Commercial General Building, Electrical work permitted December 4, 2024, with 42 permits through August 25, 2026, declaring $2,691,241 of work.
SINGLE PDF PROCESS/ OHSU RLSB ROOF EXPANSION JOINT REPLACEMENT 5TH FLR; REPLACE ROOF EXPANSION JOINT 5TH FLR BETWEEN N & S TOWERS
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
42 permits issued Dec 4 – Aug 25, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Aug 25 | #2026-063359-000-00-FA Facility Permit · Alteration Audio-video- OHSU-AV Systems refit for 9 PSU classrooms Status: Final | Not published | — |
#2026-063355-000-00-FA Facility Permit · Alteration OHSU-AV Systems refit for 9 PSU classrooms Status: Issued |
| Not published |
| — |
| applied Jun 16 | #2026-044296-000-00-FA Facility Permit · Alteration OHSU RLSB lecture halls LH3A003A & B upgrade to AV system Status: Issued | Not published | — |
| applied Jun 16 | #2026-044299-000-00-FA Facility Permit · Alteration Audio-Video-OHSU RLSB lecture halls LH3A003A & B upgrade to AV system Status: Final | Not published | — |
| applied May 28 | #2026-034102-000-00-FA Facility Permit · Alteration power-RLSB P2 car chargers, 2 new 208V 60A car chargers Status: Final | Not published | — |
| applied Mar 3 | #2026-015725-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB FOOD RESOURCE CENTER STE 1S050; DEMO WALLS, NEW INTERIOR STOREFRONT, REMODEL FOOD STORAGE RM, FOOD EXCHANGE AREA, COLD RM, ENTRY, CEILING, FLOORING, FINISHES, PLUMB AND ELEC, INSTALL 1-SINK, DEMO 2-SINKS, 1-FLOOR SINK, 1-WATER FILTER Status: Final | Not published | — |
| applied May 11 | #2026-034100-000-00-FA Facility Permit · Alteration RLSB P2 car chargers, 2 new 208V 60A car chargers Status: Issued | Not published | — |
| applied Feb 20 | #2026-013074-000-00-FA Facility Permit · Alteration power, data, sound mask & security -OHSU RLSB FOOD RESOURCE CENTER STE 1S050; DEMO WALLS, NEW INTERIOR STOREFRONT, REMODEL FOOD STORAGE RM, FOOD EXCHANGE AREA, COLD RM, ENTRY, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Final | Not published | — |
| applied Apr 9 | #2026-025690-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB ROOF EXPANSION JOINT REPLACEMENT 5TH FLR; REPLACE ROOF EXPANSION JOINT 5TH FLR BETWEEN N & S TOWERS Status: Final | Not published | $1.4M |
| applied Apr 9 | #2026-013025-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB FOOD RESOURCE CENTER STE 1S050; REVISION TO ENTRY DOOR AND FINISHES Status: Final | Not published | $18.2K |
| applied Oct 23 | #2025-086562-000-00-FA Facility Permit · Alteration power-OHSU RLSB SCHOOL OF DENTISTRY MICROSCOPE REPLACEMENT RM 11N040 11TH FLR; MINOR DEMO, INSTALL EQUIPMENT, CEILING, FINISHES AND ELEC Status: Final | Not published | — |
| applied Apr 9 | #2026-025688-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB ROOF EXPANSION JOINT REPLACEMENT 5TH FLR; REPLACE ROOF EXPANSION JOINT 5TH FLR BETWEEN N & S TOWERS Status: Issued | Not published | — |
| applied Mar 26 | #2026-021828-000-00-FA Facility Permit · Alteration OHSU RLSB classroom S019 AV system upgrade Status: Issued | Not published | — |
| applied Mar 26 | #2026-021829-000-00-FA Facility Permit · Alteration AV-OHSU RLSB classroom S019 AV system upgrade Status: Final | Not published | — |
| applied Apr 9 | #2025-027821-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY LVL 10 TI; DEMO WALLS, NEW WALLS CREATE STORAGE RM, LAB RM, CEILING, FLOORING, FINISHES, PLUMB AND ELEC, 1-EEW, 1-MIXING VALVE, 1-HOT WATER DISPENSER, 1-SINK Status: Final | Not published | — |
| applied Feb 20 | #2026-013025-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB FOOD RESOURCE CENTER STE 1S050; DEMO WALLS, NEW INTERIOR STOREFRONT, REMODEL FOOD STORAGE RM, FOOD EXCHANGE AREA, COLD RM, ENTRY, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Final | Not published | $309K |
| applied Mar 3 | #2026-015504-000-00-FA Facility Permit · Alteration RLSB 7N040 120V to 208V receptacle for freezer Status: Issued | Not published | — |
| applied Mar 3 | #2026-015507-000-00-FA Facility Permit · Alteration power-RLSB 7N040 120V to 208V recept for freezer Status: Final | Not published | — |
| applied Feb 20 | #2026-013023-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB FOOD RESOURCE CENTER STE 1S050; DEMO WALLS, NEW INTERIOR STOREFRONT, REMODEL FOOD STORAGE RM, FOOD EXCHANGE AREA, COLD RM, ENTRY, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Issued | Not published | — |
| applied Jan 13 | #2026-002868-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY LVL 10 TI; ADD 1 NEW HORN STROBE, EXTEND NAC AND SPEAKER CIRCUIT TO NEW DEVICE, LOWER EXISTING DEVICES TO NEW GRID FROM SHELL SPACE, 1 STROBE, 2 HORN STROBES Status: Final | Not published | $7.8K |
| applied Jan 5 | #2026-000924-000-00-FA Facility Permit · Alteration sensor cabling- RLSB parking garage siemens air quality sensor Status: Final | Not published | — |
| applied Jan 5 | #2026-000738-000-00-FA Facility Permit · Alteration RLSB auto doors; auto doors south rest rooms 3rd and 4th floors and learning studio doors 3A001 and 3A002 Status: Issued | Not published | — |
| applied Jan 5 | #2026-000740-000-00-FA Facility Permit · Alteration power-RLSB auto doors; auto doors south rest rooms 3rd and 4th floors and learning studio doors 3A001 and 3A002 Status: Final | Not published | — |
| applied Jan 5 | #2026-000742-000-00-FA Facility Permit · Alteration RLSB parking garage siemens air quality sensor Status: Issued | Not published | — |
| applied Jan 5 | #2026-000744-000-00-FA Facility Permit · Alteration power-RLSB parking garage siemens air quality sensor Status: Final | Not published | — |
| applied Dec 3 | #2025-097184-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY MICROSCOPE REPLACEMENT RM 11N040 11TH FLR; RELOCATE AND/OR ADD FIRE SPRINKLERS TO ACCOMMODATE TENANT IMPROVEMENT, 26 HEADS Status: Final | Not published | $4.4K |
| applied Mar 26 | #2025-023412-000-00-FA Facility Permit · Alteration power, fire alarm, data-OHSU RLSB SCHOOL OF DENTISTRY LVL 10 TI; DEMO WALLS, NEW WALLS TO CREATE STORAGE RM, LAB RM, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Final | Not published | — |
| applied Oct 22 | #2025-086445-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY MICROSCOPE REPLACEMENT RM 11N040 11TH FLR; MINOR DEMO, INSTALL EQUIPMENT, CEILING, FINISHES AND ELEC Status: Final | Not published | $55K |
| applied Mar 20 | #2025-021425-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY LVL 10 TI; INSTALL DUCTWORK, GRILLES, DIFFUSERS, PIPING AND ELEC Status: Final | Not published | $70.2K |
| applied Jul 30 | #2025-061425-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY LVL 10 TI; DEMO WALLS, NEW WALLS TO CREATE STORAGE RM, LAB RM, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Final | Not published | $394K |
| applied Oct 22 | #2025-086443-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY MICROSCOPE REPLACEMENT RM 11N040 11TH FLR; MINOR DEMO, INSTALL EQUIPMENT, CEILING, FINISHES AND ELEC Status: Issued | Not published | — |
| applied Aug 18 | #2025-066588-000-00-ET Electrical Permit · Addition/Alteration/Replacement AV CABLING AND SYSTEM REFIT Status: Final | Not published | — |
| applied Jun 11 | #2025-046384-000-00-FA Facility Permit · Alteration power-OHSU RLSB LAB VACUUM PUMP REPLACEMENT LVL P2; MINOR DEMO, INSTALL PUMPS, FINISHES, PIPING AND ELEC Status: Final | Not published | — |
| applied Jun 9 | #2025-045279-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB LAB VACUUM PUMP REPLACEMENT LVL P2; MINOR DEMO, INSTALL PUMPS, FINISHES, PIPING AND ELEC Status: Final | Not published | $234K |
| applied Jun 9 | #2025-045278-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB LAB VACUUM PUMP REPLACEMENT LVL P2; MINOR DEMO, INSTALL PUMPS, FINISHES, PIPING AND ELEC Status: Issued | Not published | — |
| applied Mar 26 | #2025-023409-000-00-FA Facility Permit · Alteration power, data-OHSU RLSB MICROSCOPE REPLACEMENT 11TH FLR TI; MINOR DEMO, REMODEL GRAD OPERATORY RM, REPLACE MICROSCOPES, CEILING, FINISHES AND ELEC Status: Final | Not published | — |
| applied Mar 20 | #2025-021631-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB MICROSCOPE REPLACEMENT 11TH FLR TI; MINOR DEMO, REMODEL GRAD OPERATORY RM, REPLACE MICROSCOPES, CEILING, FINISHES AND ELEC Status: Final | Not published | $174K |
| applied Mar 20 | #2025-021628-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB MICROSCOPE REPLACEMENT 11TH FLR TI; MINOR DEMO, REMODEL GRAD OPERATORY RM, REPLACE MICROSCOPES, CEILING, FINISHES AND ELEC Status: Issued | Not published | — |
| applied Mar 19 | #2025-021422-000-00-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB SCHOOL OF DENTISTRY LVL 10 TI; DEMO WALLS, NEW WALLS TO CREATE STORAGE RM, LAB RM, CEILING, FLOORING, FINISHES, PLUMB AND ELEC Status: Issued | Not published | — |
| applied Dec 17 | #2024-105682-000-00-FA Facility Permit · Alteration OHSU RLS LAB/OFFICE 7TH FL, TI - PROVIDE DETECTION & CONTROLS FOR CET-NMR ROOM 7N040A Status: Final | Not published | — |
| applied Dec 2 | #2024-046726-REV-01-FA Facility Permit · Alteration SINGLE PDF PROCESS/ OHSU RLSB DENTAL SCANNER REPLACEMENT LVL 11 & 12; REVISION TO ADD LEAD LINED DOOR AND FINISHES Status: Final | Not published | $32K |
| applied Nov 21 | #2022-121150-DFS-02-FA Facility Permit · Alteration FULL PROJECTDOX/ OHSU RLS LAB/OFFICE 7TH FL, TI; DFS FOR SEISMIC ANCHORAGE OF LAB EQUIPMENT Status: Final | Not published | $10K |