Get ProEvery project in every city · from $79/mo
Get Promultifamily project · New York City, NY
Multifamily General Building work permitted August 6, 2025, with 2 permits through November 17, 2025, declaring $130,000 of work. Contractor on record: Preserv BLD Restor MGT In.
SELECT EXTERIOR RESTORATION AT THE NORTH ELEVATION INCLUDING MASONRY REBUILDING, MASONRY REPOINTING, WINDOW PERIMETER RESEALING, AND WINDOW SILL PAINTING AS SHOWN ON THE DRAWINGS FILED HEREWITH. NO CHANGE TO OCCUPANCY, USE, OR EGRESS.
New York City permit records name Preserv BLD Restor MGT In as the contractor on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
2 permits issued Aug 6 – Nov 17, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Apr 9 | #M01075425-S1-ST Structural · Initial Permit Filing herewith for exterior facade repair of existing building, including temporary shoring and bracing of dunnage steel supporting a water tank and rooftop units and localized masonry repair of parapet wall as per plans submitted. No change to occupancy |
Commercial and multifamily, biggest first.
Status: Signed-Off
| Preserv BLD Restor MGT In |
| $30K |
| applied Jul 25 | #M01075425-I1-GC General Construction · Renewal Permit Without Changes SELECT EXTERIOR RESTORATION AT THE NORTH ELEVATION INCLUDING MASONRY REBUILDING, MASONRY REPOINTING, WINDOW PERIMETER RESEALING, AND WINDOW SILL PAINTING AS SHOWN ON THE DRAWINGS FILED HEREWITH. NO CHANGE TO OCCUPANCY, USE, OR EGRESS. Status: Signed-Off | Preserv BLD Restor MGT In | $100K |
In New York City, biggest first.