Get ProEvery project in every city · from $79/mo
Get Procommercial project · New York City, NY
Commercial Fire Protection work permitted October 29, 2025, with 2 permits through October 29, 2025, declaring $42,250 of work. Contractor on record: Preferred Spklr And Mech.
Remove (32) sprinkler heads, Install (33) new sprinkler heads, Relocate (1) sprinkler head and (1) FHC and associated SP/SD piping on the 3rd Floor; Relocate (2) sprinkler heads on the 4th Floor as per plans (Stifel - New Offices & Conference Rooms.)
New York City permit records name Preferred Spklr And Mech as the contractor on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
2 permits issued Oct 29 – Oct 29, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 10 | #M01289977-I1-EW-SP Sprinklers · Initial Permit Remove (32) sprinkler heads, Install (33) new sprinkler heads, Relocate (1) sprinkler head and (1) FHC and associated SP/SD piping on the 3rd Floor; Relocate (2) sprinkler heads on the 4th Floor as per plans (Stifel - New Offices & Conference Rooms.) |
Commercial and multifamily, biggest first.
Status: Signed-Off
| Preferred Spklr And Mech |
| $42.3K |
| applied Oct 10 | #M01289977-I1-EW-SD Standpipe · Initial Permit Remove (32) sprinkler heads, Install (33) new sprinkler heads, Relocate (1) sprinkler head and (1) FHC and associated SP/SD piping on the 3rd Floor; Relocate (2) sprinkler heads on the 4th Floor as per plans (Stifel - New Offices & Conference Rooms.) Status: Signed-Off | Preferred Spklr And Mech | $42.3K |
In New York City, biggest first.