Get ProEvery project in every city · from $79/mo
Get Procommercial project · Pittsburgh, PA
Commercial Demolition, Electrical, Fire Protection work permitted December 15, 2025, with 7 permits through April 30, 2026, declaring $710,000 of work. Contractor on record: Lugaila Mechanical Inc.
PHASED DEMOLITION. COMPLETE DEMOLITION OF REMAINING PORTIONS OF EXISTING FOUR-STORY BUILDING. LISTED AS PHASE II. PHASE 1 DEMO COMPLETED UNDER PERMIT DP-2025-06723
Pittsburgh permit records name Lugaila Mechanical Inc, Neumeyer Environmental Services, Inc. and Sargent Electric Co as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
7 permits issued Dec 15 – Apr 30, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
#DP-2026-01224 Demolition Permit · COMPLETE DEMOLITION PHASED DEMOLITION. COMPLETE DEMOLITION OF REMAINING PORTIONS OF EXISTING FOUR-STORY BUILDING. LISTED AS PHASE II. PHASE 1 DEMO COMPLETED UNDER PERMIT DP-2025-06723 Status: Issued | Neumeyer Environmental Services, Inc. | $680K | |
#EP-2025-09211 ELECTRICAL · MINOR ALTERATION Status: Completed | Lugaila Mechanical Inc | $10K | |
#EP-2025-07949 ELECTRICAL · ADDITION / ALTERATION ALTERATION TO THE EXISTING ELECTRICAL SYSTEM TO REMOVE AN EMERGENCY GENERATOR AND PROVIDE A CONNECTION TO A TEMPORARY EMERGENCY GENERATIOR. WORK INCLUDES NEW DISCONNECTION MEANS AND FEEDERS Status: Issued | Sargent Electric Co | $15K | |
#SSP-2025-08558 Suppression System Permit · MINOR ALTERATION MODIFY RISER FOR PARTAL DEMO Status: Completed | S & T Plumbing LLC | $5K | |
#EP-2025-08557 ELECTRICAL · MINOR ALTERATION Status: Completed | Lugaila Mechanical Inc | $5K | |
#FAS-2025-08609 Fire Alarm Permit · MINOR ALTERATION Status: Issued | Lugaila Mechanical Inc | $5K | |
#DP-2025-06723 Demolition Permit · PARTIAL DEMOLITION DEMOLITION OF THE REAR SINGLE-STORY ADDITION PORTION OF THE 1025 BEAVER AVE BUILDING AND THE REAR TWO-STORY ACCESSORY WORKSHOP BUILING. REPAIR OF EXISTING CONVEYOR OPENING BETWEEN PORTIONS OF THE BUILDING WITH NEW INFILL CONSTRUCTION. THIS DEMOLITION IS PHASE 1 OF 2. Status: Application Finalization | Neumeyer Environmental Services, Inc. | — |
In Pittsburgh, biggest first.