Commercial General Building, Hvac/Mechanical work permitted August 24, 2026, with 2 permits through August 24, 2026, declaring $3,700,000 of work.
PDOX - REMOVE SULFONATION EQUIPMENT, INSTALL SOLVENT EXTRACTION SKID, STEAM BOILER, TANKS, PROCESS PIPING. **w/ 26-024053 MT**
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
2 permits issued Aug 24 – Aug 24, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Apr 22 | #2026-024046-000-00-CO Commercial Building Permit · Alteration PDOX - REMOVE SULFONATION EQUIPMENT, INSTALL SOLVENT EXTRACTION SKID, STEAM BOILER, TANKS, PROCESS PIPING. **w/ 26-024053 MT** Status: Issued | Not published | $3.7M |
#2026-024053-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) *PDOX - MECHANICAL WORK FOR NEW SOLVENT EXTRACTION SYSTEM. **W/ 26-024046 CO** Status: Issued |