Commercial General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted June 18, 2025, with 8 permits through June 22, 2026, declaring $31,853,000 of work. Contractor on record: Vanguard Construction And.
Alteration-CO filed for the partial conversion of commercial building to a mixed-use building. Residential conversion proposed on the 8th thru 21st floors only. Refer to comments for additional information.
New York City permit records name Vanguard Construction And, Full Capacity Fire Corp and G.N.T. Mechanical LLC as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
8 permits issued Jun 18 – Jun 22, newest first.
| Issued | Permit |
|---|
Commercial and multifamily, biggest first.
| Contractor |
|---|
| Value |
|---|
| applied Nov 1 | #M01075912-S3-ST Structural · Initial Permit Structural modifications, to include, but not limited to, wall openings, slab infill, and slab openings for future stair. No change in use, egress or occupancy under this application. Status: Permit Issued | Vanguard Construction And | $1.8M |
| applied Jan 29 | #M01075912-S6-EW-SD Standpipe · Initial Permit Modification/additions to existing combined sprinkler/standpipe system, including new automatic fire pump, jockey pump and related piping. Status: Permit Issued | Full Capacity Fire Corp | $975K |
| applied Oct 27 | #M01075912-S7-EW-SD Standpipe · Initial Permit INSTALLATION OF NEW TEMPORARY DRY MANUAL STANDPIPE SYSTEM WITH AIR COMPRESSOR AND SUPERVISORY ALARM SYSTEM FOR EXISTING BUILDING RENOVATION AND PARTIAL RESIDENTIAL CONVERSION AS PER PLANS FILED HEREWITH. Status: Permit Issued | Full Capacity Fire Corp | $120K |
| applied Jan 29 | #M01075912-S6-EW-SP Sprinklers · Initial Permit Modification/additions to existing combined sprinkler/standpipe system, including new automatic fire pump, jockey pump and related piping. Status: Permit Issued | Full Capacity Fire Corp | $975K |
| applied May 27 | #M01075912-Z3-ST Structural · Initial Permit Extent, Sequence, Means and methods for the proposed partial demolition. Refer to comments section for phased scope of work. Status: Permit Issued | Vanguard Construction And | $683K |
| applied Mar 21 | #M01075912-S2-MS Mechanical Systems · Initial Permit Modification/additions to existing HVAC system and related ductwork/piping. No change in use, egress or occupancy under this application. Status: Permit Issued | Vanguard Construction And | $4.8M |
| applied Feb 20 | #M01075912-S5-PL Plumbing · Initial Permit Modification/additions to existing plumbing fixtures and related piping for proposed partial conversion of commercial space to residential use. Status: Permit Issued | G.N.T. Mechanical LLC | $3.9M |
| applied May 28 | #M01075912-I1-GC General Construction · Initial Permit Alteration-CO filed for the partial conversion of commercial building to a mixed-use building. Residential conversion proposed on the 8th thru 21st floors only. Refer to comments for additional information. Status: Permit Issued | Vanguard Construction And | $19.5M |