Multifamily General Building, Electrical, Fire Protection work permitted December 4, 2024, with 26 permits through March 24, 2026, declaring $176,834 of work.
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
26 permits issued Dec 4 – Mar 24, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Feb 17 | #2025-100961-000-00-CO Commercial Building Permit · Alteration Modify 12th story patio guardrail Status: Under Inspection | Not published | $120K |
#2023-052714-DFS-14-CO Commercial Building Permit · New Construction DFS 14 - FLS Binder Status: Issued |
| Not published |
| — |
| applied Nov 12 | #2025-092058-000-00-ET Electrical Permit · New Construction 0-100A Traffic Signal Service Disconnect with single branch circuit Status: Final | Not published | — |
| applied Oct 31 | #2023-052714-DFS-05-CO Commercial Building Permit · New Construction Julia West - DFS-05 - Fall Protection Anchors Status: Final | Not published | — |
| applied Oct 2 | #2025-080551-000-00-FS Fire Systems Permit · New ALARM (SMOKE CONTROL) - STAIR PRESSURIZATION SYSTEM WITH FIREFIGHTER PANEL Status: Final | Not published | — |
| applied Aug 18 | #2023-052714-REV-02-CO Commercial Building Permit · New Construction REV 02 - Related to DFS 07. New steel railing profile and layout released in ASI 012. Status: Final | Not published | — |
| applied Sep 11 | #2025-073849-000-00-ET Electrical Permit · New Construction PBOT- NEW 60A SIGNAL SERVICE & BRANCH Status: Final | Not published | — |
| applied Aug 11 | #2023-052714-DFS-13-CO Commercial Building Permit · New Construction DFS 13 - Roof Patio Cable Guard Rail Status: Final | Not published | — |
| applied Aug 19 | #2025-065806-000-00-FS Fire Systems Permit · New HAZARDOUS/TANK - INSTALL (1) 350kW CATERPILLAR C13 DIESEL STANDBY GENERATOR WITH 654-GALLON UL-142 ABOVEGROUND FUEL TANK, (3) AUTOMATIC TRANSFER SWITCHES (200A AND 400A), AND A 1600A DOCKING STATION WITH KIRK KEY INTERLOCK. Status: Final | Not published | — |
| applied Aug 18 | #2025-066389-000-00-FS Fire Systems Permit · New UNDERGROUND - INSTALL 7FT OF 8" DUCTILE IRON FDC PIPE FROM PWB VALVE TO WITHIN 5FT OF BUILDING Status: Final | Not published | — |
| applied May 7 | #2023-052714-DFS-12-CO Commercial Building Permit · New Construction DFS 12 - Small sliding window at L12 Status: Final | Not published | — |
| applied Nov 18 | #2023-052714-DFS-06-CO Commercial Building Permit · New Construction DFS 06 - Glazed Aluminum Curtain Walls Status: Final | Not published | — |
| applied Aug 12 | #2025-064466-000-00-FS Fire Systems Permit · New ALARM (DAS) - EMERGENCY RESPONDER RADIO COVERAGE SYSTEM Status: Final | Not published | — |
| applied Jun 12 | #2023-052714-REV-04-CO Commercial Building Permit · New Construction REV 04 - Revise DFS 09 HVAC seismic anchorage Status: Final | Not published | — |
| applied Sep 23 | #2023-052714-DFS-03-CO Commercial Building Permit · New Construction DFS 03 - Suspended Ceilings Status: Final | Not published | — |
| applied Jun 25 | #2023-052714-REV-05-CO Commercial Building Permit · New Construction REV 05 - Revise patio door size to a smaller sliding window at level 12 and addition of adjacent single door. Status: Final | Not published | — |
| applied Apr 23 | #2023-052714-REV-03-CO Commercial Building Permit · New Construction REV 03 - Drawing revisions for fire protection detailing per granted appeal 33628. Added and revised suspended ceilings at elevator lobbies and Level 12 hallway. Added rated ceiling to Stair 1 enclosure at Level 12. Status: Final | Not published | $57K |
| applied Mar 5 | #2023-052714-DFS-11-CO Commercial Building Permit · New Construction DFS 11 - Metal Panel Supports and Attachments Status: Final | Not published | — |
| applied Mar 3 | #2025-015735-000-00-FS Fire Systems Permit · New ALARM - VOICE EVACUATION FIRE ALARM NOTIFICATION SYSTEM Status: Final | Not published | — |
| applied Nov 21 | #2023-052714-DFS-08-CO Commercial Building Permit · New Construction DFS 08 - Plumbing seismic anchorage Status: Final | Not published | — |
| applied Dec 4 | #2023-052714-DFS-09-CO Commercial Building Permit · New Construction DFS 09 - HVAC seismic anchorage Status: Final | Not published | — |
| applied Nov 14 | #2023-052714-DFS-07-CO Commercial Building Permit · New Construction DFS 07 - Metal Stairs (1&2) and ladders Status: Final | Not published | — |
| applied Dec 9 | #2023-052714-DFS-10-CO Commercial Building Permit · New Construction DFS 10 - Thin brick veneer support & attachments systems Status: Final | Not published | — |
| applied Oct 24 | #2023-052714-REV-01-CO Commercial Building Permit · New Construction REV 01 - Structural revisions to add rooftop equipment supports. Add floor drains at dwelling unit kitchens per appeal. Clarify fire protection detailing. Status: Final | Not published | — |
| applied Oct 14 | #2024-081636-000-00-FS Fire Systems Permit · New SPRINKLER - INSTALL A NEW WET FIRE SPRINKLER SYSTEM TO NURSING HOME HIGH RISE. INCLUDES ONE FIRE PUMP IN BASEMENT AND TWO AUTOMATIC STANDPIPES Status: Final | Not published | — |
| applied Sep 24 | #2023-052714-DFS-04-CO Commercial Building Permit · New Construction DFS 04 - Vinyl Windows Status: Final | Not published | — |