Commercial General Building, Hvac/Mechanical, Plumbing work permitted November 14, 2024, with 16 permits through May 21, 2026, declaring $5,592,089 of work.
Connect new utilidor with redundant steam line to building, replace failed Vault 18 and associated site work **w/25-018343-MT**
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
16 permits issued Nov 14 – May 21, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Mar 31 | #2026-023138-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU LAMFORM BIOMED RESEARCH BUILDING GLASS WASHER STE 762 7TH FLR TI; LIKE FOR LIKE REPLACEMENT OF GLASS WASHER AND ELEC Status: Issued | Not published | $75K |
| applied May 18 | #2026-036148-000-00-FA Facility Permit · Alteration OHSU LBRB- install Paging system Status: Issued | Not published | — |
| applied May 18 | #2026-036150-000-00-FA Facility Permit · Alteration paging-OHSU LBRB- install Paging system Status: Issued | Not published | — |
| applied May 13 | #2026-035145-000-00-FA Facility Permit · Alteration power-OHSU LBRB FIRE PUMP UPGRADE LEVEL B3; REPLACE FIRE PUMP CONTROLLER FOR BUILDING, LIKE FOR LIKE Status: Final | Not published | — |
| applied Mar 16 | #2025-017576-DFS-03-CO Commercial Building Permit · Alteration DFS 03 - LBRB Areas B, C, and D Piping supports Status: Issued | Not published | — |
| applied Mar 31 | #2026-023136-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU LAMFORM BIOMED RESEARCH BUILDING GLASS WASHER STE 762 7TH FLR TI; LIKE FOR LIKE REPLACEMENT OF GLASS WASHER AND ELEC Status: Issued | Not published | — |
| applied Mar 18 | #2025-017576-DFS-04-CO Commercial Building Permit · Alteration DFS 04 - LBRB PRV Station Area A - Pipe Supports Status: Issued | Not published | — |
| applied Feb 12 | #2025-017576-DFS-02-CO Commercial Building Permit · Alteration DFS 02 - Ladders Status: Issued | Not published | — |
| applied Feb 19 | #2026-012715-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU LBRB FIRE PUMP UPGRADE LEVEL B3; REPLACE FIRE PUMP CONTROLLER FOR BUILDING, LIKE FOR LIKE Status: Final | Not published | $38K |
| applied Feb 19 | #2026-012714-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU LBRB FIRE PUMP UPGRADE LEVEL B3; REPLACE FIRE PUMP CONTROLLER FOR BUILDING, LIKE FOR LIKE Status: Issued | Not published | — |
| applied Dec 18 | #2025-017576-DFS-01-CO Commercial Building Permit · Alteration DFS 01 - Mechanical piping and equipment seismic bracing Status: Issued | Not published | — |
| applied Aug 28 | #2025-070203-000-00-PT Plumbing Permit · Addition/Alteration/Replacement ADD 1 FLOOR DRAIN TO UTILIDOR. Status: Final | Not published | — |
| applied Jun 19 | #2025-017576-REV-01-CO Commercial Building Permit · Alteration REV 01 - Revise steam and condensate routing to replace aging existing piping with new piping running through the Dillehunt Hall Bike Storage room rather than connecting to the existing piping in Manhole 17 (MH-17). Adjust layout in LBRB due to existing conditions. **25 018343 REV 01 MT** Status: Issued | Not published | — |
| applied Jun 19 | #2025-018343-REV-01-MT Mechanical Permit · Addition/Alteration/Replace (MT) REV 01 - Value added revision to change steam and condensate routing to replace aging existing piping with new piping running through the Dillehunt Hall Bike Storage room rather than connecting to the existing piping in Manhole 17 (MH-17). Adjust layout in LBRB due to existing conditions.… Status: Issued | Not published | — |
| applied Mar 12 | #2025-017576-000-00-CO Commercial Building Permit · Alteration Connect new utilidor with redundant steam line to building, replace failed Vault 18 and associated site work **w/25-018343-MT** Status: Under Inspection | Not published | $5.5M |
| applied Jul 10 | #2024-059497-000-00-FA Facility Permit · Alteration power- OHSU LBRB ENTRY DOOR REPLACEMENT LVL B1; MINOR DEMO, REPLACE EXTERIOR SOUTH ENTRY DOORS, FINISHES AND ELEC Status: Final | Not published | — |