commercial project · New York City, NY
156 Williams Avenue Brooklyn, New York City, NY 11207
Commercial General Building work permitted December 29, 2025, with 4 permits through August 18, 2026, declaring $794,000 of work. Contractor on record: Verde Electric Corp.
Get a free email when a new permit is filed here
- $794K
- Project value
- 4
- Permits
- Dec 29
- First permit
- 699 days
- Application to issuemedian
What's being built
STRUCTURAL WORK as per plans filed herewith. Concrete foundations for ground mounted 5 MW(22MWh) energy storage system and structural steel framing system for NFPA 15, in outdoor space. no change in use, egress or occupancy
Who is building at 156 Williams Avenue Brooklyn?
New York City permit records name Verde Electric Corp as the contractor on this project.
On file for this address
- A contractor phone number
One charge, nothing renews. Refunded in full if the record lacks what’s listed here.
Permits at 156 Williams Avenue Brooklyn
4 permits issued Dec 29 – Aug 18, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied May 23 | #B01035900-I1-FO Earth Work · Initial Permit STRUCTURAL WORK as per plans filed herewith. Concrete foundations for ground mounted 5 MW(22MWh) energy storage system and structural steel framing system for NFPA 15, in outdoor space. no change in use, egress or occupancy Status: Permit Issued | Verde Electric Corp | $794K |
| applied May 23 | #B01035900-I1-EA General Construction · Initial Permit STRUCTURAL WORK as per plans filed herewith. Concrete foundations for ground mounted 5 MW(22MWh) energy storage system and structural steel framing system for NFPA 15, in outdoor space. no change in use, egress or occupancy Status: Permit Issued | Verde Electric Corp | $794K |
| applied May 23 | #B01035900-I1-GC Foundation · Initial Permit STRUCTURAL WORK as per plans filed herewith. Concrete foundations for ground mounted 5 MW(22MWh) energy storage system and structural steel framing system for NFPA 15, in outdoor space. no change in use, egress or occupancy Status: Permit Issued | Verde Electric Corp | $794K |
| applied May 23 | #B01035900-I1-ST Structural · Initial Permit STRUCTURAL WORK as per plans filed herewith. Concrete foundations for ground mounted 5 MW(22MWh) energy storage system and structural steel framing system for NFPA 15, in outdoor space. no change in use, egress or occupancy Status: Permit Issued | Verde Electric Corp | $794K |
Other projects in 11207
Commercial and multifamily, biggest first.
- 400 Pennsylvania Avenue BrooklynK435-REPLACEMENT OF EXISTING ROOF SYSTEM, EXTERIOR DOORS, BULKHEAD EXTERIOR DOORS, WINDOWS & WINDOW GUARDS. REBUILDING OF PARAPET WALLS & EXTERIOR STAIRS. MASONRY REPAIRS &…commercialBuilding, HVAC / Mechanical, Plumbing· Roma Scaffolding Inc$48.5MOct 6
- 665 New Lots Avenue BrooklynStructural filing for partial demolition of existing building and construction of new building using existing elements as per plans filed. Changes to use, egress, and occupancy…commercialBuilding, Fire protection· Aspro Plumbing Inc$16.8MNov 4
- 2016 Pitkin Avenue BrooklynHEREWITH FILING MECHANICAL MODIFICATIONS IN CONJUNCTION WITH INTERIOR FIT-OUT PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.commercialBuilding, HVAC / Mechanical, Plumbing· Colin Construction Co.Inc$11.3MOct 26
- 2745 Atlantic Avenue BrooklynPROPOSED 14 STORY MIXED USE BUILDINGmultifamilyBuilding, Fire protection, HVAC / Mechanical, Plumbing· Success Developers LLC$10MDec 11
- 247 Williams Avenue BrooklynPerform work associated with the installation of the Battery Energy Storage System at Con Edison's Brownsville Substation. ****See comments section below for a description of the…commercialBuilding· Grace Industries LLC$5.1MNov 14
- 2219 Pitkin Avenue BrooklynREMOVAL & INSTALL ALL WALL, FLOOR & CEILING FINISHES, KITCHEN APPLIANCES & CABINETS, DOORS & FRAMES TO BE DEMOLISHED & REPLACED AS PER PLANS FILED.multifamilyBuilding· A.M.K. Contracting Corp$4.5MDec 18
More projects by Verde Electric Corp
In New York City, biggest first.
- 172 Williams Avenue BrooklynINSTALLATION OF A GRID-TIED BATTERY ENERGY STORAGE SYSTEM AND RELATED INTERCONNECTION EQUIPMENT ON VACANT LOT(S). NO BUILDING CONSTRUCTION. no change in egress, use or occupancy.commercialBuilding· Verde Electric Corp$1MFeb 27
- 178 Williams Avenue BrooklynSTRUCTURAL WORK as per plans filed herewith. Concrete supports for ground mounted 5 MW(22MWh) energy storage system and structural steel framing system for NFPA 15, in outdoor…commercialBuilding· Verde Electric Corp$794KFeb 10
- 434 Riverdale Avenue BrooklynSTRUCTURAL WORK as per plans filed herewith. Concrete supports for energy storage system and structural steel framing system for NFPA 15. no change in use, egress or occupancycommercialBuilding· Verde Electric Corp$794KDec 29
- 145 Hinsdale Street BrooklynSTRUCTURAL WORK as per plans filed herewith. Concrete supports for energy storage system and structural steel framing system for NFPA 15. no change in use, egress or occupancycommercialBuilding· Verde Electric Corp$794KDec 29
- 172 Williams Avenue BrooklynTHE STRUCTURAL WORK AS PER PLANS FILED HEREWITH INCLUDES INSTALLATION OF CONCRETE SUPPORTS FOR GROUND MOUNTED 5MW (22MWh) ENERGY STORAGE SYSTEM AND STRUCTURAL STEEL FRAMING…commercialBuilding· Verde Electric Corp$660KSep 18
- 164 Liberty Avenue Brooklyninstallation of Auxiliary pads in outdoor space. No change in egress, use or occupancy.commercialBuilding· Verde Electric Corp$50KDec 29