Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted October 2, 2025, with 16 permits through October 8, 2026.
UNDERGROUND - 2 1/2" FIRE SUPPLY LINE WITH DOUBLE CHECK VALVE IN A VAULT (FDC TO BE INSTALLED ON THE BUILDING)
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
16 permits issued Oct 2 – Oct 8, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 5 | #2026-073420-000-00-FS Fire Systems Permit · New UNDERGROUND - 2 1/2" FIRE SUPPLY LINE WITH DOUBLE CHECK VALVE IN A VAULT (FDC TO BE INSTALLED ON THE BUILDING) |
Status: Final
| Not published |
| — |
| applied Jul 28 | #2026-055384-000-00-ET Electrical Permit · Addition/Alteration/Replacement low voltage for 24-034218-MT Status: Under Inspection | Not published | — |
| applied Jun 10 | #2024-034218-REV-02-MT Mechanical Permit · New Construction JACKSON HOUSE MLK-REV-02-MT **w. 24-034217-REV-04-CO** - added mini-split system to supply air to IT room *Value Added Revision* Status: Issued | Not published | — |
| applied Jun 10 | #2024-034217-REV-04-CO Commercial Building Permit · New Construction JACKSON HOUSE MLK - **w. 24-034218-REV-02-MT** Revision to structural drawings for reorientation of beams and floor structure at outdoor patio, added mini-split system to supply air to IT room. Status: Final | Not published | — |
| applied Apr 23 | #2024-034217-REV-03-CO Commercial Building Permit · New Construction JACKSON HOUSE MLK -REV-03 - Revision to site utilities to show anticipated electrical and gas service routing to coordinate with utility providers and Public Works Permit. Enlarged fire vault, additional storm piping and concrete walkway on the development property have been included to help serve… Status: Under Inspection | Not published | — |
| applied May 12 | #2026-034886-000-00-PT Plumbing Permit · New Construction Install 200' of storm piping, install 1 manhole, install 4 catch basins. Status: Under Inspection | Not published | — |
| applied Nov 24 | #2024-034217-REV-01-CO Commercial Building Permit · New Construction JACKSON HOUSE MLK -REV-01- **w. 24-034218-REV-01-MT** Revision to include additional safety tie-off beams in the elevator hoist way as required by OSHA. Adjusted elevator shaft walls as required by elevator manufacturer. Revised RTU size to match actual, structural adjustments to account for size.… Status: Final | Not published | — |
| applied Nov 24 | #2024-034218-REV-01-MT Mechanical Permit · New Construction JACKSON HOUSE MLK - **w. 24-034217-REV-01-CO** Adjustments to plumbing layout to account for reorientation of shower rooms. Adjustments to roof plan & RTU schedule to capture change in RTU manufacturer. Status: Issued | Not published | — |
| applied Feb 20 | #2026-012986-000-00-ET Electrical Permit · New Construction Service and wiring for new two story building Status: Under Inspection | Not published | — |
| applied Nov 26 | #2024-034217-DFS-01-CO Commercial Building Permit · New Construction JACKSON HOUSE MLK - DFS-01 - Exterior storefront system Status: Under Inspection | Not published | — |
| applied Dec 30 | #2024-034217-DFS-02-CO Commercial Building Permit · New Construction JACKSON HOUSE MLK -DFS-02 - Roof Trusses and Floor Joists Status: Final | Not published | — |
| applied Nov 24 | #2024-034217-REV-02-CO Commercial Building Permit · New Construction JACKSON HOUSE MLK -REV-02- Revision to move the fire department connection from the site to the building Status: Under Inspection | Not published | — |
| applied Nov 10 | #2025-091351-000-00-FS Fire Systems Permit · New ALARM - NEW FIRE ALARM SYSTEM TO MEET CODE MINIMUM. NOTIFIER, HONEYWELL, SYSTEM SENSOR, AND SPACE AGE PARTS IN NEW CONSTRUCTION Status: Issued | Not published | — |
| applied Oct 16 | #2025-082921-000-00-FS Fire Systems Permit · New SPRINKLER - INSTALL A WET FIRE SPRINKLER SYSTEM WITH AN AUXILIARY ANTIFREEZE SYSTEM IN NEW BUILDING Status: Under Inspection | Not published | — |
| applied Oct 24 | #2025-087061-000-00-PT Plumbing Permit · New Construction plumbing new building Status: Under Inspection | Not published | — |
| applied Oct 2 | #2025-080456-000-00-ET Electrical Permit · Addition/Alteration/Replacement Fire Alarm, 2-Way, Security, & Structured Cabling System upgrades to code minimum. Status: Under Inspection | Not published | — |