Multifamily General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted September 4, 2025, with 4 permits through November 7, 2025, declaring $308,000 of work. Contractor on record: CNS Construction Inc.
Get new commercial permits near 10014 or New York City, free weekly email
Non-structural partition demolition, bathroom & kitchen fixture removals, new partitions and millwork, new laundry, replace existing wood flooring throughout, new cabinetry and lighting. No change to use, egress or occupancy.
New York City permit records name CNS Construction Inc, Mo Contracting Inc and JMW Plumbing, Inc as the contractors on this project.
The property owner is included with Pro.
4 permits issued Sep 4 – Nov 7, newest first.
| Issued | Permit | Contractor |
|---|
Commercial and multifamily, biggest first.
| Value |
|---|
| applied Oct 27 | #M01172146-S4-EW-SP Sprinklers · Initial Permit Modifications to existing sprinkler system. Status: Permit Issued | Mo Contracting Inc | $3K |
| applied Apr 10 | #M01172146-S2-PL Plumbing · Initial Permit Modifications to plumbing system. Removal of gas range. Status: Signed-Off | JMW Plumbing, Inc | $51K |
| applied Apr 24 | #M01172146-S1-MS Mechanical Systems · Initial Permit Disconnect & relocate existing fan coil unit. Adjust HW piping connection to suite new fan coil unit location. Disconnect & remove portion of existing HW baseboard radiation to accommodate relocated fan coil unit. Adjust hot water piping accordingly. Status: Permit Issued | CNS Construction Inc | $4K |
| applied Apr 1 | #M01172146-I1-GC General Construction · Initial Permit Non-structural partition demolition, bathroom & kitchen fixture removals, new partitions and millwork, new laundry, replace existing wood flooring throughout, new cabinetry and lighting. No change to use, egress or occupancy. Status: Signed-Off | CNS Construction Inc | $250K |