Get ProEvery project in every city · from $79/mo
Get Procommercial project · Portland, OR
Commercial Electrical, Plumbing work permitted March 13, 2025, with 2 permits through March 18, 2025.
PPD WILL procure all needed permits call 811 to locate all utilities confirm city sewer connection excavate at city sewer stub up to 14ft deep excavate at cleanout up to 4ft deep saw cut asphalt 30in wide up to 50ft in length open trench approx 50ft in length install 4in abs up to 50ft in length bed all piping in rock backfill with 100 % rock (parking lot and right of way) compacting to 100% replace asphalt 30in wide and up to 50ft in length
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
2 permits issued Mar 13 – Mar 18, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Mar 18 | #2025-021048-000-00-PT Plumbing Permit · Addition/Alteration/Replacement PPD WILL procure all needed permits call 811 to locate all utilities confirm city sewer connection excavate at city sewer stub up to 14ft deep excavate at cleanout up to 4ft deep saw cut asphalt 30in wide up to 50ft in length open trench approx 50ft in length install 4in abs up to 50ft in length… |
Status: Final
| Not published |
| — |
| applied Mar 13 | #2025-019543-000-00-ET Electrical Permit · Addition/Alteration/Replacement Add 3 phase ckt to motor (35A with 70A OCPD for motor start-up) Add 20A circuit for motor control circuit Status: Final | Not published | — |