Commercial General Building work permitted March 11, 2025, with 2 permits through March 12, 2025, declaring $1,969,800 of work. Contractor on record: P B Contracting Corp.
NYCC, Spitzer School Roof restoration per plans: Install steel dunnage & handrail. Removal/ Replacement/Repairs of roof membrane, concrete pavers, steel metal cladding, insulation, waterproofing, roof drains, atrium ceiling drywall.
New York City permit records name P B Contracting Corp as the contractor on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
2 permits issued Mar 11 – Mar 12, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Aug 23 | #M00904091-I1-ST Structural · Renewal Permit Without Changes NYCC, Spitzer School Roof restoration per plans: Install steel dunnage & handrail. Removal/ Replacement/Repairs of roof membrane, concrete pavers, steel metal cladding, insulation, waterproofing, roof drains, atrium ceiling drywall. |
Commercial and multifamily, biggest first.
Status: Signed-Off
| P B Contracting Corp |
| $2M |
| applied Aug 23 | #M00904091-I1-GC Structural · Renewal Permit Without Changes NYCC, Spitzer School Roof restoration per plans: Install steel dunnage & handrail. Removal/ Replacement/Repairs of roof membrane, concrete pavers, steel metal cladding, insulation, waterproofing, roof drains, atrium ceiling drywall. Status: Signed-Off | P B Contracting Corp | $2M |