Get ProEvery project in every city · from $79/mo
Get Promultifamily project · Portland, OR
Multifamily General Building, Electrical, Fire Protection work permitted December 18, 2024, with 14 permits through November 14, 2025.
KAFOURY COURT - REV-03- see Revision Narrative 2nd page of application includes window header calcs, bicycle parking changes, lobby sf changed, ships ladder/stem wall change, Inspector requested change to guardrail height.
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
14 permits issued Dec 18 – Nov 14, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Sep 23 | #2022-204173-REV-03-CO Commercial Building Permit · New Construction KAFOURY COURT - REV-03- see Revision Narrative 2nd page of application includes window header calcs, bicycle parking changes, lobby sf changed, ships ladder/stem wall change, Inspector requested change to guardrail height. |
Status: Final
| Not published |
| — |
| applied Mar 13 | #2024-022467-000-00-ET Electrical Permit · New Construction Temp power Status: Final | Not published | — |
| applied May 30 | #2022-204173-DFS-12-CO Commercial Building Permit · New Construction KAFOURY COURT -DFS-12-CO - Glass Guardrail Systems Status: Final | Not published | — |
| applied Apr 22 | #2022-204173-DFS-11-CO Commercial Building Permit · New Construction KAFOURY COURT - DFS-11- Exterior Cladding System Status: Final | Not published | — |
| applied Oct 28 | #2022-204173-DFS-05-CO Commercial Building Permit · New Construction KAFOURY COURT - DFS-05 - Roof Access Ladder Status: Final | Not published | — |
| applied Feb 24 | #2022-204173-DFS-09-CO Commercial Building Permit · New Construction KAFOURY COURT -DFS-09 - Mechanical Equipment Anchorage Status: Final | Not published | — |
| applied Feb 26 | #2022-204173-DFS-10-CO Commercial Building Permit · New Construction KAFOURY COURT -DFS-10 - Vinyl Windows Status: Final | Not published | — |
| applied Jan 22 | #2022-204173-DFS-08-CO Commercial Building Permit · New Construction KAFOURY COURT - DFS-08 - Aluminum storefront Status: Final | Not published | — |
| applied Dec 31 | #2022-204173-REV-02-CO Commercial Building Permit · New Construction KAFOURY COURT - REV-02 - Void all drawings/calcs in DFS -04 for ships ladder and submitting new drawings/calculations Status: Final | Not published | — |
| applied Nov 13 | #2022-204173-DFS-06-CO Commercial Building Permit · New Construction KAFOURY COURT - DFS-06 - Fall Protection / Lifeline Supports Status: Final | Not published | — |
| applied Dec 6 | #2022-204173-DFS-07-CO Commercial Building Permit · New Construction KAFOURY COURT - DFS-07 - Curtain Wall / non structural metal framing Status: Final | Not published | — |
| applied Dec 18 | #2024-055810-000-00-FS Fire Systems Permit · New ALARM - INSTALL A NEW ADDRESSABLE CLASS B FIRE ALARM SYSTEM AND A NEW TWO WAY COMMUNICATION SIGNAL SYSTEM Status: Final | Not published | — |
| applied Dec 16 | #2024-055815-000-00-FS Fire Systems Permit · New ALARM (DAS) - PROVIDE A NEW EMERGENCY RESPONDER RADIO COMMUNICATION ENHANCEMENT SYSTEM (ERRCS) Status: Final | Not published | — |
| applied Oct 28 | #2022-204173-DFS-04-CO Commercial Building Permit · New Construction KAFOURY COURT - DFS-04 - Ship's Ladder Status: Final | Not published | — |