Commercial Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted December 16, 2025, with 6 permits through October 5, 2026. Contractor on record: MK Fire Protection & Supply, LLC.
Get new commercial permits near 19143 or Philadelphia, free weekly email
INSTALLATION OF 6" FIRE SERVICE MAIN WITH 6" ZURN/WILKINS 375 BACKFLOW PREVENTION ASSEMBLY (WITHIN HOT BOX) AND 4" WATER SERVICES TO FIVE (5) BUILDINGS ON SITE (REDUCED TO 2" AND 1" INSIDE BUILDINGS) AS PER APPROVED PLANS AND NFPA 24 STANDARD. ALL BUILDINGS INCLUDE MODULAR CONSTRUCTION WITH PRE-INSTALLED SPRINKLER SYSTEMS APPROVED BY PA DCED THIRD-PARTY AGENCY EXCEPT BUILDING 5 COMMUNITY SPACE (SEE PERMIT FP-2026-001505).
Philadelphia permit records name MK Fire Protection & Supply, LLC, DKM Mechancial and BBJ Mechanical Inc as the contractors on this project, among 5 contractors in all.
The property owner is included with Pro.
Commercial and multifamily, biggest first.
6 permits issued Dec 16 – Oct 5, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#FP-2026-002013 Fire Suppression Permit · New Construction INSTALLATION OF 6" FIRE SERVICE MAIN WITH 6" ZURN/WILKINS 375 BACKFLOW PREVENTION ASSEMBLY (WITHIN HOT BOX) AND 4" WATER SERVICES TO FIVE (5) BUILDINGS ON SITE (REDUCED TO 2" AND 1" INSIDE BUILDINGS) AS PER APPROVED PLANS AND NFPA 24 STANDARD. ALL BUILDINGS INCLUDE MODULAR CONSTRUCTION WITH… Status: Issued | Contractor with Pro | — | |
#FP-2026-001505 Fire Suppression Permit · New Construction FOR THE INSTALLATION OF SPRINKLER HEADS AND ASSOCIATED PIPING THROUGHOUT THE SITE-CONSTRUCTED COMMUNITY SPACE ONLY. TO BE CONNECTED TO THE SPRINKLER SYSTEM THROUGHOUT THE MODULAR PORTION OF THE BUILDING AND SERVED BY A SIX (6) INCH ON-SITE FIRE SERVICE MAIN AND SIX (6) INCH BACKFLOW PREVENTER… Status: Issued | MK Fire Protection & Supply, LLC | — | |
#MP-2026-000151 Mechanical / Fuel Gas Permit · New Construction FOR THE INSTALLATION OF REGISTERS, DIFFUSERS AND APPLIANCES WITH ASSOCIATED DUCTWORK. APPLIANCES TO BE INSTALLED IN ACCORDANCE WITH THE MANUFACTURER’S SPECIFICATIONS. ALL WORK TO BE DONE PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. Status: Issued | DKM Mechancial | — | |
#PP-2025-015403 Plumbing Permit · New Construction or Additions NEW CONSTRUCTION OF 2 SOTRY MODULAR BUILDING WITH USE OF A COMMUNITY CENTER AND 5 RESIDENTIAL DWELLING UNITS. INTERIOR INSTALLATION OF DRAINAGE, WASTE, VENT, AND WATER SUPPLY FOR LISTED FIXTURES. ALL WORK TO BE INSTALLED IN STRICT COMPLIANCE WITH 2018 PPC AND APPROVED PLANS Status: Issued | BBJ Mechanical Inc | — | |
#EP-2025-009702 Electrical Permit · New Construction Provide new incoming electrical service to each modular unit existing load center. Provide new building exterior light fixtures, receptacles, site lighting fixtures and temporary light and power. Make final electrical connections at each modular unit. Provide new lights, devices, lighting control,… Status: Completed | Anmar Electrical Contractor Inc | — | |
#PP-2025-015813 Plumbing Permit · New Construction or Additions INSTALL CT, FAI, MD & 2" WDP CURB IN. Status: Completed | John J Dougherty & Son Inc | — |