Multifamily General Building, Hvac/Mechanical, Plumbing work permitted June 6, 2025, with 5 permits through September 22, 2026, declaring $10,606,500 of work. Contractor on record: Eastern PLBG & Mech Contr.
Get new commercial permits near 11236 or New York City, free weekly email
Install new boilers for Bay View Houses per plans.
New York City permit records name Eastern PLBG & Mech Contr and Awl Industries Inc as the contractors on this project.
The property owner is included with Pro.
5 permits issued Jun 6 – Sep 22, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jul 6 | #B00488623-S3-BE Boiler Equipment · Initial Permit |
Commercial and multifamily, biggest first.
Install new boilers for Bay View Houses per plans.
Status: Permit Issued
| Eastern PLBG & Mech Contr |
| $2.8M |
| applied Jul 2 | #B00488623-S2-MS Mechanical Systems · Initial Permit Remove seven (7) existing 300 HP 3-pass low pressure steam scotch marine boilers and all associated piping, controls, and ancillary steam equipment as shown in drawings. Replace all associated piping, controls, ancillary steam equipment, etc. as shown. Status: Permit Issued | Awl Industries Inc | $2.4M |
| applied Jul 29 | #B00488623-S5-PL Plumbing · Renewal Permit Without Changes Replace existing instantaneous domestic water heating station and all associated piping, controls, pumps, etc. in conjunction with new mechanical extension as per plans. Replace sump pump. Replace roof drains. Provide new floor drains. Status: Permit Issued | Eastern PLBG & Mech Contr | $683K |
| applied Sep 17 | #B00488623-I1-GC General Construction · Renewal Permit Without Changes Addition of 2 story mechanical/boiler enclosure. Status: Permit Issued | Awl Industries Inc | $2.4M |
| applied Aug 3 | #B00488623-S4-BE Boiler Equipment · Renewal Permit Without Changes Install TEMPORARY boilers Bay View Houses per plans. PAA added scope includes a new temporary above ground fuel oil storage tank and the associated fuel oil piping and fuel oil pump. All equipment and piping will be located outdoors. Status: Permit Issued | Eastern PLBG & Mech Contr | $2.3M |