Commercial Electrical work permitted May 14, 2025, with 2 permits through August 18, 2025.
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
2 permits issued May 14 – Aug 18, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Aug 18 | #2025-066787-000-00-ET Electrical Permit · Addition/Alteration/Replacement Relocate Gate Power and low-volt conduits. Status: Final | Not published | — |
| applied May 14 | #2025-037938-000-00-ET Electrical Permit · Addition/Alteration/Replacement |
Replace existing dimming system: (1) 208V, 300A, 3PH, & (1) 208V, 225A, 3PH Feeders & Panels. (55) Reconfigured Circuits.
Status: Final
| Not published |
| — |