Get ProEvery project in every city · from $79/mo
Get Procommercial project · New York City, NY
Commercial General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted November 19, 2024, with 13 permits through February 13, 2026. Contractor on record: WDF Inc.
Get new commercial permits near 11201 or New York City, free weekly email
Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use, or occupancy.
New York City permit records name WDF Inc, Tutor Perini Corporation and Enclos Corp as the contractors on this project.
The property owner is included with Pro.
13 permits issued Nov 19 – Feb 13, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
| applied Feb 13 | #B00939362-Z9-SC Suspended Scaffold · Initial Permit Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use, or occupancy. Status: Permit Issued | Enclos Corp | — |
| applied Jan 28 | #B00939362-Z4-EW-SP Standpipe · Initial Permit Sprinkler and Standpipe Installation to accommodate the new building. Status: Permit Issued | WDF Inc | — |
| applied Jan 28 | #B00939362-Z4-EW-SD Standpipe · Initial Permit Sprinkler and Standpipe Installation to accommodate the new building. Status: Permit Issued | WDF Inc | — |
| applied May 10 | #B00939362-S3-FO Foundation · Renewal Permit with Changes Construct foundations and footings for the new building as per plans filed herewith. Status: Permit Issued | Tutor Perini Corporation | — |
| applied Apr 30 | #B00939362-S7-PL Plumbing · Initial Permit Install fixtures and piping including medical gases to accommodate the new jail building as per plans filed herewith. Status: Permit Issued | WDF Inc | — |
| applied May 6 | #B00939362-S6-MS Mechanical Systems · Initial Permit Mechanical work to accommodate the new 22 story jail building. Status: Permit Issued | WDF Inc | — |
| applied Jun 21 | #B00939362-S9-PL Plumbing · Renewal Permit Without Changes Install underground plumbing piping to accommodate the new building. Status: Permit Issued | WDF Inc | — |
| applied Feb 15 | #B00939362-S1-SE Support of Excavation · Renewal Permit Without Changes Support of excavation for the proposed new building. Status: Permit Issued | Tutor Perini Corporation | — |
| applied Feb 28 | #B00939362-S5-ST Structural · Renewal Permit Without Changes Filing solely to include concrete for the purpose of Concrete TR2 and TR3 inspections relative to concrete heelblocks indicated in SOE per B00939362-S1. Status: Permit Issued | Tutor Perini Corporation | — |
| applied Mar 31 | #B00939362-I1-GC General Construction · Initial Permit Construction of a new jail with accessory parking, loading support spaces, community space. Status: Permit Issued | Tutor Perini Corporation | — |
| applied Mar 4 | #B00939362-Z2-ST Structural · Initial Permit Structural work for the new 17 story building. Status: Permit Issued | Tutor Perini Corporation | — |
| applied Jan 30 | #B00939362-Z3-PL Plumbing · Initial Permit Installation of incoming services for domestic and fire water services to the the new building and sewer connections. Status: Permit Issued | WDF Inc | — |
| applied Jun 28 | #B00939362-Z1-GC General Construction · Initial Permit Sub-membrane depressurization system for the new building. Status: Permit Issued | Tutor Perini Corporation | — |