Get ProEvery project in every city · from $79/mo
Get Procommercial project · Portland, OR
Commercial Electrical work permitted February 11, 2026, with 5 permits through September 4, 2026.
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
5 permits issued Feb 11 – Sep 4, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Sep 4 | #2026-066195-000-00-ET Electrical Permit · Addition/Alteration/Replacement Life safety panel connection Status: Final | Not published | — |
| applied Aug 18 | #2026-061501-000-00-ET Electrical Permit · Addition/Alteration/Replacement |
Install (2) new duplex receptacles on Level 1 of parking structure on SW 2nd Ave, (1) near corner of SW Jefferson St and (1) near corner of SW Madison St. Install (1) new duplex receptacle on Level 2 of parking structure on SW 1st Ave. Replace (1) existing 2-pole 40a breaker with (1) new 1-pole…
Status: Final
| Not published |
| — |
| applied Jun 12 | #2026-043189-000-00-ET Electrical Permit · Addition/Alteration/Replacement 261041 - OPCONNECT 1ST AND JEFFERSON 5TH AND 6TH FLOORS EVCS Status: Final | Not published | — |
| applied Apr 15 | #2026-027330-000-00-ET Electrical Permit · Addition/Alteration/Replacement 254973 - Install (7) Make ready EVCS locations Status: Final | Not published | — |
| applied Jan 27 | #2026-005890-000-00-ET Electrical Permit · New Construction PDOX (1) 1200A SERVICE, (3) 400AMP PANELS, (49) BRANCH CIRCUITS FOR CAR CHARGERS Status: Final | Not published | — |