commercial project · New York City, NY
20 Hudson Yards Manhattan, New York City, NY 10001
Commercial Fire Protection, Plumbing work permitted March 5, 2025, with 3 permits through March 6, 2025, declaring $9,044,964 of work. Contractor on record: Abco-Peerless Sprklr Corp.
Get a free email when a new permit is filed here
- $9M
- Project value
- 3
- Permits
- Mar 5
- First permit
- 75 days
- Application to issuemedian
What's being built
Modification to existing plumbing systems and fixtures and sprinkler / standpipe systems and installation of new sprinkler heads as per plans filed herewith. 001, 005, 006, 008 C (10M). No change in use, egress or occupancy
Who is building at 20 Hudson Yards Manhattan?
New York City permit records name Abco-Peerless Sprklr Corp and Par Plumbing Co., Inc as the contractors on this project.
On file for this address
- A contractor phone number
- The property owner
One charge, nothing renews. Refunded in full if the record lacks what’s listed here.
Permits at 20 Hudson Yards Manhattan
3 permits issued Mar 5 – Mar 6, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Dec 20 | #M01148054-I1-PL Plumbing · Initial Permit Modification to existing plumbing systems and fixtures and sprinkler / standpipe systems and installation of new sprinkler heads as per plans filed herewith. 001, 005, 006, 008 C (10M). No change in use, egress or occupancy Status: Signed-Off | Par Plumbing Co., Inc | $9M |
| applied Dec 20 | #M01148054-I1-EW-SD Sprinklers · Initial Permit Modification to existing plumbing systems and fixtures and sprinkler / standpipe systems and installation of new sprinkler heads as per plans filed herewith. 001, 005, 006, 008 C (10M). No change in use, egress or occupancy Status: Permit Issued | Abco-Peerless Sprklr Corp | $9M |
| applied Dec 20 | #M01148054-I1-EW-SP Standpipe · Initial Permit Modification to existing plumbing systems and fixtures and sprinkler / standpipe systems and installation of new sprinkler heads as per plans filed herewith. 001, 005, 006, 008 C (10M). No change in use, egress or occupancy Status: Permit Issued | Abco-Peerless Sprklr Corp | $9M |
Other projects in 10001
Commercial and multifamily, biggest first.
- 20 Hudson Yards ManhattanREMOVAL OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.commercialBuilding· Structure Tone, LLC$52.5MJan 3
- 20 Hudson Yards ManhattanModification to existing HVAC systems including installation of commercial cooking and hood/duct system. Commercial kitchen on 5th floor. No change in use, egress or occupancy.commercialHVAC / Mechanical· Structure Tone, LLC$23.1MDec 26
- 11 Pennsylvania Plaza ManhattanGENERAL CONSTRUCTION MODIFICATIONS TAKING PLACE ON THE 15TH AND 16TH FLOORS AS PER DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.commercialBuilding, HVAC / Mechanical$21.9MOct 22
- 30 Hudson Yards ManhattanFiling herewith Interior renovation, construction of non-load bearing partitions, floors, ceilings and doors as per plans. No change to use, egress or occupancy.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Benchmark Builders LLC$20.6MFeb 20
- 66 Hudson Boulevard ManhattanHereby filing to construct interior partitions, ceilings and doors for for office fit out as shown on plans filed herewith. No change to use, occupancy or egress.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· JRM Construction MGMT LLC$20MSep 10
- 30 Hudson Yards ManhattanHEREWITH FILING ARCHITECTURAL RENOVATIONS FOR INTERIOR FITOUT OF 12TH FLR (MARKETING FLR 16) PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Structure Tone, LLC$19.4MFeb 13
More projects by Abco-Peerless Sprklr Corp
In New York City, biggest first.
- 6303 14 Avenue BrooklynNew Building PS 82 K PAA description in commentscommercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Technico Construction$63.4MApr 13
- 13-20 124 Street QueensRenovation of existing school use building including correction to existing Certificate of Occupancy. PAA description in commentscommercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· KG Construction Services$39.3MJul 7
- 22 Vanderbilt Avenue ManhattanOFFICE DEMO & RENOVATION FOR TENANT SPACE (BAIN & COMPANY) AS PER PLANS FIRLED HEREWITH. NO CHANGES TO EGRESS, USE OR OCCUPANCYcommercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· L&K Partners, Inc$38.9MJan 21
- 1120 Amsterdam Avenue ManhattanRenovation/Conversion of dorm suites to fully accessible single/double occupant sleeping rooms, proposed turnstiles and modifications to office/conference/lounge rooms as per…commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Skanska USA Building, Inc$30.4MSep 24
- 575 Exterior Street BronxREMOVAL AND INSTALLATION OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER DRAWINGS FILED HEREWITH. FILED IN CONJUNCTION WTH HUB NB #210179929. (Hub consultation…multifamilyBuilding, Elevator, Fire protection, HVAC / Mechanical, Plumbing· Pavarini Mcgovern LLC$22.3MNov 5
- 375 Madison Avenue ManhattanINTERIOR FIT-OUT. NEW INTERIOR PARTITIONS. NO DEMOLITION. NO CHANGE IN USE, EGRESS, OR OCCUPANCY PROPOSED IN THIS APPLICATION.commercialBuilding, Fire protection, HVAC / Mechanical, Plumbing· Structure Tone, LLC$21.9MSep 10