Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing, Sign work permitted June 9, 2025, with 33 permits through August 7, 2026, declaring $2,108,797 of work.
UKANDU - renovation and addition for non-profit use and services **w. 25-020291-MT **demo of 118 SW Porter separate submittal see 25-012555-CO
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
33 permits issued Jun 9 – Aug 7, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jul 29 | #2026-054671-000-00-SG Sign Permit · New Sign/Awning |
SINGLE PDF - SIGN 2 OF 2 - NEW .74 SQFT ILLUMINATED ADDRESS SIGN ATTACHED TO CANOPY
Status: Final
| Not published |
| — |
| applied Jul 29 | #2026-054669-000-00-SG Sign Permit · New Sign/Awning SINGLE PDF - SIGN 1 OF 2 - NEW 1.49 SQFT ILLUMINATED SIGN ATTACHED TO CANOPY Status: Final | Not published | — |
| applied Mar 11 | #2025-020289-DFS-14-CO Commercial Building Permit · Addition UKANDU - DFS-14 - Decorative Metal Railings Status: Final | Not published | $20K |
| applied Mar 4 | #2025-020289-REV-02-CO Commercial Building Permit · Addition UKANDU - REV-02 - **4/17/26 added scope - detail reference at circulation/metal guardrail instead of glass/metal picket guardrail details***, see narrative, changes including door types, parking layout, windows , roof, lighting, garage door, updates from RFI process including architectural and… Status: Final | Not published | — |
| applied Mar 19 | #2025-020289-DFS-15-CO Commercial Building Permit · Addition UKANDU -DFS-15- Pipe & Tube Railing Status: Final | Not published | $2K |
| applied Mar 11 | #2025-020289-DFS-13-CO Commercial Building Permit · Addition UKANDU - DFS-13 - Interior Expansion Joint Cover Assemblies Status: Final | Not published | — |
| applied Jan 27 | #2025-020289-DFS-09-CO Commercial Building Permit · Addition UKANDU - DFS-09 - Decorative Metal Fence Status: Final | Not published | $20K |
| applied Nov 26 | #2025-096175-000-00-CO Commercial Building Permit · Alteration SINGLEPDF - SOLAR INSTALLATION OF 22.55KDC ROOF MOUNTED PV SYSTEM - ENGINEERED Status: Final | Not published | $22.5K |
| applied Mar 4 | #2025-020289-DFS-12-CO Commercial Building Permit · Addition UKANDU -DFS-12 - Ribbon Sculpture Attachment Status: Final | Not published | $2K |
| applied Feb 25 | #2025-020289-DFS-11-CO Commercial Building Permit · Addition UKANDU -DFS-11- Hanging Dome Status: Final | Not published | $10K |
| applied Mar 3 | #2026-015022-000-00-FS Fire Systems Permit · New UNDERGROUND - INSTALL 10' OF NEW 4" FIRE LINE AND CONNECT 2' FROM OUTSIDE OF THE BUILDING Status: Final | Not published | — |
| applied Feb 3 | #2025-020289-DFS-10-CO Commercial Building Permit · Addition UKANDU -DFS-10 - Pedestal Paver Status: Final | Not published | $20K |
| applied Dec 22 | #2025-020289-DFS-07-CO Commercial Building Permit · Addition UKANDU -DFS-07 - Rock Wall and Attachments Status: Final | Not published | $15K |
| applied Dec 2 | #2025-020289-DFS-03-CO Commercial Building Permit · Addition UKANDU -DFS-03 - Metal Panel Fixing/Support Systems for Wall Panels (included in DFS list on G1.001) Status: Final | Not published | $86K |
| applied Jan 2 | #2025-020289-DFS-08-CO Commercial Building Permit · Addition UKANDU -DFS-08- Masonry Veneer Ties Status: Final | Not published | $10K |
| applied Oct 31 | #2025-020289-REV-01-CO Commercial Building Permit · Addition UKANDU -REV-01-**w. 25-020291-REV-01-MT** - Revision to roof slopes, drainage and fall protection on the roof addition. The slope change includes adjustments to glulam roof joists. Revisions to rooftop equipment locations and ductwork for architectural and structural coordination. Revision of load… Status: Final | Not published | — |
| applied Nov 7 | #2025-020289-DFS-05-CO Commercial Building Permit · Addition UKANDU -DFS-05 - Fall Protection Status: Final | Not published | — |
| applied Oct 31 | #2025-020291-REV-01-MT Mechanical Permit · Addition/Alteration/Replace (MT) UKANDU-REV-01-MT **w. 25-020289-REV-01-CO** Revision to roof slopes, rooftop equipment locations and ductwork, DFS list. See CO REV-01 for additional work description. Status: Final | Not published | — |
| applied Nov 6 | #2025-020289-DFS-04-CO Commercial Building Permit · Addition UKANDU - DFS-04- I-Joists Status: Final | Not published | — |
| applied Nov 8 | #2025-020289-DFS-06-CO Commercial Building Permit · Addition UKANDU -DFS-06 - Attachment of Mechanical Equipment Status: Final | Not published | — |
| applied Oct 14 | #2025-080234-000-00-ET Electrical Permit · Addition/Alteration/Replacement PDOX 251045 NEW ELECTRICAL SERVICE, DISTRIBUTION, LIGHTING, AND BRANCH CIRCUITS Status: Final | Not published | — |
| applied Oct 8 | #2025-020289-DFS-02-CO Commercial Building Permit · Addition UKANDU - DFS-02- Fixed-in-Place custom landscape elements Status: Final | Not published | $75K |
| applied Nov 26 | #2025-096262-000-00-ET Electrical Permit · Addition/Alteration/Replacement ELECTRICAL INSTALLATION OF 22.55KW SOLAR SYSTEM Status: Final | Not published | — |
| applied Aug 28 | #2025-020289-DFS-01-CO Commercial Building Permit · Addition UKANDU - DFS-01- PT Slab Status: Final | Not published | $191K |
| applied Oct 8 | #2025-082236-000-00-ET Electrical Permit · New Construction LV stats to branchbox to unit outdoors Status: Final | Not published | — |
| applied Sep 8 | #2025-071074-000-00-FS Fire Systems Permit · Alteration ALARM - INSTALL A NEW ADDRESSABLE FIRE ALARM SYSTEM TO CODE MINIMUM (+28 SPEAKER/STROBES) Status: Final | Not published | — |
| applied Aug 26 | #2025-069096-000-00-ET Electrical Permit · Addition/Alteration/Replacement Fire Alarm, 2-Way, Electronic Security, Structured Cabling, & Audio Distribution System upgrades to code minimum. Status: Final | Not published | — |
| applied Jul 17 | #2025-057683-000-00-PT Plumbing Permit · Addition/Alteration/Replacement NEW PLUMBING FIXTURES, EQUIPMENT AND PIPING FOR ADDITION AND REMODEL. Status: Final | Not published | — |
| applied Jul 15 | #2025-056421-000-00-PT Plumbing Permit · New Construction Installation of 71 ln ft of 6" storm piping, 2 new drywells, 1 ea SD manhole, on backwater valve, 20 ln ft of 12" storm piping, 1 new storm catch basin, 24 ln ft 6" sanitary sewer piping, 1 6" sanitary sewer cleanout, 4 ln ft of 2" domestic water piping, 4 ln ft 4" dia fire water piping Status: Final | Not published | — |
| applied Jul 3 | #2025-049112-000-00-FS Fire Systems Permit · Alteration SPRINKLER - INSTALL SPRINKLER PROTECTION WITHIN THE BUILDING PER NFPA 13 2019 Status: Final | Not published | — |
| applied Mar 26 | #2025-020291-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) UKANDU - **w. 25-020289-CO** New HVAC system for addition and remodel including ventilation systems, exhaust systems and split system heat pumps.**INCLUDED GAS PIPING ON P SHEETS** Status: Final | Not published | — |
| applied Mar 26 | #2025-020289-000-00-CO Commercial Building Permit · Addition UKANDU - renovation and addition for non-profit use and services **w. 25-020291-MT **demo of 118 SW Porter separate submittal see 25-012555-CO Status: Final | Not published | $1.7M |
| applied Jun 9 | #2025-045335-000-00-PT Plumbing Permit · New Construction Cap existing sewer during demolition Status: Final | Not published | — |