Commercial Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted September 23, 2025, with 4 permits through December 30, 2025. Contractor on record: Lor-Mar Mechanical Services LLC.
• Furnish and install [2] Water CLosets, [2] Lavatories, [22] Exam Room Sinks, [3] Breakroom Sinks. • Provide labor and material to extend from existing sanitary, vent and domestic water as shown. ********* installed to the 2018 Philadelphia Plumbing Code section 919(Philadelphia Single Stack/venting System****************
Philadelphia permit records name Lor-Mar Mechanical Services LLC, Madden Electric Associates, Inc and Preferred Fire Protection Inc as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
4 permits issued Sep 23 – Dec 30, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#PP-2025-009921 Plumbing Permit · Alterations • Furnish and install [2] Water CLosets, [2] Lavatories, [22] Exam Room Sinks, [3] Breakroom Sinks. • Provide labor and material to extend from existing sanitary, vent and domestic water as shown. ********* installed to the 2018 Philadelphia Plumbing Code section 919(Philadelphia Single… Status: Completed | Lor-Mar Mechanical Services LLC | — | |
#EP-2025-009678 Electrical Permit · Addition and/or Alteration MINOR ELECTRICAL DEMO. INSTALLING RECEPTACLES, LIGHTING, LIGHTING CONTROLS, STANDALONE NURSE CALL, SOUND MASKING, PATHWAYS ONLY FOR LOW VOLTAGE AS PER 2017 NEC. AMENDMENT: Install fire alarm system as per 2016 NFPA 72. Status: Completed | Madden Electric Associates, Inc | — | |
#FP-2025-002115 Fire Suppression Permit · Addition and/or Alterations EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. RELOCATE 112 FIRE SPRINKLER HEADS, FOR CHANGES TO 2ND FLOOR Status: Completed | Preferred Fire Protection Inc | — | |
#MP-2025-004029 Mechanical / Fuel Gas Permit · Addition and/or Alterations FOR AN ALTERATION TO AN EXISTING MECHANICAL SYSTEM TO ACCOMMODATE THE SECOND FLOOR LEVEL OF AN EXISTING STRUCTURE. PROPOSED APPLIANCES TO BE INSTALLED IN ACCORDANCE WITH THE MANUFACTURER’S SPECIFICATIONS. ** ALL WORK TO BE DONE PER APPROVED PLANS.** IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER… Status: Completed | Hunter Mechanical Inc | — |