FOR EXTERIOR ALTERATIONS (REPAIR OF EXTERIOR STAIRS) AS PER APPROVED PLANS AND IN ACCORDANCE WITH 2018 IEBC AND PHC APPROVAL. SEPARATE PERMITS REQUIRED FOR ALL OTHER WORK.
Philadelphia permit records name Lorenzon Bros Co, Guidi E P Inc and Pullman SST Inc as the contractors on this project, among 4 contractors in all.
The property owner is included with Pro.
5 permits issued Jul 8 – Jun 24, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#CP-2026-002752 Commercial Building Permit · Addition and/or Alteration |
Commercial and multifamily, biggest first.
FOR EXTERIOR ALTERATIONS (REPAIR OF EXTERIOR STAIRS) AS PER APPROVED PLANS AND IN ACCORDANCE WITH 2018 IEBC AND PHC APPROVAL. SEPARATE PERMITS REQUIRED FOR ALL OTHER WORK.
Status: Issued
| Lorenzon Bros Co |
| — |
#CP-2026-001016 Commercial Building Permit · Addition and/or Alteration FOR THE EXTERIOR ALTERATIONS WORK FOR ROOF FALL PROTECTION PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. SEPARATE PERMITS TO BE OBTAINED FOR ALL OTHER WORK. Status: Issued | Guidi E P Inc | — |
#CP-2026-000122 Commercial Building Permit · Addition and/or Alteration FOR LEVEL I ALTERATIONS (STRUCTURAL REPAIRS AND MAINTENANCE REPAIRS TO JOINT SEALS AND WATERPROOFING) TO AN EXISTING GROUP S-2 PARKING GARAGE AS PER APPROVED PLANS AND IN ACCORDANCE WITH 2018 IEBC. SEPARATE PERMITS TO BE OBTAINED FOR ALL OTHER WORK. Status: Issued | Pullman SST Inc | — |
#SP-2025-000910 Site / Utility Permit · Foundation INSTALLATION OF FOUNDATIONS FOR A PROPOSED SCULPTURE INSTALLATION AS PER APPROVED PLANS. *2018 IBC REVIEW* AMENDMENT 3/11/26 TO CHANGE DPRC-SI Status: Completed | P Agnes Inc | — |
#ZP-2025-005269 Zoning Permit · New construction, addition, GFA change FOR THE ERECTION OF ONSITE PUBLIC ART (FREE STANDING SCULPTURE). SIZE AND LOCATION AS SHOWN ON THE APPLICATION/PLAN. Status: Completed | Not published | — |