration/Replacement A new EST4 panel will replace the existing EST3 panel. No construction will happen and no new/additional devices of any kind will be installed (GROUND RUN UP). Status: Issued | Not published | — |
| applied Mar 26 | #2026-022158-000-00-ET Electrical Permit · Addition/Alteration/Replacement A new EST4 panel will replace the existing EST3 panel. No construction will happen and no new/additional devices of any kind will be installed (PDX CARGO CENTER WEST). Status: Issued | Not published | — |
| applied Mar 13 | #2026-018638-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; INSTALLATION OF A FIRE SAFETY SYSTEM INTO A TI SPACE, 1 SMOKE DETECTOR, 1 HEAT DETECTOR, 2 SPEAKER STROBES Status: Final | Not published | $9.1K |
| applied Mar 10 | #2025-016402-DFS-12-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR GLASS PANELS Status: Final | Not published | $500K |
| applied Mar 5 | #2025-016402-DFS-11-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR FIREPLACE Status: Final | Not published | $100K |
| applied Mar 18 | #2026-019695-000-00-ET Electrical Permit · Addition/Alteration/Replacement Install power pole and connect to existing ckt. Install (2) 20a ckts for receptacles. Status: Final | Not published | — |
| applied Feb 27 | #2025-016402-DFS-09-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR SLIDING ALUMINUM GLASS DOOR Status: Final | Not published | $39.2K |
| applied Feb 10 | #2026-010104-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS, FAN COIL UNIT, EXHAUST FAN AND ELEC Status: Final | Not published | $89K |
| applied Mar 17 | #2026-018723-000-00-FS Fire Systems Permit · Alteration ALARM - EXTEND EXISTING PUBLIC SAFETY COVERAGE Status: Final | Not published | — |
| applied Feb 24 | #2021-099907-REV-01-CO Commercial Building Permit · Alteration T CORE - CUP - REV-01 to DFS-06 - Revision to anchorage for VFD EWP-02 due to change in equipment size (other VFDs remain the same) Status: Final | Not published | — |
| applied Mar 10 | #2026-017426-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL REROOF & CLADDING CONCOURSE C, D & E; EXTERIOR - REROOF CONCOURSE C & D AND PARTIAL REROOF CONCOURSE E, INSTALL FALL PROTECTION, REPAIR SKYLIGHTS, ACCESS LADDERS, REPAIR & REPLACE CLADDING CONCOURSE D, REPLACE DOOR FRAMES, REPLACE WINDOW GASKETS, FINISHES, PLUMB… Status: Issued | Not published | — |
| applied Mar 5 | #2024-020399-DFS-81-CO Commercial Building Permit · Addition T CORE - DFS-81 (DFS 279 for 20-124057-MG) - Seismic anchorage for mezzanine Sector 31 racks Status: Final | Not published | — |
| applied Feb 27 | #2026-014889-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SMITH TEA ENPLANNING LVL TI; RELOCATE 1 VOICE ENABLED NOTIFICATION DEVICE, 1 SPEAKER STROBE Status: Final | Not published | $15.9K |
| applied Feb 19 | #2025-058654-DFS-02-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; DFS FOR WATER HEATER PLATFORM SEISMIC ATTACHMENT Status: Final | Not published | $650 |
| applied Jun 11 | #2025-046167-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL PORTLAND COFFEE ROASTERS TI; 1ST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE COFFEE SHOP RETAIL AREA, SERVICE AREA, DISHWASHING AREA, OFFICE, CEILING, FLOORING, FINISHES, PLUMBING AND ELEC, 2-ESPRESSO MACHINES, 1-STEAMER, 1-MOP SINK, 1-DISHWASHING… Status: Final | Not published | — |
| applied Mar 5 | #2026-016368-000-00-CO Commercial Building Permit · Addition T CORE - PLACEHOLDER PERMIT #3 - Permit created for #300-399 DFS and REV permits for 20-124057-MG Status: Issued | Not published | — |
| applied Feb 19 | #2025-094423-REV-02-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SKANNER NEWS ENPLANNING LVL TI; REVISION TO REMOVE RELOCATION OF BRANCH LINE FROM SCOPE OF WORK Status: Final | Not published | — |
| applied Dec 15 | #2025-100015-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL MARKET 503 ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $54K |
| applied Dec 15 | #2025-100012-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL MARKET 503 ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, STORAGE RM, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $296K |
| applied Dec 15 | #2025-100010-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL MARKET 503 ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, STORAGE RM, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Feb 11 | #2025-073472-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; DFS HVAC SEISMIC ATTACHMENTS Status: Issued | Not published | $650 |
| applied Dec 26 | #2025-016402-DFS-03-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR SUSPENDED CEILINGS Status: Final | Not published | $67.3K |
| applied Feb 17 | #2026-011767-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; MODIFY EXISTING WET SPRINKLER SYSTEM TO ACCOMMODATE NEW LAYOUT, 34 HEADS Status: Under Inspection | Not published | $23.7K |
| applied Feb 25 | #2026-014159-000-00-FA Facility Permit · Alteration hvac controls - PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, CREATE BACK OF HOUSE AREA, BAR AREA, SEATING AREA, CEILING, FINISHES, ELECTRICAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Feb 25 | #2026-014169-000-00-FA Facility Permit · Alteration hvac controls - PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FINISHES; ELECTRICAL ******* BID ESTIMATE ******* Status: Under Inspection | Not published | — |
| applied Feb 25 | #2026-014254-000-00-FA Facility Permit · Alteration hvac contols_PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FINISHES; ELECTRCAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Feb 10 | #2025-016402-DFS-06-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR KITCHEN EQUIPMENT ANCHORAGE AND SUSPENSION Status: Final | Not published | $5K |
| applied Feb 10 | #2025-073561-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; DFS FOR EXHAUST FAN SEISMIC ATTACHMENT Status: Final | Not published | $650 |
| applied Feb 10 | #2025-016402-DFS-08-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR HANDRAIL ANCHOARGE Status: Final | Not published | $100K |
| applied Feb 10 | #2025-016402-DFS-07-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR METAL PANEL ANCHORAGE Status: Final | Not published | $100K |
| applied Jan 16 | #2024-020399-DFS-79-CO Commercial Building Permit · Addition T CORE - DFS-79 (DFS 277 for 20-124057-MG) - Seismic anchorage for low voltage suspended raceway racks Sector 41/42 Status: Issued | Not published | — |
| applied Jan 15 | #2024-020399-DFS-78-CO Commercial Building Permit · Addition T CORE - DFS-78 (DFS 276 for 20-124057-MG) - Seismic anchorage for repeater room conduits Status: Issued | Not published | — |
| applied Feb 11 | #2026-010561-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL PORTLAND GEAR TI; INSTALL FIRE SAFETY SYSTEM, 1 SPEAKER STROBE Status: Final | Not published | $5.8K |
| applied Feb 11 | #2026-010569-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; INSTALL FIRE SAFETY SYSTEM, 3 SMOKE DETECTORS, 1 SPEAKER STROBE Status: Final | Not published | $6.7K |
| applied Feb 11 | #2026-010645-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; RELOCATING EXISTING HORN/STROBE FROM WALL TO ADJACENT WALL, PROVIDING 3 NEW SMOKE DETECTORS AND RELOCATING 1 SMOKE DETECTOR Status: Final | Not published | $5.7K |
| applied Feb 20 | #2026-013037-000-00-ET Electrical Permit · Addition/Alteration/Replacement Tenant Improvements Status: Final | Not published | — |
| applied Feb 10 | #2026-010271-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL POWELLS BOOKS ENPLANNING LEVEL TI; INSTALL 1 SPEAKER STROBE FOR NEW TENANT Status: Issued | Not published | $3.5K |
| applied Jan 20 | #2026-004501-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; INSTALL DUCTWORK, TYPE 1 HOOD, WALK IN COOLER, CONDENSING UNIT, FINISHES, PIPING AND ELEC Status: Final | Not published | $49K |
| applied Feb 10 | #2025-058654-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; DFS FOR WALK IN COOLER Status: Issued | Not published | $10K |
| applied Feb 10 | #2026-010311-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SKANNER NEWS ENPLANNING LVL TI; REMOVING EXISTING HORN/STROBE FROM WALL AND PROVIDING NEW SPEAKER STROBE DEVICE FOR CEILING, ADDING 5 SMOKE DETECTORS AND RELOCATING 1 SMOKE DETECTOR ALL AT OTS CEILING Status: Final | Not published | $5.7K |
| applied Feb 10 | #2026-010213-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL FREELAND SPIRITS ENPLANNING LVL TI; ADDITION OF 2 NEW PENDENT SPRINKLERS IN 2 NEW CLOSETS FOR TENANT IMPROVEMENT Status: Final | Not published | $2.9K |
| applied Feb 10 | #2026-010275-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL FREELAND SPIRITS ENPLANNING LVL TI; INSTALL FIRE SAFETY SYSTEM, 1 SPEAKER STROBE Status: Final | Not published | $6.2K |
| applied Feb 5 | #2026-009276-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; ADD AND RELOCATE HEADS FOR TI, 5 HEADS Status: Final | Not published | $2K |
| applied Feb 10 | #2026-010264-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; INSTALL FIRE SAFETY SYSTEM, 9 SMOKE DETECTORS, 4 SPEAKER STROBES Status: Final | Not published | $12.7K |
| applied Feb 11 | #2026-010564-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL WASHINGTON PARK TI; INSTALL FIRE SAFETY SYSTEM, 4 SMOKE DETECTORS, 3 SPEAKER STROBES Status: Final | Not published | $10.6K |
| applied Feb 5 | #2026-009258-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; INSTALL FIRE SAFETY SYSTEM, 3 SMOKE DETECTORS, 2 SPEAKER STROBES Status: Final | Not published | $9.7K |
| applied Feb 5 | #2026-009216-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL PORTLAND COFFEE ROASTERS TI; INSTALL FIRE SAFETY SYSTEM, 1 SPEAKER STROBE Status: Final | Not published | $4.8K |
| applied Dec 15 | #2025-100036-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT ROSE CITY MARKET ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $75K |
| applied Dec 15 | #2025-100035-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT ROSE CITY MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, STORAGE RM, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Under Inspection | Not published | $300K |
| applied Dec 15 | #2025-100034-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT ROSE CITY MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, STORAGE RM, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Sep 10 | #2025-073728-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, CREATE OFFICE, RETAIL AREA, CEILING, FINISHES AND ELECTRICAL ***** BID ESTIMATE ***** Status: Final | Not published | — |
| applied Jul 28 | #2025-060552-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE ENPLANNING LVL - RESTAURANT SERVICE AREA, KITCHEN, WALK IN COOLER, DEPLANNING LVL - CONCESSION STORAGE, CEILING, FLOORING, FINISHES, PLUMB AND ELEC,… Status: Final | Not published | — |
| applied Dec 29 | #2024-020399-DFS-77-CO Commercial Building Permit · Addition T CORE - DFS-77 (DFS 275 for 20-124057-MG) - Phase 02 suspended gypsum ceilings Status: Issued | Not published | — |
| applied Sep 8 | #2025-072693-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $187K |
| applied Sep 10 | #2025-073713-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL PORTLAND GEAR TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, CREATE RETAIL AREA, STORAGE RM, CEILING, FINISHES ELECTRICAL ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Sep 8 | #2025-072690-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE OFFICE, RETAIL AREA, CEILING, FLOORING, FINISHES AND ELEC ***** BID ESTIMATE ***** Status: Issued | Not published | — |
| applied Jan 13 | #2025-016402-DFS-04-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR PLUMBING SEISMIC ATTACHMENTS Status: Final | Not published | $1.3K |
| applied Sep 8 | #2025-072692-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL CASCADES MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE OFFICE, RETAIL AREA, CEILING, FLOORING, FINISHES AND ELEC ***** BID ESTIMATE ***** Status: Final | Not published | $419K |
| applied Jan 15 | #2026-003511-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; FIXED SYSTEM - CONNECTION OF A FACTORY INSTALLED CAPTIVE AIRE FIRE SUPPRESSION SYSTEM TO COVER TEH DUCT, PLENUM & APPLIANCES. Status: Final | Not published | $1.6K |
| applied Jan 20 | #2025-094423-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SKANNER NEWS ENPLANNING LVL TI; VALUE ADDED REVISION TO ADD 5 SPRINKLER HEADS TO SCOPE FOR FIRE SPRINKLER COVERAGE Status: Final | Not published | $1.3K |
| applied Sep 10 | #2025-073663-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FINISHES; ELECTRICAL ******* BID ESTIMATE ******* Status: Under Inspection | Not published | — |
| applied Sep 10 | #2025-073677-000-00-FA Facility Permit · Alteration pwr_ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FINISHES; ELECTRCAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Jul 17 | #2025-057490-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, CREATE ENPLANNING LVL - RESTAURANT SERVICE AREA, KITCHEN, WALK IN COOLER, DEPLANNING LVL - CONCESSION STORAGE, CEILING, FINISHES; ELECTRICAL ***** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Jul 9 | #2025-054494-000-00-FA Facility Permit · Alteration pwr_ PDX TERMINAL FREELAND SPIRITS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE SALES AREA, BAR AREA, ELECTRICAL CLOSET, UTILITY CLOSET, CEILING, FINISHES, ELEC Status: Final | Not published | — |
| applied Jan 27 | #2026-006365-000-00-ET Electrical Permit · Addition/Alteration/Replacement 181125-99-030 PDX Circulation & Capacity Project Status: Under Inspection | Not published | — |
| applied Jan 27 | #2026-006329-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, CREATE STORAGE RM, RETAIL AREA, CEILING, FINISHES, ELECTRICAL ***** BID ESTIMATE ***** Status: Final | Not published | — |
| applied Dec 18 | #2021-099907-DFS-06-CO Commercial Building Permit · Alteration T CORE - CUP - DFS-06 - Seismic restraints for electrical raceways and equipment Status: Final | Not published | — |
| applied Sep 10 | #2025-073816-000-00-FA Facility Permit · Alteration hvac controls_PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, CREATE STORAGE RM, RETAIL AREA, CEILING, FINISHES, ELECTRICAL ***** BID ESTIMATE ***** Status: Final | Not published | — |
| applied Jan 13 | #2025-016402-DFS-05-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR DUCTWORK SEISMIC ATTACHMENTS Status: Final | Not published | $650 |
| applied Sep 10 | #2025-073693-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE SALES AREAS, BACK OF HOUSE AREA, CEILING, FINISHES; ELECTRCAL ******* BID ESTIMATE ******* Status: Final | Not published | — |
| applied Sep 10 | #2025-073709-000-00-FA Facility Permit · Alteration pwr_ PDX TERMINAL WASHINGTON PARK TI; FIRST TIME TENANT, OCCUPANCY M, CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FINISHES; ELECTRICAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Jan 20 | #2026-004359-000-00-FA Facility Permit · Alteration hvac controls - PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREAS, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ******* BID ESTIMATE ******* Status: Final | Not published | — |
| applied Sep 2 | #2025-070835-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE BACK OF HOUSE AREA, BAR AREA, SEATING AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC, 1-DISHWASHER, 1-ICE MAKER, 1-HAND SINK, 1-WATER… Status: Final | Not published | — |
| applied Jul 28 | #2025-060535-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL FREELAND SPIRITS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE SALES AREA, BAR AREA, ELECTRICAL CLOSET, UTILITY CLOSET, CEILING, FLOORING, FINISHES, PLUMB AND ELEC, 1-WATER HEATER, 1-EXPANSION TANK, 1-MOP SINK, 2-FLOOR SINKS,… Status: Final | Not published | — |
| applied Dec 15 | #2020-124057-REV-68-MG Major Project Groups · Addition T CORE - REV-68 to 23-055994-DFS-46-CO - Revision to include additional wedge anchors Status: Final | Not published | — |
| applied Jan 13 | #2026-002727-000-00-ET Electrical Permit · Addition/Alteration/Replacement 181142 PDX P3 - electrical for DAS intall. Status: Final | Not published | — |
| applied Jan 5 | #2026-000990-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SMITH TEA ENPLANNING LVL TI; MODIFICATIONS TO THE EXISTING WET SPRINKLER SYSTEM TO ACCOMMODATE NEW LAYOUT FOR TENANT, 1 HEAD Status: Final | Not published | $2.5K |
| applied Sep 29 | #2025-079218-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL SMITH TEA ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, CREATE FOOD AND BEVERAGE RETAIL AREA, SERVICE AREA, KITCHEN, CEILING, FINISHES; ELECTRICAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Dec 17 | #2025-024142-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; VALUE ADDED REVISION, NEW WALLS TO CREATE OFFICES, STORAGE RMS, CEILING, FLOORING, FINISHES, INSTALL DUCTWORK, GRILLES, DIFFUSERS, TERMINAL UNITS, PLUMB AND ELEC Status: Issued | Not published | $450K |
| applied Jun 9 | #2025-045163-000-00-FA Facility Permit · Alteration pwr_ PDX AIRPORT TERMINAL BOILER DEPLANNING LVL TI; INSTALL DUAL FUEL BOILER, PUMP, HOUSEKEEPING PAD, PIPING; ELECTRICAL Status: Final | Not published | — |
| applied Oct 16 | #2025-084366-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SMITH TEA ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE FOOD AND BEVERAGE RETAIL AREA, SERVICE AREA, KITCHEN, CEILING, FLOORING, FINISHES, PLUMB AND ELEC, 1-MIXING VALVE, 1-WATER METER, 1-FLOOR DRAIN, 1-TRAP PRIMER, 1-FLOOR… Status: Final | Not published | — |
| applied Oct 30 | #2024-020399-DFS-76-CO Commercial Building Permit · Addition T CORE - DFS-76 (DFS 274 for 20-124057-MG) - Phase 02 plumbing supports and seismic delegated design Status: Issued | Not published | — |
| applied Dec 19 | #2025-016402-DFS-02-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR SEISMIC RESTRAINTS FOR HVAC PIPING & EQUIPMENT Status: Final | Not published | $1.5K |
| applied Dec 16 | #2025-040029-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EAST ELEVATION REVOLVING DOOR REHAB TI; VALUE ADDED REVISION, EXTERIOR - DEPLANNING LEVEL REMODEL ADDITIONAL ENTRIES, REPLACE REVOLVING DOORS, CLADDING, WATERPROOFING, CEILING, FLOORING, FINISHES AND ELEC Status: Issued | Not published | $2.1M |
| applied Dec 18 | #2025-101508-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; MODIFY EXISTING SHELL SPRINKLER SYSTEM FOR NEW TENANT FLOOR AND CEILING LAYOUT, 7 HEADS Status: Final | Not published | $15K |
| applied Dec 18 | #2025-101174-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL WASHINGTON PARK TI; MODIFY EXISTING FIRE SPRINKLER SYSTEM FOR NEW FLOOR AND CEILING LAYOUT, 28 HEADS Status: Final | Not published | $15K |
| applied Dec 18 | #2025-101429-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; MODIFY EXISTING FIRE SPRINKLER SYSTEM FOR NEW TENANT FLOOR AND CEILING LAYOUT, 5 HEADS Status: Under Inspection | Not published | $12K |
| applied Dec 17 | #2025-100920-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; MODIFY SHELL FIRE SPRINKLER SYSTEM FOR NEW TENANT BUILDOUT, 7 HEADS Status: Final | Not published | $8K |
| applied Dec 15 | #2025-100116-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; MODIFY EXISTING FIRE SPRINKLER COVERAGE FOR NEW AIRPORT RESTAURANT, 11 HEADS Status: Final | Not published | $8.5K |
| applied Dec 16 | #2025-100328-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; MODIFY EXISTING SHELL SPRINKLERS FOR NEW TENANT BUILDOUT, 11 HEADS Status: Final | Not published | $12K |
| applied Dec 15 | #2025-099998-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; ADDING AND RELOCATING FIRE SPRINKLER HEADS FOR TENANT IMPROVEMENT, 12 HEADS Status: Final | Not published | $3.9K |
| applied Jul 7 | #2025-053557-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL FREELAND SPIRITS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE SALES AREA, BAR AREA, ELECTRICAL CLOSET, UTILITY CLOSET, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Jul 7 | #2025-053558-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL FREELAND SPIRITS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE SALES AREA, BAR AREA, ELECTRICAL CLOSET, UTILITY CLOSET, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $210K |
| applied Nov 26 | #2025-016402-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DFS FOR MECHANICAL PIPING SEISMIC BRACING Status: Final | Not published | $2K |
| applied Dec 2 | #2025-097146-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; INSTALL 1 SMOKE DETECTOR, 1 HEAT DETECTOR, 1 SPEAKER STROBE Status: Final | Not published | $10K |
| applied Aug 13 | #2025-065488-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, ENPLANNING LVL - NEW WALLS TO CREATE RESTAURANT SERVICE AREA, KITCHEN, WALK IN COOLER, DEPLANNING LVL - REMODEL CONCESSION STORAGE, CEILING, FLOORING, FINISHES, PLUMB AND… Status: Final | Not published | — |
| applied Oct 29 | #2024-020399-DFS-74-CO Commercial Building Permit · Addition T CORE - DFS-74 (DFS 272 for 20-124057-MG) - Seismic anchorage for switchgear 4D1T-14M-A Status: Final | Not published | — |
| applied Sep 16 | #2025-075013-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC, 1-ELECTRIC WATER COOLER Status: Final | Not published | — |
| applied Jul 17 | #2025-057397-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE ENPLANNING LVL - RESTAURANT SERVICE AREA, KITCHEN, WALK IN COOLER, DEPLANNING LVL - CONCESSION STORAGE, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ******… Status: Final | Not published | $790K |
| applied Jul 17 | #2025-057399-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL LOLAS CAFE ENPLANNING & DEPLANNING LVLS TI; INSTALL DUCTWORK, GRILLES, DIFFUERS, FAN COIL UNIT, PIPING AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $235K |
| applied Nov 20 | #2025-094788-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; ADDING AND RELOCATING FIRE SPRINKLER HEADS FOR TENANT IMPROVEMENT, 5 HEADS Status: Final | Not published | $2.4K |
| applied Nov 19 | #2025-094423-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SKANNER NEWS ENPLANNING LVL TI; ADDING AND RELOCATING FIRE SPRINKLER HEADS FOR TENANT IMPROVEMENT, 1 HEAD Status: Final | Not published | $1.3K |
| applied Sep 10 | #2025-073723-000-00-FA Facility Permit · Alteration pwr_ PDX TERMINAL SKANNER NEWS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE STORAGE RM, RETAILS AREAS, CEILING, FINISHES; ELECTRICAL ***** BID ESTIMATE ***** Status: Final | Not published | — |
| applied Jul 23 | #2025-059063-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, ENPLANNING LVL - CREATE RESTAURANT SERVICE AREA, KITCHEN, WALK IN COOLER, DEPLANNING LVL - REMODEL CONCESSION STORAGE, CEILING, FINISHES; ELECTRICAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Sep 16 | #2025-075005-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE STORAGE RM, RETAIL AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC, 1-WATER METER, 1-WATER HEATER, 1-HAND SINK Status: Final | Not published | — |
| applied Nov 5 | #2025-033523-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT TERMINAL BOILER DEPLANNING LVL TI; DFS FOR BOILER ANCHORAGE Status: Issued | Not published | $2K |
| applied Nov 17 | #2025-093483-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DESIGN BUILD PROPOSAL INCLUDES FIRE ALARM SYSTEM PROVISIONS, 1 SMOKE DETECOTR, 1 HEAT DETECTOR, 5 STROBES, 6 SPEAKER STROBES Status: Final | Not published | $25.6K |
| applied Oct 3 | #2023-088018-000-00-FS Fire Systems Permit · Addition ALARM - DEMO AND REBUILD OF CENTRAL TERMINAL IN THE AIRPORT. CHANGES ARE ON ALL LEVELS OF THE TERMINAL. DEPLANING (LEVEL 1) IS MOSTLY EXISTING WITH POCKETS OF CHANGES. OTHER LEVELS HAVE FULL DEMO AND BUILD OUT IN THE PLAN. CHANGES TO EVAC AND SPRINKLER ZONES TO FACILITATE EVACUATION PLAN Status: Under Inspection | Not published | — |
| applied Sep 4 | #2025-071886-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SKANNER NEWS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE STORAGE RM, RETAILS AREAS, CEILING, FLOORING, FINISHES AND ELEC ***** BID ESTIMATE ***** Status: Issued | Not published | — |
| applied Sep 4 | #2025-071896-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES, EXHAUST FAN AND ELEC ***** BID ESTIMATE ***** Status: Final | Not published | $279K |
| applied Sep 4 | #2025-071895-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE STORAGE RM, RETAIL AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ***** BID ESTIMATE ***** Status: Final | Not published | $629K |
| applied Sep 4 | #2025-071893-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SHERIDAN FRUIT CO ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE STORAGE RM, RETAIL AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ***** BID ESTIMATE ***** Status: Issued | Not published | — |
| applied Sep 4 | #2025-071890-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SKANNER NEWS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE STORAGE RM, RETAILS AREAS, CEILING, FLOORING, FINISHES AND ELEC ***** BID ESTIMATE ***** Status: Final | Not published | $410K |
| applied Jul 22 | #2025-058654-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, ENPLANNING LVL - NEW WALLS TO CREATE RESTAURANT SERVICE AREA, KITCHEN, WALK IN COOLER, DEPLANNING LVL - REMODEL CONCESSION STORAGE, CEILING, FLOORING, FINISHES, PLUMB AND… Status: Final | Not published | $600K |
| applied Jul 22 | #2025-058655-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; INSTALL TERMINAL UNITS, DUCTWORK, DIFFUSERS, GRILLES AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $55K |
| applied Nov 12 | #2025-092460-000-00-ET Electrical Permit · Addition/Alteration/Replacement 89395-25: Furnish and install (2) work area outlets consisting of (2) Category 6 cables and connectors from PoP D1083 IDF, Rack B3, Patch Panel ports 21-24 to Allegiant Office D1364 via Utility Tunnel. Status: Final | Not published | — |
| applied Jul 22 | #2025-058650-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL KURE SUPERFOODS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, ENPLANNING LVL - NEW WALLS TO CREATE RESTAURANT SERVICE AREA, KITCHEN, WALK IN COOLER, DEPLANNING LVL - REMODEL CONCESSION STORAGE, CEILING, FLOORING, FINISHES, PLUMB AND… Status: Issued | Not published | — |
| applied May 13 | #2020-124057-REV-64-MG Major Project Groups · Addition T CORE - REV-64 to 20-124057-DFS-86-MG - Revision to fireproofing Status: Issued | Not published | — |
| applied Oct 31 | #2025-089166-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL COLUMBIA SPORTSWEAR DEPLANING & ENPLANING LEVEL TI; RELOCATION OF 1 SPEAKER STROBE TO BE CONNECTED TO AIRPORTS SYSTEM Status: Final | Not published | $5.6K |
| applied Nov 3 | #2025-089598-000-00-FA Facility Permit · Alteration controls - PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DEMO WALLS, NEW WALLS TO CREATE ENPLANNING - TELECOM RM, LOBBY AREA, COMMERCIAL KITCHEN, WALK IN COOLER, DRY STORAGE RM, DEPLANNING - STORAGE RMS, OFFICES, BREAKRM, MEZZANINE - BATHRMS, STORAGE RMS, BISTRO AREA,… Status: Final | Not published | — |
| applied Oct 14 | #2025-083700-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) SINGLEPDF - MODERNIZATION OF EIGHT EXISTING ESCALATORS AT THE SOUTH END OF BAGGAGE CLAIM FROM SOUTH TUNNEL TO THE SKY BRIDGE: 8 EXISTING ESCALATORS AT THE NORTH END OF BAGGAGE CLAIM TO THE SKY BRIDGE Status: Under Inspection | Not published | — |
| applied Sep 29 | #2025-079180-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SMITH TEA ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE FOOD AND BEVERAGE RETAIL AREA, SERVICE AREA, KITCHEN, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Aug 29 | #2025-070511-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL STRAIGHTWAWAY COCKTAILS ENPLANNING & DEPLANNING LVLS TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE BACK OF HOUSE AREA, BAR AREA, SEATING AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $500K |
| applied Sep 29 | #2025-079182-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SMITH TEA ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE FOOD AND BEVERAGE RETAIL AREA, SERVICE AREA, KITCHEN, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $450K |
| applied Sep 26 | #2020-124057-REV-67-MG Major Project Groups · Addition T CORE - REV-67 to 24-020399-DFS-69-CO - Revision to Mezzanine Sector 11 raceway support modification Status: Final | Not published | — |
| applied Sep 24 | #2024-020399-DFS-72-CO Commercial Building Permit · Addition T CORE - DFS-72 (DFS 270 for 20-124057-MG) - Exit lane breach control system seismic attachment Status: Final | Not published | — |
| applied Oct 16 | #2025-073561-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; VALUE ADDED REVISION TO REMODEL REMOTE STORAGE ON DEPLANNING LEVEL, FLOORING, FINISHES AND ELEC ******* BID ESTIMATE ******* Status: Final | Not published | $50K |
| applied Oct 16 | #2025-073472-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; VALUE ADDED REVISION TO REMODEL REMOTE STORAGE ON DEPLANNING LEVEL, FLOORING, FINISHES AND ELEC ******* BID ESTIMATE ******* Status: Issued | Not published | $50K |
| applied Oct 16 | #2025-073437-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL WASHINGTON PARK TI; VALUE ADDED REVISION TO REMODEL REMOTE STORAGE ON DEPLANNING LEVEL, FLOORING, FINISHES AND ELEC ******* BID ESTIMATE ******* Status: Final | Not published | $60K |
| applied Oct 16 | #2025-073536-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; VALUE ADDED REVISION TO REMODEL REMOTE STORAGE ON DEPLANNING LEVEL, FLOORING, FINISHES AND ELEC ******* BID ESTIMATE ******** Status: Final | Not published | $50K |
| applied Aug 22 | #2025-068244-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL POWELLS BOOKS ENPLANNING LEVEL TI; FIRST TIME TENANT, OCCUPANCY M, CREATE RETAIL AREA, SHELVING, CEILING, FINISHES AND ELECTRICAL Status: Final | Not published | — |
| applied Jun 17 | #2025-047774-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL PORTLAND COFFEE ROASTERS TI; 1ST TIME TENANT, OCCUPANCY A2, CREATE COFFEE SHOP RETAIL AREA, SERVICE AREA, DISHWASHING AREA, OFFICE, CEILING, FINISHES, ELECTRICAL ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Oct 21 | #2025-085866-000-00-ET Electrical Permit · Addition/Alteration/Replacement 300860374 - Columbia Sportswear C20174 - Installation of Burglary Alarm System / CCTV System Status: Final | Not published | — |
| applied Sep 12 | #2024-020399-DFS-68-CO Commercial Building Permit · Addition T CORE - DFS-68 (DFS 266 for 20-124057-MG) - WindowTech glass wall shop drawings for Phase 2 Status: Final | Not published | — |
| applied Mar 11 | #2025-018776-000-00-FA Facility Permit · Alteration FULL PDOX PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DEMO WALLS, NEW WALLS TO CREATE ENPLANNING - TELECOM RM, LOBBY AREA, COMMERCIAL KITCHEN, WALK IN COOLER, DRY STORAGE RM, DEPLANNING - STORAGE RMS, OFFICES, BREAKRM, MEZZANINE - BATHRMS, STORAGE RMS, BISTRO… Status: Final | Not published | — |
| applied Jun 10 | #2025-045821-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL PORTLAND COFFEE ROASTERS TI; 1ST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE COFFEE SHOP RETAIL AREA, SERVICE AREA, DISHWASHING AREA, OFFICE, CEILING, FLOORING, FINISHES, PLUMBING AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $450K |
| applied Jun 10 | #2025-045817-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL PORTLAND COFFEE ROASTERS TI; 1ST TIME TENANT, OCCUPANCY A2, MINOR DEMO, NEW WALLS TO CREATE COFFEE SHOP RETAIL AREA, SERVICE AREA, DISHWASHING AREA, OFFICE, CEILING, FLOORING, FINISHES, PLUMBING AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Sep 10 | #2025-073565-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS, SUPPLY FAN AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $75K |
| applied Sep 11 | #2024-020399-DFS-54-CO Commercial Building Permit · Addition T CORE - DFS-54 (DFS 252 for 20-124057-MG) - Acoustic metal ceiling AMC3, AMC4 - Phase 2 Status: Issued | Not published | — |
| applied Sep 5 | #2024-020399-DFS-71-CO Commercial Building Permit · Addition T CORE - DFS-71 (DFS 269 for 20-124057-MG) - Metal stairs - Phase 2 - Stair 4 Status: Final | Not published | — |
| applied Sep 5 | #2024-020399-DFS-70-CO Commercial Building Permit · Addition T CORE - DFS-70 (DFS 268 for 20-124057-MG) - Seismic restraints for Sector 42 police equipment Status: Final | Not published | — |
| applied Sep 9 | #2024-020399-DFS-69-CO Commercial Building Permit · Addition T CORE - DFS-69 (DFS 267 for 20-124057-MG) - Seismic restraints for HVAC piping and equipment - Phase 2 - RUES 1, 2, 11, 12 Status: Final | Not published | — |
| applied Sep 25 | #2024-020399-DFS-73-CO Commercial Building Permit · Addition T CORE - DFS-73 (DFS 271 for 20-124057-MG) - Anchorage for sector 32 DAS remote units relocation Status: Final | Not published | — |
| applied Oct 3 | #2025-081064-000-00-PT Plumbing Permit · Addition/Alteration/Replacement Modernization of eight existing escalators at the south end of baggage claim from the south tunnel to the skybridge, and eight existing escalators at the north end of baggage claim to the skybridge. The work also includes providing a new escalator from the south tunnel to baggage claim, a new… Status: Under Inspection | Not published | — |
| applied Sep 29 | #2025-079279-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EAST ELEVATION REVOLVING DOOR REHAB TI; REPLACEMENT OF 18 PENDENT SPRINKLERS AND RAISING EXISTING SPRINKLER PIPING Status: Under Inspection | Not published | $18.9K |
| applied Sep 10 | #2025-073536-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREAS, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ******* BID ESTIMATE ******* Status: Under Inspection | Not published | $600K |
| applied Sep 10 | #2025-073537-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS, SUPPLY FAN AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $75K |
| applied Sep 10 | #2025-073468-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ******* BID ESTIMATE ******* Status: Under Inspection | Not published | — |
| applied Sep 10 | #2025-073437-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL WASHINGTON PARK TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $500K |
| applied Sep 10 | #2025-073439-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL WASHINGTON PARK ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS, SUPPLY FAN AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $75K |
| applied Sep 10 | #2025-073534-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EASTBANK MARKET ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREAS, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ******* BID ESTIMATE ******* Status: Issued | Not published | — |
| applied Sep 10 | #2025-073473-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS, SUPPLY FAN AND ELEC ******* BID ESTIMATE ******* Status: Final | Not published | $75K |
| applied Sep 10 | #2025-073472-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL BARBUR FOODS ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ******* BID ESTIMATE ******* Status: Under Inspection | Not published | $500K |
| applied Sep 10 | #2025-073434-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL WASHINGTON PARK TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Sep 10 | #2025-073558-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Sep 10 | #2025-073561-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL TOPAZ FARM ENPLANNING LVL TI; FIRST TIME TENANT, OCCUPANCY M, NEW WALLS TO CREATE SALES AREA, BACK OF HOUSE AREA, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $500K |
| applied Aug 26 | #2024-020399-DFS-67-CO Commercial Building Permit · Addition T CORE - DFS-67 (DFS 265 for 20-124057-MG) - Phase 02 mechanical seismic design Status: Issued | Not published | — |
| applied Sep 25 | #2025-078530-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL COLUMBIA SPORTSWEAR DEPLANING & ENPLANING LEVEL TI; ADDITION OF 2 NEW PENDENT SPRINKLERS IN 2 NEW CLOSETS Status: Final | Not published | $1.9K |
| applied Aug 21 | #2025-067965-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL POWELLS BOOKS ENPLANNING LEVEL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, SHELVING, CEILING, FLOORING, FINISHES AND ELEC ******* BID ESTIMATE ******* Status: Issued | Not published | — |
| applied Aug 21 | #2025-067967-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL POWELLS BOOKS ENPLANNING LEVEL TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, SHELVING, CEILING, FLOORING, FINISHES AND ELEC ******* BID ESTIMATE ******* Status: Final | Not published | $417K |
| applied Sep 16 | #2025-075165-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; MODIFICATION OF THE EXISTING WET SPRINKLER SYSTEM TO ACCOMMODATE NEW TENANT IMPROVEMENT, 63 HEADS Status: Final | Not published | $29.9K |
| applied Aug 18 | #2024-020399-DFS-65-CO Commercial Building Permit · Addition T CORE - DFS-65 (DFS 263 for 20-124057-MG) - Stair 33 shop/erection drawings Status: Final | Not published | — |
| applied Jun 18 | #2025-048368-000-00-FA Facility Permit · Alteration power - PDX TERMINAL COLUMBIA SPORTSWEAR DEPLANING & ENPLANING LEVEL TI; FIRST TIME TENANT, OCCUPANCY M & S1, MINOR DEMO, ENPLANING LVL - NEW WALLS TO CREATE RETAIL AREA, CLOSETS, DEPLANING LVL - REMODEL STORAGE AREA, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | — |
| applied Sep 22 | #2025-077213-000-00-ET Electrical Permit · Addition/Alteration/Replacement 300860382 - Columbia Sportswear - C20174 Storage Room - Wire run to install Burglary Alarm System Status: Final | Not published | — |
| applied Jul 9 | #2025-054512-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL SCREEN DOOR STORAGE DEPLANNING LVL TI; REMODEL STORAGE RM, CREATE WALK IN COOLER, CEILING, FINISHES, ELECTRICAL Status: Final | Not published | — |
| applied Aug 14 | #2020-124057-REV-66-MG Major Project Groups · Addition T CORE - REV-66 to 23-05594-DFS-52-CO - Revision to add KEF-T-4-27 (previously approved seismic details apply to this fan) Status: Final | Not published | — |
| applied Aug 14 | #2024-020399-DFS-64-CO Commercial Building Permit · Addition T CORE - DFS-64 (DFS 262 for 20-124057-MG) - Seismic anchorage Sector 42 corridor B10950 cable tray Status: Final | Not published | — |
| applied Jul 17 | #2025-057379-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL PORTLAND GEAR TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, STORAGE RM, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Under Inspection | Not published | $183K |
| applied Jul 17 | #2025-057375-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL PORTLAND GEAR TI; FIRST TIME TENANT, OCCUPANCY M, MINOR DEMO, NEW WALLS TO CREATE RETAIL AREA, STORAGE RM, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Sep 8 | #2025-072802-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SCREEN DOOR STORAGE DEPLANNING LVL TI; ADDING AND RELOCATING FIRE SPRINKLER HEADS FOR TENANT IMPROVEMENT, 2 DRY HEADS Status: Final | Not published | $2.2K |
| applied Aug 27 | #2025-069543-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL HVAC UPGRADE; INSTALL DUCTWORK, GRILLES, AIR HANDLING UNITS, DAMPERS, SPLIT SYSTEMS, ROOF TOP CONDENSING UNITS, EXHAUST FAN, PIPING AND ELEC Status: Under Inspection | Not published | $7.7M |
| applied Aug 27 | #2025-069540-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL HVAC UPGRADE; MINOR DEMO, NEW HOUSEKEEPING PADS, REPLACE EXTERIOR LOUVERS, REPAIR/REPLACE STAIR WALL ENCLOSURE DUE TO CEILING WORK, NEW ROOF CURBS, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Under Inspection | Not published | $9.2M |
| applied Sep 8 | #2025-072636-000-00-ET Electrical Permit · Addition/Alteration/Replacement Demo of existing branch circuits, PDUs and and feeders for UPS. Installation of new panel, circuits and receptacles for new UPS. [700368] Status: Final | Not published | — |
| applied Jul 30 | #2021-091506-REV-01-MT Mechanical Permit · Addition/Alteration/Replace (MT) MT - T CORE - REV-01 - Revision to hydronic piping at the injection well heated enclosures Status: Issued | Not published | — |
| applied Aug 27 | #2025-069538-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL HVAC UPGRADE; MINOR DEMO, NEW HOUSEKEEPING PADS, REPLACE EXTERIOR LOUVERS, REPAIR/REPLACE STAIR WALL ENCLOSURE DUE TO CEILING WORK, NEW ROOF CURBS, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Issued | Not published | — |
| applied Jul 22 | #2024-020399-DFS-63-CO Commercial Building Permit · Addition T CORE - DFS-63 (DFS 261 for 20-124057-MG) - Seismic anchorage for Sector 42 conduit and cable tray Status: Final | Not published | — |
| applied Aug 18 | #2025-064394-000-00-FS Fire Systems Permit · Alteration ALARM - THE EXISTING FIRE ALARM SYSTEM, AN EST3 ADDRESSABLE SYSTEM TO BE MODIFIED FOR COMPLIANCE Status: Issued | Not published | — |
| applied Jul 10 | #2024-020399-DFS-62-CO Commercial Building Permit · Addition T CORE - DFS-62 (DFS 260 for 20-124057-MG) - Suspended raceway racks seismic anchorage Status: Final | Not published | — |
| applied Jul 9 | #2025-054013-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SCREEN DOOR STORAGE DEPLANNING LVL TI; INSTALL CONDENSING UNIT, EVAPORATOR UNIT, PIPING AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $54.1K |
| applied Jul 9 | #2025-054011-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SCREEN DOOR STORAGE DEPLANNING LVL TI; MINOR DEMO, REMODEL STORAGE RM, NEW WALLS TO CREATE WALK IN COOLER, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $200K |
| applied Jul 8 | #2025-053999-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL SCREEN DOOR STORAGE DEPLANNING LVL TI; MINOR DEMO, REMODEL STORAGE RM, NEW WALLS TO CREATE WALK IN COOLER, CEILING, FLOORING, FINISHES, PLUMB AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied May 21 | #2025-040029-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EAST ELEVATION REVOLVING DOOR REHAB TI; EXTERIOR - REHAB ENPLANNING LEVEL CURTAIN WALL, REMODEL ALL ENTRIES, REPLACE REVOLVING DOORS, CLADDING, WATERPROOFING, CEILING, FLOORING, FINISHES AND ELEC Status: Issued | Not published | $2.8M |
| applied Jul 10 | #2024-020399-DFS-61-CO Commercial Building Permit · Addition T CORE - DFS-61 (DFS 259 for 20-124057-MG) - Hydronic piping in Sector 22 bag road and Sector 32/33/tunnel Status: Final | Not published | — |
| applied Jul 3 | #2024-020399-DFS-60-CO Commercial Building Permit · Addition T CORE - DFS-60 (DFS 258 for 20-124057-MG) - Existing slabs EF fans seismic - Phase 2 Status: Final | Not published | — |
| applied Jul 11 | #2025-051283-000-00-ET Electrical Permit · Addition/Alteration/Replacement PDOX ELECTRICAL FOR EGSE PHASE II INFASTRUCTURE INSTALL Status: Under Inspection | Not published | — |
| applied Jun 30 | #2024-020399-DFS-59-CO Commercial Building Permit · Addition T CORE - DFS-59 (DFS 257 for 20-124057-MG) - Phase 2 handrails/guardrails Status: Issued | Not published | — |
| applied Jun 30 | #2024-020399-DFS-57-CO Commercial Building Permit · Addition T CORE - DFS-57 (DFS 255 for 20-124057-MG) - Acoustical ceilings - Phase 2 APC3 Status: Issued | Not published | — |
| applied Mar 7 | #2025-017901-000-00-FA Facility Permit · Alteration pwr_PDX TERMINAL ALASKA AIRLINES MEZZANINE LOUNGE: ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; CREATE ENPLANNING - TELECOM RM, LOBBY AREA, COMMERCIAL KITCHEN, WALK IN COOLER, DRY STORAGE RM, DEPLANNING - STORAGE RMS, OFFICES, BREAKRM, MEZZANINE - BATHRMS, STORAGE RMS, BISTRO AREA, LOUNGE AREAS,… Status: Final | Not published | — |
| applied May 19 | #2025-036376-000-00-CO Commercial Building Permit · Alteration PDOX PS - PERSONAL WIRELESS SERVICE FACILITY - WIRELESS GARAGE - APPLICATION #3 - PROPOSED TO REMOVE ALL EXISTING ANTENNAS AND ANCILLARY EQUIPMENT AND ADDITION OF (2) PANEL ANTENNAS, (3) PANEL ANTENNA / RADIO COMBINATIONS, (1) SURGE SUPPRESSOR (OVP-6) AND (1) HYBRID CABLE. REMOVE ALL UNUSED… Status: Issued | Not published | — |
| applied Jul 14 | #2025-055102-000-00-FS Fire Systems Permit · New HAZARDOUS/TANK - INSTALL (1) 460-GALLON ABOVE GROUND STORAGE DAY TANK. SYSTEM TO FEED EMERGENCY GENERATOR. Status: Final | Not published | — |
| applied Jun 9 | #2025-045294-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL COLUMBIA SPORTSWEAR DEPLANNING & ENPLANNING LEVEL TI; FIRST TIME TENANT, OCCUPANCY M & S1, MINOR DEMO, ENPLANNING LVL - NEW WALLS TO CREATE RETAIL AREA, CLOSETS, DEPLANNING LVL - REMODEL STORAGE AREA, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Issued | Not published | — |
| applied Jun 9 | #2025-045296-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL COLUMBIA SPORTSWEAR DEPLANING & ENPLANING LEVEL TI; FIRST TIME TENANT, OCCUPANCY M & S1, MINOR DEMO, ENPLANING LVL - NEW WALLS TO CREATE RETAIL AREA, CLOSETS, DEPLANING LVL - REMODEL STORAGE AREA, CEILING, FLOORING, FINISHES AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $369K |
| applied Jul 16 | #2025-056812-000-00-ET Electrical Permit · Addition/Alteration/Replacement 103182 Alaska Airlines ATO Work Stations Status: Final | Not published | — |
| applied Mar 28 | #2025-024142-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; DEMO WALLS, NEW WALLS TO CREATE, NETWORK RM, STORAGE RM, BAGGAGE CLAIM 1 AREA, BAG CLAIM 1 SECURITY COIL DOORS, MODERIZE ESCALATORS, CEILING, FLOORING, FINISHES AND ELEC Status: Under Inspection | Not published | $19.1M |
| applied Mar 28 | #2025-024144-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; INSTALL DUCTWORK, GRILLES, FAN COIL, AIR CONDITIONER, PIPING AND ELEC Status: Issued | Not published | $21.1K |
| applied Apr 29 | #2025-033526-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT TERMINAL BOILER DEPLANNING LVL TI; INSTALL BOILER, PUMP, PIPING AND ELEC Status: Under Inspection | Not published | $750K |
| applied Apr 29 | #2025-033523-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT TERMINAL BOILER DEPLANNING LVL TI; INSTALL DUAL FUEL BOILER, PUMP, HOUSEKEEPING PAD, PIPING AND ELEC Status: Issued | Not published | $1.1M |
| applied May 21 | #2020-124057-REV-65-MG Major Project Groups · Addition T CORE - REV-65 to 20-124057-DFS-86-MG - Revision to add intumescent at North Terminal 2 - column and grade beam at Bag Road Status: Final | Not published | — |
| applied Jun 25 | #2021-099907-DFS-05-CO Commercial Building Permit · Alteration T CORE - CUP - DFS-05 - GSHPS Seismic anchorage for unit substation 5D2U-G2.5-5D Status: Final | Not published | — |
| applied Jun 25 | #2021-099907-DFS-04-CO Commercial Building Permit · Alteration T CORE - CUP - DFS-04 - Seismic anchorage for vista switchgear bases Status: Issued | Not published | — |
| applied Jun 25 | #2021-099907-DFS-03-CO Commercial Building Permit · Alteration T CORE - CUP - DFS-03 - GSHPS equipment anchorage Status: Final | Not published | — |
| applied Jun 18 | #2024-020399-DFS-55-CO Commercial Building Permit · Addition T CORE - DFS-55 (DFS 253 for 20-124057-MG) - Interior glazing at the Phase 2 concession spaces Status: Issued | Not published | — |
| applied Jun 18 | #2021-099907-DFS-02-CO Commercial Building Permit · Alteration T CORE - CUP - DFS-02 - Panelboard 4P1U-3E seismic anchorage - GSHPS Status: Final | Not published | — |
| applied Jun 20 | #2024-020399-DFS-56-CO Commercial Building Permit · Addition T CORE - DFS-56 (DFS 254 for 20-124057-MG) - Phase 2 RUW 11 seismic supports Status: Final | Not published | — |
| applied Jun 23 | #2024-020399-DFS-58-CO Commercial Building Permit · Addition T CORE - DFS-58 (DFS 256 for 20-124057-MG) - APC2 and APC3 ceilings at the South Mezzanine Conference Center Status: Final | Not published | — |
| applied Jun 10 | #2021-099907-DFS-01-CO Commercial Building Permit · Alteration T CORE - CUP - DFS-01 - Seismic restraints for HVAC piping - Central Utility Plant building GSHPS system Status: Final | Not published | — |
| applied Mar 6 | #2025-016405-000-00-FA Facility Permit · Alteration FULL PDOX PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS, CONDENSING UNITS, FAN, COILS, TERMINAL UNITS, EXHAUST FANS, FIREPLACE EXHAUST FAN, PIPING AND ELEC ****** BID ESTIMATE ****** Status: Final | Not published | $668K |
| applied Mar 6 | #2025-016402-000-00-FA Facility Permit · Alteration FULL PDOX PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DEMO WALLS, NEW WALLS TO CREATE ENPLANNING - TELECOM RM, LOBBY AREA, COMMERCIAL KITCHEN, WALK IN COOLER, DRY STORAGE RM, DEPLANNING - STORAGE RMS, OFFICES, BREAKRM, MEZZANINE - BATHRMS, STORAGE RMS, BISTRO… Status: Final | Not published | $9.3M |
| applied Mar 3 | #2025-016389-000-00-FA Facility Permit · Alteration FULL PDOX PROCESS/ PDX TERMINAL ALASKA AIRLINES ENPLANNING, DEPLANNING & MEZZANINE LVLS TI; DEMO WALLS, NEW WALLS TO CREATE ENPLANNING - TELECOM RM, LOBBY AREA, COMMERCIAL KITCHEN, WALK IN COOLER, DRY STORAGE RM, DEPLANNING - STORAGE RMS, OFFICES, BREAKRM, MEZZANINE - BATHRMS, STORAGE RMS, BISTRO… Status: Issued | Not published | — |
| applied Jun 11 | #2025-046219-000-00-ET Electrical Permit · Addition/Alteration/Replacement 181086: Passenger Boarding Bridges Phase II. (6) 300A feeders and (6) 120V 20A branch circuits Status: Final | Not published | — |
| applied Jun 11 | #2025-046228-000-00-ET Electrical Permit · Addition/Alteration/Replacement 103166 Leidos PDX - demo and rework of existing floor boxes, installing a new receptacle and circuit in Concourse D at PDX. Status: Final | Not published | — |
| applied May 30 | #2024-020399-DFS-53-CO Commercial Building Permit · Addition T CORE - DFS-53 (DFS 251 for 20-124057-MG) - Seismic anchorage for ELBC cabinets Status: Final | Not published | — |
| applied May 28 | #2024-020399-DFS-52-CO Commercial Building Permit · Addition T CORE - DFS-52 (DFS 250 for 20-124057-MG) - Sector 31 Mezzanine VVR Seismic DFS - Phase 2 Status: Final | Not published | — |
| applied May 23 | #2024-020399-DFS-48-CO Commercial Building Permit · Addition T CORE - DFS-48 (DFS 246 for 20-124057-MG) - Existing slab VVRs seismic - Phase 2 Status: Issued | Not published | — |
| applied May 22 | #2024-020399-DFS-51-CO Commercial Building Permit · Addition T CORE - DFS-51 (DFS 249 for 20-124057-MG) - Seismic restraints for Sector 42 feeder conduits Status: Final | Not published | — |
| applied Apr 30 | #2020-124057-REV-62-MG Major Project Groups · Addition T CORE - REV-62 to 24-020399-DFS-44-CO - Revision to include additional drawings for Phase 2 metal wall panels Status: Issued | Not published | — |
| applied May 21 | #2025-040025-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL EAST ELEVATION REVOLVING DOOR REHAB TI; EXTERIOR - REHAB ENPLANNING LEVEL CURTAIN WALL, REMODEL ALL ENTRIES, REPLACE REVOLVING DOORS, CLADDING, WATERPROOFING, CEILING, FLOORING, FINISHES AND ELEC Status: Issued | Not published | — |
| applied Apr 15 | #2020-124057-REV-60-MG Major Project Groups · Addition T CORE - REV-60 - Revision to remove the glazed canopy structure at the Tri-Met lobby from the approved drawings (to be submitted as a deferred submittal) Status: Issued | Not published | — |
| applied May 15 | #2025-038610-000-00-ET Electrical Permit · Addition/Alteration/Replacement HVAC Controls Low Voltage Status: Final | Not published | — |
| applied May 13 | #2024-020399-DFS-50-CO Commercial Building Permit · Addition T CORE - DFS-50 (DFS 248 for 20-124057-MG) - Captive hook interior wall glazing (Phase 2) Status: Issued | Not published | — |
| applied May 12 | #2024-020399-DFS-49-CO Commercial Building Permit · Addition T CORE - DFS-49 (DFS 247 for 20-124057-MG) - Metal stairs - Stair 02 Status: Final | Not published | — |
| applied May 9 | #2020-124057-REV-63-MG Major Project Groups · Addition T CORE - REV-63 to 23-055994-DFS-05-CO - Revision to applied fireproofing - CAFCO board Status: Issued | Not published | — |
| applied Feb 24 | #2020-124057-REV-57-MG Major Project Groups · Addition T CORE - REV-57 to 23-055994-DFS-05-CO (Applied Fireproofing) - Retrofit Revised Shop Drawings Status: Issued | Not published | — |
| applied Mar 25 | #2024-020399-DFS-44-CO Commercial Building Permit · Addition T CORE - DFS-44 (DFS 242 for 20-124057-MG) - Phase 2 metal wall panels Status: Issued | Not published | — |
| applied Apr 24 | #2025-032253-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT TERMINAL BOILER DEPLANNING LVL TI; INSTALL DUAL FUEL BOILER, PUMP, HOUSEKEEPING PAD, PIPING AND ELEC Status: Issued | Not published | — |
| applied Apr 22 | #2020-124057-REV-61-MG Major Project Groups · Addition T CORE - REV-61 - Revision to add engineering for hanger wire attachment to metal deck and clarify hanger wire attachment to steel trusses Status: Final | Not published | — |
| applied Feb 11 | #2024-020399-DFS-40-CO Commercial Building Permit · Addition T CORE - DFS-40 (DFS 238 for 20-124057-MG) - Tri Met canopy Status: Issued | Not published | — |
| applied Apr 10 | #2024-020399-DFS-47-CO Commercial Building Permit · Addition T CORE - DFS-47 (DFS 245 for 20-124057-MG) - Phase 2 RUE 11 seismic supports Status: Final | Not published | — |
| applied Apr 8 | #2024-020399-DFS-46-CO Commercial Building Permit · Addition T CORE - DFS-46 (DFS 244 for 20-124057-MG) - Seismic restraints for HVAC piping and equipment Status: Issued | Not published | — |
| applied Apr 4 | #2024-020399-DFS-45-CO Commercial Building Permit · Addition T CORE - DFS-45 (DFS 243 for 20-124057-MG) - Sector 42 shafts TSTB26 and TSTB12 duct support Status: Final | Not published | — |
| applied Mar 28 | #2025-024140-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX AIRPORT CIRCULATION & CAPACITY BAGGAGE CLAIM TI; DEMO WALLS, NEW WALLS TO CREATE ELEVATOR SHAFT, NETWORK RM, STORAGE RM, BAGGAGE CLAIM 1 AREA, BAG CLAIM 1 SECURITY COIL DOORS, MODERIZE ESCALATORS, CEILING, FLOORING, FINISHES AND ELEC Status: Issued | Not published | — |
| applied Mar 13 | #2020-124057-REV-59-MG Major Project Groups · Addition T CORE - REV-59 to 20-124057-DFS-36-MG - Revision to hangers and supports for HVAC piping and equipment Status: Final | Not published | — |
| applied Mar 13 | #2025-019631-000-00-FA Facility Permit · Alteration PDX TERMINAL ESCAPE LOUNGE TI CONCOURSE D; ALTERATION TO FIRE ALARM SYSTEM, FULL COVERAGE PROVIDED, SOME EXISTING DEVICES REUSED FOR ELEVATOR AND LOBBY SPACES, 28 SMOKE DETECTORS, 3 HEAT DETECTORS, 8 STROBES, 15 SPEAKER STROBES Status: Final | Not published | $28.1K |
| applied Mar 12 | #2025-019317-000-00-ET Electrical Permit · Addition/Alteration/Replacement 82080-25: Eight 120v 20A circuits for office general use, data cables for office general data connectivity. Status: Final | Not published | — |
| applied Mar 7 | #2024-020399-DFS-43-CO Commercial Building Permit · Addition T CORE - DFS-43 (DFS 241 for 20-124057-MG) - Stair 22 shop/erection drawings Status: Final | Not published | — |
| applied Feb 21 | #2024-020399-DFS-41-CO Commercial Building Permit · Addition T CORE - DFS-41 (DFS 239 for 20-124057-MG) - Seismic anchorage for deplaning Sector 42 cable tray Status: Issued | Not published | — |
| applied Feb 20 | #2024-020399-DFS-42-CO Commercial Building Permit · Addition T CORE - DFS-42 (DFS 240 for 20-124057-MG) - Stair 20 shop/erection drawings Status: Final | Not published | — |
| applied Feb 11 | #2024-020399-DFS-39-CO Commercial Building Permit · Addition T CORE - DFS-39 (DFS 237 for 20-124057-MG) - Seismic engineering for BHS conveyor and catwalk XO9-03, XO3-04, XO9-05 Status: Final | Not published | — |
| applied Feb 19 | #2025-013137-000-00-ET Electrical Permit · Addition/Alteration/Replacement Extend 3 circuits Status: Final | Not published | — |
| applied Feb 11 | #2025-011206-000-00-ET Electrical Permit · Addition/Alteration/Replacement Security camera install Status: Final | Not published | — |
| applied Jan 16 | #2024-040927-REV-04-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ESCAPE LOUNGE TI CONCOURSE D; REVISION TO DFS-01, FIN WALLS SUPPORT STEEL AND FRAMING Status: Final | Not published | $25K |
| applied Jan 22 | #2024-040927-REV-05-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ESCAPE LOUNGE TI CONCOURSE D; REVISION TO STRUCTURAL STEEL/CURB FOR VRF UNIT, CEILING, FINISHES AND PLUMB Status: Final | Not published | $20K |
| applied Nov 25 | #2024-040927-DFS-04-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ESCAPE LOUNGE TI CONCOURSE D; DFS SEISMIC BRACING FOR HVAC EQUIPMENT Status: Final | Not published | $22K |
| applied Dec 16 | #2024-050160-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL CAPERS CAFE DEPLANNING LVL TI; DFS FOR SEISMIC ANCHORAGE OF EXTERIOR CONDENSING UNIT RACK FOR WALK IN COOLER & FREEZER Status: Final | Not published | $720 |
| applied Dec 12 | #2024-040927-DFS-05-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX TERMINAL ESCAPE LOUNGE TI CONCOURSE D; DFS FOR SEISMIC ANCHORAGE OF GREASE TANK. GREASE TANK IS GROUND SUPPORTED AND WEIGHS 190 LBS. Status: Final | Not published | $2.5K |
| applied Nov 19 | #2024-026802-DFS-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ PDX SIZZLE PIE CONCOURSE D TI; DFS FOR WALK IN COOLER Status: Final | Not published | $50K |
| applied Nov 26 | #2024-100697-000-00-ET Electrical Permit · Addition/Alteration/Replacement Add 1 circuit. Status: Final | Not published | — |
| applied Sep 4 | #2024-020399-DFS-28-CO Commercial Building Permit · Addition T CORE - DFS-28 (DFS 226 for 20-124057-MG) - SCG1 side coiling grilles Status: Final | Not published | — |
| applied Nov 14 | #2024-097322-000-00-ET Electrical Permit · Addition/Alteration/Replacement 102942 Frontier Airline Casework - rework (3) circuits at Gate C16. Status: Final | Not published | — |
| applied Oct 8 | #2024-084221-000-00-SG Sign Permit · Alteration - Sign/Awning SINGLE PDF 2 of 2, REPLACE EXISTING SIGN WITH NEW SIGN (#105) ON THE EXISTING FREESTANDING STRUCTURE, NON-ILLUMINATED, EXISTING EXTERNAL LIGHTING TO BE REMOVED. w/ 24 084219/221 SG and 24-093965 SG Status: Final | Not published | — |
| applied Nov 7 | #2024-093965-000-00-SG Sign Permit · Alteration - Sign/Awning SINGLE PDF 3 of 3, REPLACE EXISTING SIGN WITH NEW SIGN (#103) ON THE EXISTING FREESTANDING STRUCTURE, NON-ILLUMINATED, EXISTING EXTERNAL LIGHTING TO BE REMOVED. w/ 24 084219/221 SG and 24-093965 SG Status: Final | Not published | — |
| applied Oct 8 | #2024-084219-000-00-SG Sign Permit · Alteration - Sign/Awning SINGLE PDF 1 of 2, REPLACE EXISTING SIGN WITH NEW SIGN (#104) ON THE EXISTING FREESTANDING STRUCTURE, NON-ILLUMINATED, EXISTING EXTERNAL LIGHTING TO BE REMOVED. w/ 24 084219/221 SG and 24-093965 SG Status: Final | Not published | — |
| applied Nov 7 | #2024-020399-DFS-37-CO Commercial Building Permit · Addition T CORE - DFS-37 (DFS 235 for 20-124057-MG) - Fiber IT rack seismic anchorage Status: Final | Not published | — |
| applied Nov 8 | #2024-020399-DFS-38-CO Commercial Building Permit · Addition T CORE - DFS-38 (DFS 236 for 20-124057-MG) - Generator room duct supports Status: Final | Not published | — |
| applied Nov 7 | #2024-095537-000-00-ET Electrical Permit · Addition/Alteration/Replacement 102968 Gate E7 Common Use - (4) circuits. Status: Final | Not published | — |
| applied Oct 2 | #2020-124057-REV-56-MG Major Project Groups · Addition T CORE - REV-56 - Occupant Safety Plan (OSP) - DP - D.8 Phase 2 demo plan Status: Issued | Not published | — |