Multifamily General Building, Electrical, Hvac/Mechanical, Plumbing work permitted October 24, 2025, with 8 permits through September 8, 2026, declaring $222,900 of work.
SINGLE PDF - TENANT IMPROVEMENT FOR ADDITIONAL STRUCTURAL FRAMING TO SUPPORT ROOF-MOUNTED SOLAR PANELS. NO CHANGE OF OCCUPANCY. ***SEPARATE PERMIT REQUIRED FOR PANEL INSTALATION***
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
8 permits issued Oct 24 – Sep 8, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Sep 3 | #2026-019265-REV-01-ET Electrical Permit · Addition/Alteration/Replacement PDOX REVISION FOR PANEL SWAP AND CHANGE IN INTERCONNECTION Status: Final |
| Not published |
| — |
| applied Mar 13 | #2026-018561-000-00-CO Commercial Building Permit · Alteration SINGLEPDF - SOLAR INSTALLATION OF 60.33 KW ROOF MOUNTED PV SYSTEM ¿ ENGINEERED Status: Final | Not published | $24.9K |
| applied May 8 | #2025-103598-REV-01-CO Commercial Building Permit · Alteration SINGLE PDF - NON-VALUE-ADDED REVISION TO STRUCTURAL FRAMING DETAILS ON PLAN SHEET S2. Status: Final | Not published | — |
| applied May 1 | #2026-031840-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) SINGLEPDF - RELOCATE EXISTING VENTS FOR SOLAR PANEL Status: Final | Not published | — |
| applied May 8 | #2026-033951-000-00-PT Plumbing Permit · Addition/Alteration/Replacement Move plumbing vents for installation of new solar panels on roof. Status: Final | Not published | — |
| applied Mar 20 | #2026-019265-000-00-ET Electrical Permit · Addition/Alteration/Replacement PDOX 60.33 KWDC ENGINEERED, ROOF MOUNT, SOLAR SYSTEM PERMIT FOR STRUCTURAL STEEL PERMIT NUMBERS FOR WALNUT PARK PERMIT 25-103598-CO Status: Final | Not published | — |
| applied Feb 18 | #2025-103598-000-00-CO Commercial Building Permit · Alteration SINGLE PDF - TENANT IMPROVEMENT FOR ADDITIONAL STRUCTURAL FRAMING TO SUPPORT ROOF-MOUNTED SOLAR PANELS. NO CHANGE OF OCCUPANCY. ***SEPARATE PERMIT REQUIRED FOR PANEL INSTALATION*** Status: Final | Not published | $198K |
| applied Oct 10 | #2025-082791-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) SINGLEPDF - INSTALL HEAT PUMP Status: Final | Not published | — |