commercial project · New York City, NY
5260 Fieldston Road Bronx, New York City, NY 10471
Commercial Solar work permitted March 20, 2025, declaring $138,600 of work. Contractor on record: Accord Power Inc.
Get a free email when a new permit is filed here
- $139K
- Project value
- 1
- Permit
- Mar 20
- First permit
- 3 days
- Application to issuemedian
What's being built
Installation of 46.2 kw solar energy system on roof. No change of occupancy, use or egress
Who is building at 5260 Fieldston Road Bronx?
New York City permit records name Accord Power Inc as the contractor on this project.
On file for this address
- A contractor phone number
- The property owner
One charge, nothing renews. Refunded in full if the record lacks what’s listed here.
Permits at 5260 Fieldston Road Bronx
1 permit, issued Mar 20.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Mar 17 | #X01191234-I1-SL Solar · Initial Permit Installation of 46.2 kw solar energy system on roof. No change of occupancy, use or egress Status: Signed-Off | Accord Power Inc | $139K |
Other projects in 10471
Commercial and multifamily, biggest first.
- 3869 Palisade Avenue BronxPROJECT CONSISTS OF PARTIAL DEMOLITION AND RECONSTRUCTION OF AN EXISTING NYCDEP PUMPING STATION INCLUDING NEW MECHANICAL, PLUMBING, PROCESS, AND SITE WORK.commercialPlumbing· Civetta Mechanical, LLC$18.9MJul 18
- 4575 Manhattan College Parkway Bronxwork includes per the filed plans remove/replace existing roof membrane and flashing, parapet replacement, remove/replace cracked/spalled masonry units, sealant replacement,…commercialBuilding· Maven Restoration Inc$2.4MFeb 4
- 5700 Arlington Avenue BronxFACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.multifamilyBuilding· Harbor Waterproofing Serv$2.2MJun 1
- 5900 Arlington Avenue BronxFACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.multifamilyBuilding· Harbor Waterproofing Serv$2.2MJul 29
- 5959 Palisade Avenue BronxINTERIOR RENOVATION OF 2ND FLOOR, RESNICK PAVILION, AS SHOWN PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.commercialBuilding, HVAC / Mechanical, Plumbing· Miter Construction Corp$2MMay 8
- 6035 Broadway BronxFacade repairs to include masonry, pointing, lintels, sills, parapet repairs, scrape/prime/paint exposed steel, and caulking. Install roof recovery system, flashing, membrane,…multifamilyBuilding· LCS Restoration Corp$1.9MJul 21
More projects by Accord Power Inc
In New York City, biggest first.
- 12-16 43 Avenue QueensInstallation of 403.845 kw solar energy system Carport in parking lot. No change of occupancy, use or egress.commercialSolar· Accord Power Inc$2.2MFeb 6
- 3018 3 Avenue BronxInstallation of 676.89 kw solar energy system on roof. No change of occupancy, use or egress.commercialSolar· Accord Power Inc$1.9MJun 10
- 101 Myrtle Avenue Staten IslandInstallation of 272.565 kw solar energy system on roof. No change of occupancy, use or egress.commercialSolar· Accord Power Inc$1.6MAug 7
- 535 Morgan Avenue BrooklynInstallation of 312.4 kw solar energy system on roof. No change of occupancy, use or egress.commercialSolar· Accord Power Inc$1.3MJul 23
- 3400 Fort Independence Street BronxInstallation of 95.58 kw solar energy system on roof. No change of occupancy, use or egress.multifamilySolar· Accord Power Inc$749KApr 20
- 74 Bogart Street BrooklynInstallation of 137.340 kw solar energy system on roof. No change of occupancy, use or egress.commercialSolar· Accord Power Inc$558KJul 11