Commercial General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted September 25, 2025, with 7 permits through May 19, 2026, declaring $4,849,111 of work. Contractor on record: Richter & Ratner Contract.
Get new commercial permits near 10128 or New York City, free weekly email
PHASE 3.3: Partial int. fitout including dismantling/installation of non-load bearing walls, doors, ceiling, floors, finishes, exterior repairs and glazing. Replace existing windows at 1st & 2nd floors.
New York City permit records name Richter & Ratner Contract, Capitol Fire Sprinkler Co and Universal Plumbing Inc as the contractors on this project.
The property owner is included with Pro.
7 permits issued Sep 25 – May 19, newest first.
| Issued | Permit | Contractor |
|---|
Commercial and multifamily, biggest first.
| Value |
|---|
| applied Apr 9 | #M01130126-S6-EW-SD Standpipe · Initial Permit 3.3 SOUTH: MODIFICATION TO EXISTING STANDPIPE SYSTEM IN CONJUNCTION WITH SPRINKLER APPLICATION # M01130126-S4 Status: Permit Issued | Capitol Fire Sprinkler Co | $100K |
| applied Dec 26 | #M01130126-S4-EW-SP Sprinklers · Initial Permit 3.3 SOUTH: MODIFICATION TO EXISTING SPRINKLER SYSTEM Status: Permit Issued | Capitol Fire Sprinkler Co | $173K |
| applied Dec 26 | #M01130126-S3-PL Plumbing · Initial Permit PHASE 3.3 SOUTH: MODIFY EXISTING SANITARY, VENT, DOMESTIC WATER AND STORM DISTRIBUTION IN CONJUNCTION WITH BUILDING ALTERATION. Status: Signed-Off | Universal Plumbing Inc | $200K |
| applied Dec 27 | #M01130126-S1-ST Structural · Initial Permit PHASE 3.3 SOUTH TOWER: MINOR ALTERATIONS TO EXISTING BUILDING, INCLUDING NEW SLAB OPENINGS AND INFILLS AND NEW OPENINGS IN NON-STRUCTURAL EXTERIOR WALLS. Status: Signed-Off | Richter & Ratner Contract | $697K |
| applied Dec 20 | #M01130126-I1-GC General Construction · Initial Permit PHASE 3.3: Partial int. fitout including dismantling/installation of non-load bearing walls, doors, ceiling, floors, finishes, exterior repairs and glazing. Replace existing windows at 1st & 2nd floors. Status: Signed-Off | Richter & Ratner Contract | $1.9M |
| applied Dec 31 | #M01130126-S2-MS Mechanical Systems · Initial Permit PHASE 3.3 SOUTH: REPLACE EXISTING SOUTH BUILDING DUAL DUCT SYSTEM WITH NEW MULTI ZONE DEDICATED OUTDOOR UNIT W/CHILLED/HW COILS ALONG W/ NEW VAVS & DUCTWORK. DOAS-SC-1 WILL PROVIDE VENTILATION AIR TO ALL OF THE SOUTH BASEMENT THRU 3FLS & PORTIONS OF S4-S Status: Signed-Off | Richter & Ratner Contract | $1.2M |
| applied Sep 5 | #M01130126-S5-GC General Construction · Initial Permit PHASE 3.3 MINOR INTERIOR DEMO WORK AT SOUTH WING INCLUDING DEMOLITION OF CEILINGS AND ABOVE CEILING EQUIPMENT. Status: Signed-Off | Richter & Ratner Contract | $532K |
In New York City, biggest first.