commercial project · New York City, NY
525 East 68 Street Manhattan, New York City, NY 10065
Commercial Fire Protection work permitted April 8, 2025, with 2 permits through April 10, 2025, declaring $128,940 of work. Contractor on record: Sirina Fire Prot Corp.
Get a free email when a new permit is filed here
- $129K
- Project value
- 2
- Permits
- Apr 8
- First permit
- 145 days
- Application to issuemedian
What's being built
L-4 CARDIOLOGY Phase 3: PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE THE PHASE 3, CARDIOLOGY, IN THE EXISTING HOSPITAL BUILDING AS PER PLANS FILED HEREWITH. NO CHANGE TO ZONING, USE, EGRESS OR OCCUPANCY.
Who is building at 525 East 68 Street Manhattan?
New York City permit records name Sirina Fire Prot Corp and Riehm Plumbing Corp as the contractors on this project.
On file for this address
- A contractor phone number
- The property owner
One charge, nothing renews. Refunded in full if the record lacks what’s listed here.
Permits at 525 East 68 Street Manhattan
2 permits issued Apr 8 – Apr 10, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Nov 15 | #M07993476-I1-EW-SP Sprinklers · Initial Permit L-4 CARDIOLOGY Phase 3: PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE THE PHASE 3, CARDIOLOGY, IN THE EXISTING HOSPITAL BUILDING AS PER PLANS FILED HEREWITH. NO CHANGE TO ZONING, USE, EGRESS OR OCCUPANCY. Status: Signed-Off | Sirina Fire Prot Corp | $129K |
| applied Nov 15 | #M07993476-I1-PL Sprinklers · Initial Permit L-4 CARDIOLOGY Phase 3: PLUMBING AND SPRINKLER MODIFICATIONS TO ACCOMMODATE THE PHASE 3, CARDIOLOGY, IN THE EXISTING HOSPITAL BUILDING AS PER PLANS FILED HEREWITH. NO CHANGE TO ZONING, USE, EGRESS OR OCCUPANCY. Status: Signed-Off | Riehm Plumbing Corp | $129K |
Other projects in 10065
Commercial and multifamily, biggest first.
- 854 5 Avenue ManhattanJOB WAS ACCEPTED TO HUB AT CONSULTATION ON 7/18/23. PROPOSED CHANGE OF USE FROM UG 3 & 4 TO UG V & VIII. HORIZONTAL ENLARGEMENT AT 6TH FLOOR & ROOF. INTERIOR AND EXTERIOR…commercialBuilding, Fire protection, HVAC / Mechanical· Donato Plumbing, Inc$28.3MMay 7
- 1233 York Avenue ManhattanMPP 139: FULL DEMOLITION OF (2) TOWER MEMORIAL SLOAN-KETTERING SLOAN HOUSE (20-STORY) & SCHOLARS RESIDENCE (23-STORY) USING MECHANICAL MEANS.commercialDemolition, HVAC / Mechanical· Breeze National Inc$22.2MMay 22
- 809 Madison Avenue ManhattanDevHUB Consultation 7.18.2025 @2pm. Application filed to enlarge building horizontally and vertically.commercialBuilding, HVAC / Mechanical, Plumbing· CM And Associates Const$21MOct 8
- 695 Park Avenue ManhattanDEMOLITION AND INSTALLATION OF DUCTWORK, PIPING, AIR HANDLING UNITS, FAN COIL UNITS, FANS.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Infinity Contracting Serv$17.6MApr 3
- 541 East 68 Street ManhattanSWARMP REPAIR AT GREENBERG PAVILION FACADE, CEILING ABOVE FDR DRIVE, 1ST FL AND PARKING LEVEL INCLUDING REPAIR STEEL DECKING AND CONCRETE, AND PRECAST STONE FACADE AS INDICATED…commercialBuilding· Consigli Construction Co$17.3MJul 22
- 37 East 64 Street ManhattanAPPLICATION FILED FOR NEW PARTITIONS, FLOORING AND CEILING WORK WITHIN APARTMENT HOTEL AS PER PLANS PROVIDED. NO CHANGE TO USE, EGRESS, BULK, OR OCCUPANCY.commercialBuilding· Shawmut Woodworking & Sup$14.3MJan 30
More projects by Sirina Fire Prot Corp
In New York City, biggest first.
- 375 Madison Avenue ManhattanFiling herewith for additions and modifications to existing Mechanical systems and associated ducts and piping for women's and men's washrooms/restrooms.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Sirina Fire Prot Corp$96.4MMay 15
- 375 Madison Avenue ManhattanAlteration-CO for changes in use, occupancy, and egress on floors sub-cellar, cellar, 1, 1M, 2-11, 18, & 19 as part of full building renovation. Changes to overall building…commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Tishman Interiors Corp$74.9MApr 30
- 170 Central Park West ManhattanAlteration Type one for addition as per plans.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Turner Construction Compa$61.9MAug 17
- 140 West 65 Street ManhattanFiling herewith structural partial demolition scope inside garage/parking structure and at the garage/parking structure roof/plaza level which includes a slab cut as per plans.…commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Turner Construction Compa$47.8MMar 26
- 22 Vanderbilt Avenue ManhattanOFFICE DEMO & RENOVATION FOR TENANT SPACE (BAIN & COMPANY) AS PER PLANS FIRLED HEREWITH. NO CHANGES TO EGRESS, USE OR OCCUPANCYcommercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· L&K Partners, Inc$38.9MJan 21
- 1000 5 Avenue ManhattanGREAT HALL GALLERY PACKAGE 2. RENOVATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCYcommercialBuilding, Fire protection, HVAC / Mechanical· Olympic PLBG & HTG SVC In$36.8MApr 23