Commercial Electrical, Fire Protection, Hvac/Mechanical work permitted October 31, 2024, with 20 permits through October 30, 2026.
Portland’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
20 permits issued Oct 31 – Oct 30, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 30 | #2026-080539-000-00-ET Electrical Permit · Addition/Alteration/Replacement REMOVE AND REPLACE (3) RTUs Status: Issued | Not published | — |
#2026-057921-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) SINGELPDF - LIKE FOR LIKE REPLACEMENT OF (3) RTUS Status: Issued |
| Not published |
| — |
| applied Nov 12 | #2025-092445-000-00-ET Electrical Permit · Addition/Alteration/Replacement 1 CIRCUIT FOR AIR COMPRESSOR, 1 CIRCUIT FOR EDPA DEVICE. Status: Final | Not published | — |
| applied Sep 18 | #2025-076211-000-00-ET Electrical Permit · Addition/Alteration/Replacement WO 111479 - CCTV SECURITY SYSTEMS Status: Final | Not published | — |
| applied Sep 11 | #2025-072380-000-00-FS Fire Systems Permit · Addition ALARM - ADDITION OF MODULES FOR NEW DRY SYSTEMS. 2 DUAL MODULES TOTAL Status: Final | Not published | — |
| applied Aug 28 | #2025-067825-000-00-FS Fire Systems Permit · New SPRINKLER - DESIGN & INSTALL (2) NEW DRY FIRE SPRINKLER SYSTEMS THROUGHOUT EXISTING BUILDING. Status: Final | Not published | — |
| applied May 20 | #2025-036836-000-00-FS Fire Systems Permit · Alteration ALARM - FIRE PANEL UPGRADE. 2 SECURITY / FIRE COMBO PANELS INTO ONE MAIN PANEL. CORRECTING SPACING ISSUES & ADDING NOTIFICATION STROBES IN BATHROOMS. REPLACING EXISTING DEVICES WITH NEW ADDRESSABLE. REPLACING EXISTING NOTIFICATION WITH NEW DEVICES Status: Final | Not published | — |
| applied Mar 17 | #2025-020478-000-00-ET Electrical Permit · Addition/Alteration/Replacement INSTALL 120V TRANSFORMERS AND CONTROL WIRES FOR UNIT HEATERS. THREE CIRCUITS FOR HEATERS. PANEL 2E1-14,16,18 LOCATED UPSTAIRS IN BUILDING 2. Status: Final | Not published | — |
| applied Mar 17 | #2025-020560-000-00-ET Electrical Permit · Addition/Alteration/Replacement ADD/MODIFY ONE (1) BRANCH CIRCUIT FOR REPLACEMENT OF SITE LIGHT CIRCUITRY. Status: Final | Not published | — |
| applied Mar 5 | #2025-017065-000-00-ET Electrical Permit · Addition/Alteration/Replacement REPLACE CONNECTIONS AT GUARD SHACK, SEVEN CIRCUITS. Status: Final | Not published | — |
| applied Feb 28 | #2025-016186-000-00-ET Electrical Permit · Addition/Alteration/Replacement INSTALL 6 DATA DROPS, INSTALL 9 LIGHTS AND INSTALL 4 OUTLETS. Status: Final | Not published | — |
| applied Mar 4 | #2025-016901-000-00-ET Electrical Permit · Addition/Alteration/Replacement 82538-25 ITS STRUCTURED CABLING INFRASTRUCTURE FOR NEW DISPATCH OFFICE AREA. Status: Final | Not published | — |
| applied Feb 13 | #2025-009706-000-00-MT Mechanical Permit · Addition/Alteration/Replace (MT) SINGLEPDF -REPLACEMENT OF 15 GAS-FIRED LIKE FOR LIKE SUSPENDED UNIT HEATERS AND ONE GAS FURNACE Status: Final | Not published | — |
| applied Feb 20 | #2025-013780-000-00-ET Electrical Permit · Addition/Alteration/Replacement LIGHT INSTALL FOR CONFERENCE ROOM AND MID-DOCK OFFICES Status: Final | Not published | — |
| applied Feb 11 | #2025-011255-000-00-ET Electrical Permit · Addition/Alteration/Replacement SITE LIGHT REPAIR-MODIFY (1) BRANCH CIRCUIT Status: Final | Not published | — |
| applied Feb 4 | #2025-009066-000-00-ET Electrical Permit · Addition/Alteration/Replacement Reinstall wiring in ceiling of conference room. Install new circuits in break room and storage closet of shipping office. Status: Final | Not published | — |
| applied Jan 24 | #2025-005894-000-00-ET Electrical Permit · Addition/Alteration/Replacement 81002-24 add power for networking equipment Status: Final | Not published | — |
| applied Oct 3 | #2024-085188-000-00-FS Fire Systems Permit · New HAZARDOUS/TANK - LEGALIZE EXISTING ABOVE GROUND DIESEL TANKS AND ASSOCIATED EQUIPMENT. NO WORK IS PROPOSED HEREIN, PENDING AGENCY REVIEW AND INSPECTION. WILL COMPLY WITH ANY REQUIREMENTS DETERMINED DURING REVIEW AND INSPECTION. Status: Final | Not published | — |
| applied Nov 7 | #2024-095488-000-00-ET Electrical Permit · Addition/Alteration/Replacement alter 4 diesel dispensers Status: Final | Not published | — |
| applied Oct 31 | #2024-093812-000-00-ET Electrical Permit · Addition/Alteration/Replacement 70188-24: structured cabling infrastructure for voice/data/video applications. Status: Final | Not published | — |