Commercial General Building, Electrical, Fire Protection, Plumbing work permitted January 24, 2025, with 29 permits through September 2, 2026, declaring $2,956,000 of work.
SINGLE PDF - DFS FOR METAL PANEL SIDING AND ATTACHMENT
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
29 permits issued Jan 24 – Sep 2, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Mar 27 | #2025-023907-000-00-ET Electrical Permit · New Construction 400A temp power pole Status: Final | Not published | — |
| applied Feb 25 | #2025-014908-000-00-ET Electrical Permit · New Construction 200A temp power pole Status: Final | Not published | — |
| applied Jan 20 | #2025-093111-000-00-CO Commercial Building Permit · Alteration PDOX - 1ST TIME TI, INSTALL SELF STORAGE UNITS ON ALL FLOORS. Status: Under Inspection | Not published | $416K |
| applied May 27 | #2026-037746-000-00-FS Fire Systems Permit · New HAZARDOUS/TANK - INSTALLATION AND FILL OF EMERGENCY BACK UP DIESEL GENERATOR WITH 20" 531-GALLON DOUBLE WALL UL142 BASETANK. Status: Final | Not published | — |
| applied Feb 23 | #2023-054809-DFS-16-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR MECHANICAL UNIT ANCHORAGE AT CONCRETE T-WALL PACKAGE Status: Under Inspection | Not published | $15K |
| applied Feb 22 | #2025-020310-REV-01-ET Electrical Permit · New Construction PDOX - REVISION FOR ELECTRICAL Status: Final | Not published | — |
| applied Mar 12 | #2026-018104-000-00-ET Electrical Permit · New Construction Installation of low voltage HVAC controls, including thermostats and other sensors Status: Final | Not published | — |
| applied Jan 21 | #2023-054809-DFS-15-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR GUARDRAILS Status: Under Inspection | Not published | $50K |
| applied Mar 19 | #2023-054809-DFS-02-CO Commercial Building Permit · New Construction SINGLE PDF - SCULPTURE AS REQUIRED PER 17-266132-DZM Status: Under Inspection | Not published | — |
| applied Nov 25 | #2023-054809-DFS-13-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR MECHANICAL UNIT ANCHORAGE Status: Under Inspection | Not published | $200K |
| applied Nov 17 | #2023-054809-DFS-12-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR LEVEL 2 TO LEVEL 6 WINDOWS ATTACHMENT Status: Under Inspection | Not published | $640K |
| applied Sep 24 | #2023-054809-DFS-11-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR STEEL JOISTS AND GIRDERS Status: Under Inspection | Not published | $350K |
| applied Sep 9 | #2023-054809-DFS-07-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR STOREFRONT, WINDOWS AND DOORS SYSTEM Status: Under Inspection | Not published | $10K |
| applied May 29 | #2023-054809-REV-01-CO Commercial Building Permit · New Construction PDOX PS - REVISION TO REMOVE MEZZANINE, MOVE RESTROOM, ADD UNISEX RESTROOM, ELIMINATE 1 RETENTION POND, INSTALL STORM WATER FILTER, STRUCTURAL REVISIONS. ALL CHANGES ARE ON SITE AND 1ST FLOOR, NO CHANGES TO FLOORS 2-6. w/23-055658-REV-01-MT Status: Under Inspection | Not published | — |
| applied Aug 25 | #2023-054809-DFS-06-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR SHIP LADDER Status: Under Inspection | Not published | $15K |
| applied Sep 15 | #2023-054809-DFS-09-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR STEEL FIREPROOFING Status: Under Inspection | Not published | — |
| applied Sep 19 | #2023-054809-DFS-10-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR METAL PANEL SIDING AND ATTACHMENT Status: Final | Not published | $1.1M |
| applied Sep 10 | #2023-054809-DFS-08-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR FIRE PUMP ANCHORAGE Status: Under Inspection | Not published | $10K |
| applied Aug 21 | #2023-054809-DFS-05-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR SECURITY FENCE Status: Under Inspection | Not published | $175K |
| applied Aug 5 | #2025-060534-000-00-FS Fire Systems Permit · New SPRINKLER & UNDERGROUND - INSTALL ONE WET FIRE SPRINKLER SYSTEM WITH VERTICAL IN-LINE TURBINE FIRE PUMP, ONE WET COMBO STANDPIPE W/ FLOOR CONTROL VALVES, ONE WET STANDPIPE W/ HOSE VALVES, ONE DRY PIPE SPRINKLER SYSTEM Status: Final | Not published | — |
| applied May 21 | #2023-054809-DFS-03-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR STEEL TOWER STAIRS Status: Under Inspection | Not published | $200K |
| applied Jun 3 | #2025-041165-000-00-FS Fire Systems Permit · New ALARM (SMOKE CONTROL) - STAIRWAY PRESSURIZATION/SMOKE CONTROL Status: Issued | Not published | — |
| applied Jun 26 | #2025-050453-000-00-FS Fire Systems Permit · New ALARM - EMERGENCY RESPONDER RADIO COVERAGE SYSTEM. Status: Issued | Not published | — |
| applied Mar 18 | #2025-020310-000-00-ET Electrical Permit · New Construction PDOX - ELECTRICAL FOR NEW SIX STORY SELF STORAGE BUILDING WITH RETAIL/OFFICE ON THE MAIN FLOOR ALONG WITH STORAGE OPERATIONS Status: Final | Not published | — |
| applied Apr 2 | #2025-025438-000-00-FS Fire Systems Permit · New ALARM - INSTALL FIRE ALARM SPRINKLER MONITORING SYSTEM AND ALARMS WITH NOTIFICAITON SYSTEM. Status: Final | Not published | — |
| applied Feb 26 | #2025-007019-000-00-FS Fire Systems Permit · New UNDERGROUND - INSTALL UNDERGROUND FIRE LINE AND 6" ABOVE GROUND RPDA Status: Final | Not published | — |
| applied Mar 11 | #2025-018935-000-00-PT Plumbing Permit · New Construction Installing a plumbing system into a self-storage building. Status: Final | Not published | — |
| applied Dec 18 | #2023-054809-DFS-01-CO Commercial Building Permit · New Construction SINGLE PDF - DFS FOR FOUNDATION AUGER DRILLED CONCRETE CAST PILES Status: Under Inspection | Not published | — |
| applied Jan 23 | #2025-005434-000-00-PT Plumbing Permit · New Construction SEWER, STORM AND WATER SYSTEMS Status: Final | Not published | — |