Commercial General Building, Demolition work permitted April 28, 2025, with 4 permits through September 9, 2026. Contractor on record: SD General Contractor.
NEW CONSTRUCTION OF A THREE-STORY BUILDING WITH BASEMENT AND PRIVATE ROOF DECKS WITH PILOT HOUSES FOR USE AS A THREE (3) FAMILY DWELLING AS PER APPROVED PLANS. SEE PERMIT SP-2025-000512 FOR ASSOCIATED EXCAVATION WORK AND PERMIT SP-2025-000510 FOR ASSOCIATED FOUNDATION WORK. BUILDING TO BE FULLY SPRINKLERED PER NFPA 13. *2018 IBC REVIEW* **SEPARATE PERMITS REQUIRED FOR MEP & FIRE SUPPRESSION WORK**
Philadelphia permit records name SD General Contractor and Raymond Smith as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
4 permits issued Apr 28 – Sep 9, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
Commercial and multifamily, biggest first.
#CP-2026-002790 Commercial Building Permit · New Construction NEW CONSTRUCTION OF A THREE-STORY BUILDING WITH BASEMENT AND PRIVATE ROOF DECKS WITH PILOT HOUSES FOR USE AS A THREE (3) FAMILY DWELLING AS PER APPROVED PLANS. SEE PERMIT SP-2025-000512 FOR ASSOCIATED EXCAVATION WORK AND PERMIT SP-2025-000510 FOR ASSOCIATED FOUNDATION WORK. BUILDING TO BE FULLY… Status: Issued |
| SD General Contractor |
| — |
#SP-2025-000510 Site / Utility Permit · Foundation FOR THE ERECTION OF CONCRETE FOUNDATION FOR NEW CONSTRUCTION WORK. SEE PERMIT #SP-2025-000512 FOR EXCAVATION AND UNDERPINNING WORK. SEPARATE PERMIT REQUIRED FOR NEW CONSTRUCTION WORK. AMENDMENT APPROVED AS OF 03/25/2026: FOR REVISIONS TO FOUNDATION/ CONCRETE FOOTINGS, COLUMN BASE PLATE & ANCHOR… Status: Issued | SD General Contractor | — |
#SP-2025-000512 Site / Utility Permit · Excavation FOR THE EXCAVATION AND UNDERPINNING WORK PER APPROVED PLANS. Status: Issued | SD General Contractor | — |
#DP-2025-000354 Demolition Permit · Minor Demolition FOR THE COMPLETE DEMOLITION OF THE SEMI-DETACHED TWO-STORY STRUCTURE BY HAND AND HAND HOLD DEVICES. PEDESTRIAN PROTECTION TO BE IN PLACE PRIOR TO START OF WORK AND TO BE MAINTAINED DURING ALL DEMOLITION ACTIVITIES. *SEPERATE STREETS DEPARTMENT PERMIT REQUIRE FOR CLOSURE OF RIGHT OF WAY. *21 DAY… Status: Completed | Raymond Smith | — |
In Philadelphia, biggest first.