Commercial Electrical, Hvac/Mechanical work permitted January 7, 2025, with 3 permits through March 11, 2025.
SINGLEPDF - ADDITION OF 3 NEW GAS UNIT HEATERS TO BE INSTALLED IN WAREHOUSE SPACE AS FREEZE PROTECTION; 1/2INCH 40 GAS PIPING TO UNITS CONNECTED TO EXISTING GAS LINE AND 3INCH B-VENT FROM UNITS THROUGH EXISTING WALL PENETRATION
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
3 permits issued Jan 7 – Mar 11, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Feb 4 | #2025-009112-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) SINGLEPDF - ADDITION OF 3 NEW GAS UNIT HEATERS TO BE INSTALLED IN WAREHOUSE SPACE AS FREEZE PROTECTION; 1/2INCH 40 GAS PIPING TO UNITS CONNECTED TO EXISTING GAS LINE AND 3INCH B-VENT FROM UNITS THROUGH EXISTING WALL PENETRATION Status: Final |
| — |
| applied Jan 31 | #2025-008366-000-00-ET Electrical Permit · Addition/Alteration/Replacement Installation of (2) new 20-amp single pole breakers to feed (5) new Natural Gas Freeze Protection Heaters. Status: Final | Not published | — |
| applied Jan 7 | #2025-001189-000-00-ET Electrical Permit · Addition/Alteration/Replacement Plumb and wire new card reader system Status: Final | Not published | — |